Attachment 4 AF Form 3052 INC 1106.xlsx

Air Force Form XLSX spreadsheet 61 KB Posted

Attached to
LJYC 10-1018, Repair Roof Bldg 282, Warehouse
Solicitation number
FA5685-11-R-0009
Issued by

About this file

AF Form 3052 INC 1106

View the file

Other versions and copies of AF Form 3052

File Revision Posted Attached to
Attachment E - Blank Sample AF Form 3052.xls Revision not stated Robins AFB Paving Multi-Award IDIQ
Attachment 5 - PNQS 24-4829 Airfield Improvements AF Form 3052 - Amendment 0002.xlsx Revision not stated Maxwell AFB - Airfield Repairs - Amendment 0006
31 - AF Form 3052 Cost Estimate Template.xlsx Revision not stated SABER IDIQ
31 - AF Form 3052 Cost Estimate Template.xlsx Revision not stated SABER IDIQ
B6 AF Form 3052 - Construction Cost Estimate.pdf Revision not stated Emergent Requirements Construction IDIQ (Single-Award)
AF Form 3052 (Blank) ReplCath Prot 240026 at Multi Facs -- .xlsx Revision not stated FBNV240026 Replace Cathodic Protection Test Points DMAFB
FBNV240017 - AF Form 3052 Blank.xlsx Revision not stated FA487724R0020 - Upgrade PGS Fire System
Attachment 4 - JUBJ 22 1016 Construct RIC - AF Form 3052.xlsx Revision not stated Construct Research Information Center (Solicitation Amendment 0002)
Attachment 4 - PNQS 24-3992 Replace Localizer Pad - AF Form 3052.xlsx Revision not stated PNQS 24-3992 Replace Localizer Pad (Solicitation Amendment 0001)
05. FBNV230009_AF Form 3052 (Blank).xlsx Revision not stated Solicitation - Repair Command Post Bldg 2300 - DMAFB
B941 Replace AHU AF Form 3052 - Construction Cost Estimate.xlsx Revision not stated Bldg 941 Replace Air Handling Unit 1
AF Form 3052.xlsx Revision not stated BLDG 4868 Additional Electrical Panel for DMAFB
Atch 7 AF Form 3052.xlsx Revision not stated B324 Add Sewer Line, FE Warren AFB, WY
AF Form 3052-Construction Cost Estimate Breakdown (3).xlsx Revision not stated Barnes Center Command Suite Modification Bldg. 832 Gunter Annex (Amendment 0003)
5. AF Form 3052-BLANK.xlsx Revision not stated Replace Swamp Cooler B5045
Copy of Attachment 3 - AF Form 3052-Construction Cost Estimate Breakdown.xlsx Revision not stated Repair Battery Room - Maxwell AFB, AL (Solicitation)
Attachment 4 - PNQS 23-0379 Connect Fire Mains - AF Form 3052.xlsx Revision not stated PNQS 23-0379 Connect Fire Mains Bldgs. 849 & 1143, MAFB & Gunter Annex
17. AF Form 3052 (Blank) - FBNV190002.xlsx Revision not stated Repair and Construct Primary Electric Distribution
Attachment 2.12 - AF Form 3052 Construction Cost Estimate Breakdown Template.xlsx Revision not stated Multiple Award Basic Ordering Agreement for Construction Services at Cannon AFB, NM
Attachment 3 - AF Form 3052-Construction Cost Estimate Breakdown.xlsx Revision not stated Repair Rooms, Building 1410 Gunter
Show all 20

Who attaches AF Form 3052

Other files

File Type Posted
FA5685-11-R-0009-0001 Repair Roof Bldg 282 Warehouse Amendment.doc DOC document
Attachment 1 Specifications.pdf PDF
FA5685-11-R-0009 Repair Roof Bldg 282 Warehouse.doc DOC document
Attachment 5 INCIRLIK INSTRUCTIONS.doc DOC document
Preferred Product List .xls XLS spreadsheet
Attachment 6 WAWF Instructions.doc DOC document
Site Visit Reservation Form LJYC 10-1018.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INC-1101 (Front) TOTAL

