AF Form 3052.xlsx

XLSX spreadsheet 30 KB Posted

Attached to
BLDG 4868 Additional Electrical Panel for DMAFB
Solicitation number
24QA026
Issued by

About this file

This document appears to be an AF Form 3052 - an IGE Design-Build Cost Estimate Breakdown for a federal contract opportunity. The contract is for furnishing labor, equipment, and materials to design and install a new 200 Amp, 120/208-volt, three phase Panel Board in Building 4868 at Davis-Monthan AFB, AZ. The solicitation number is 24QA026. Key details include:

The overall proposed total contract price is $0. The contract will be awarded by the Department of the Air Force Air Combat Command. A site visit is scheduled for July 25, 2024, and Expressions of Interest Letters are due by July 10, 2024 at 1:00 PM local time. The contract will involve design, construction, and installation work. The cost estimate breakdown provides detailed labor hours and material costs across various divisions of work including electrical, concrete, and earthwork.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF 3052 IGE

DESIGN-BUILD COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR(WORK TO BE PERFORMED)Additional Electrical Panel for Building 4868PROPOSED TOTAL CONTRACT PRICE0
PURCHASE REQUEST NUMBERPROJECT NUMBERFBNV240023WORK LOCATIONDAVIS-MONTHAN AFB, AZ 85707
LINEUNIT OFMATERIAL COSTLABOR COSTDIRECTLINEBare Costs Per Labor-hour
NO.ITEMMEASUREQUANTITYUNITTOTALMANHOURSRATETOTALCOSTSTOTALCrew CodeCrewEquipmentLabour-hours
SUMMARY
1SUBTOTAL DIVISION 01 GENERAL CONDITIONS0.000.000.000.000.00
2SUBTOTAL DIVISION 03 CONCRETE0.000.000.000.000.00
3DIVISION SPECIALTIES 10 FALL PROTECTION0.000.000.000.000.00
4SUBTOTAL DIVISION 26 ELECTRICAL0.000.000.000.000.00
5SUBTOTAL DIVISION 31 EARTHWORK0.000.000.000.000.00
LINE TOTALS OVERALL0.000.000.000.000.00
OVERHEAD TOTAL OVERALL (10%)0.00
SUBTOTAL OVERALL W/ OVERHEAD0.00
PROFIT TOTAL OVERALL (10%)0.00
SUBTOTAL OVERALL W/ OVERHEAD AND PROFIT0.00
TAX OVERALL 3.97% (6.11% of 65%)0.00
BOND OVERALL (2.0%)0.00
TOTAL OVERALL PROJECT PRICE0.000
DATE:21-Mar-24FIRM NAME:Davis-Monthan AFB
TITLE:PROJECT MANAGERBY:
DIVISION 01 GENERAL CONDITIONS
1
2
3
4
5
6
7
8A-3A
9A-6
10A-5

SUBTOTAL DIVISION 01 GENERAL CONDITIONS 0.00 0.00 0.00 0.00 0.00

DIVISION 02 EXISTING CONDITIONS
SUBTOTAL DIVISION 02 EXISTING CONDITIONS0.000.000.000.000.00
DIVISION 03 CONCRETE
12
12
12
12

SUBTOTAL DIVISION 03 CONCRETE 0.00 0.00 0.00 0.00 0.00

DIVISION 10 SPECIALTIES Fall Protection

SUBTOTAL DIVISION 10 SPECIALTIES 0.00 0.00 0.00 0.00 0.00

DIVISION 26 ELECTRICAL
Elec$ - 032
Elec$ - 016
Elec16
Elec20
Elec1
Elec1
Elec1.5
Elec0.04
Elec1
Elec1
Elec1.1
Elec
Inspector
Elec$ - 016
Elec$ - 016

SUBTOTAL DIVISION 26 ELECTRICAL 0.00 0.00 0.00 0.00 0.00

DIVISION 31 EARTHWORK
$ 27.6224
$ 27.6224
$ 27.6224
$ 27.6224

SUBTOTAL DIVISION 31 EARTHWORK 0.00 0.00 0.00 0.00 0.00

AF Form 3052 (Computer Generated) *FOR OFFICIAL USE ONLY* PAGE &P OF &N

Construction Schedule

Construction Schedule
NTP/Contract Award
Project Mob
Blue Stake0
Survey Pole locations0
Shop Drawing 1 Submittal
Government Review0
Ordering LPS Materials (Poles, etc.)60
Digging Notification0
Foundation Digging0
Rebar Cage Setting0
Concrete in drive way at0
Concrete Cure Time028 days set include total duration time
Electrical/Grounding/SPD Survey0
Electrical Review of SPD0
Grounding Welds0
Ground Rods0
Arrester installation0
Air Terminal Installation0
Misc. Electrical0
Pre Final Inspection0
Testing UL0
3rd Party Inspection0
Final Inspection0
Close out0
Total Working Days:0
Calendar Days:48Includes Lag time for Material (48 days)
Max. Calendar days

Design Sch

NTP/Contract Award10
Project Mob14
Charrette/Field Investigation4
Charrette Report Submission18
Government Review14
Charrette Review Meeting1
35% Conceptual Design21
Government Review14
35% Design Review Meeting1
Government Review14
65% Design Submission21
Government Review14
65% Design Review Meeting1
95% Design Submission14
Government Review14
95% Design Review Meeting1

Calendar Days: 176

File details come from the government source that posted it. Updated .