CONTRACTORADDRESS{END}{UP}{DOWN 52}~{/ Block;Erase}This is NOT a comprehensive cost estimation macro. The User
{UP 52}{/ Block;Copy}{RIGHT 3}is required to do many of the revisions manually. The User
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE{/ Protection;Disable}{ESC}{UP 53}{DOWN 33}~must be capable of using a spreadsheet with minimum help.
RPR ROOF BLDG 282, WAREHOUSE0.000.00{/ Block;Copy}.{DOWN 52}{RIGHT 5}
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION :{DOWN 52}{RIGHT 12}~~{/ Block;Erase}The cost form is prepared for Quattro Pro version 4.0. The printer
LJYC 101018INCIRLIK AIR BASEAdana,Turkey{RIGHT 12}~{/ Protection;Enable}{RIGHT 1}selected is Canon Laser Printer LPB-4. Hovewer, as the program's
UNIT OFMATERIAL COSTLABOR COST$${DOWN 53}~{DOWN 33}~soft fonts are used, changing a printer should not present problems.
LINEITEMMEASUREQUANTITY$$$$OTHERLINE{/ Protection;Enable}{RIGHT 3}
NOUNITTOTALMANDAYSAVERAGETOTALDIRECTTOTAL{/ Block;Erase}It is possible that, at the first trials, problems with page fitting may
RATECOSTS{DOWN 33}~arise. The User should experiment with the size of the first
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10){LEFT 8}font on the font table.
R E C A P I T U L A T I O N{/ Protection;Enable}
The User is recommended to work in protected mode initially to avoid
1ARCHITECTURAL0.000.000.000.000.000.00

2 MECHANICAL 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL- 0- 0- 0- 0- 0
ARCHITECTURAL0.000.00
1REMOVE EXISTING ROOF PANELS, FLASHING, GUTTERS, DOWNSPOUTS C/W ACCESSORIESSM
2PAINT STEEL TRUSS SECTIONS, EXPOSED AFTER ROOF PANELS REMOVALLS
3PROVIDE AND INSTALL NEW FACTORY PAINTED 0.7MM/50MM 0.5MM METAL SANDWICH PANEL ROOF C/W ACCESSORIESSM
4PROVIDE AND INSTALL NEW FACTORY PAINTED METAL ROOF RIDGELM
5BOTTOM 1.50 MM, TOP 2.00 MM TRANSPARENT PLASTIC ROOF PANELS FOR SKYLIGHTS.SM
6PROVIDE AND INSTALL ANCHORS C/W STEEL SAFETY ROPELS
7PROVIDE AND INSTALL NEW 0.7MM THICK GALVANIZED FACTORY PAINTED METAL FLASHING.LM
8PROVIDE AND INSTALL 2MM FACTORY PAINTED NEW METAL VALLEY RAIN GUTTERS.LM
9PROVIDE AND INSTALL NEW 0.7MM THICK; FACTORY PAINTED METAL DOWNSPOUTS AND GUTTERSLM
10PROVIDE AND INSTALL NEW DOWNSPOUTS FOR SHED SECTION C/W ACCESSORIES AND CONNECTION TO THE MAIN DOWNSPOUT.LS
TOTAL- 0- 0- 0- 0- 0
MECHANICAL- 0- 0- 0
1PROVIDE AND INSTALL CENTRIFUGAL ROOF FANS C/W ACCESSORIESEA
2DISMENTAL AND REINSTALL ROOF HOOD ARCHES C/W NEW ARCHES AND ACCESSORIESEA
3HEAT SENSOR AND SWITCHEA

- 0

- 0- 0- 0
TOTAL- 0- 0- 0- 0- 0

&"Arial,Italic"&8Engineer's Final&"Courier,Regular"&12

&"Arial,Bold"&10CONSTRUCTION COST ESTIMATE BREAKDOWNATTACHMENT 5
FA5685-08-R-0032&"Arial,Bold"&10FOR OFFICIAL USE ONLY

SHEET NO. &P OF &N

&"Times New Roman,Bold"&10Form INC-1101, Construction Cost Estimate Breakdown. (Rev 2, Nov 2009) &"Arial,Bold"&10FOR OFFICIAL USE ONLY&"Courier,Regular"&12

INC-1101 (Back) TOTAL

INSTRUCTIONS FOR COMPLETING Form INC-1101

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to
permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples : square yards - SY, cubic yards - CY, square
feet - SF, linear feet - LF, board feet - BF, each - EA, pound -LB).
Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be
funished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract
will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in Col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1.
Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract
and of significant dollar value.

Col 10 Line Total. Self-explanatory.

NOTE: In addition to the other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last
page as follows.
TOTAL MATERIAL COSTS$0.00
-------------------------------
TOTAL LABOR COSTS$0.00
-------------------------------
TOTAL OTHER DIRECT COSTS$0.00
-------------------------------
TOTAL COSTS$0.00
-------------------------------
OVERHEAD%$0.00
-------------------------------
SUBTOTAL$0.00
-------------------------------
PROFIT%$0.00
-------------------------------
TOTAL PRICE$0.00
DATE :FIRM NAME
-----------------------------------------------------------------
TITLE:BY
---------------------------------------------------------------------------------------------------------------------------

INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and
estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from
this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data
(see ASPR 3-807.3(e) and 3-807.4).
2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this
form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and
analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of
a. The existing, verifiable data.
b. The judgmental factors applied in projecting from known data to the estimate, and
c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate),
and made available to the contracting officer or his authorized representative upon request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the
purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate
evaluation of such cost or pricing data, along with the computations and projections used herein. This right may be exercised in connection
with any negotiations prior to contract award.