The AF Form 3052 is a Construction Cost Estimate Breakdown template used for detailed cost projection and analysis in federal construction contracting. This blank form allows contractors to itemize costs across multiple categories including material costs, labor costs, manhours, average rates, and other direct costs, with columns for line-by-line breakdown of project expenses. The form includes instructions for completing each column, emphasizing the need for granular cost documentation, and provides space for calculating total material costs, labor costs, overhead, profit, bonding, and final total price. The instructions also outline the contractor's obligation to provide verifiable cost data and grant the government the right to examine supporting documentation for cost verification purposes.

View the file

Other files for this federal contract opportunity

Other files attached to Emergent Requirements Construction IDIQ (Single-Award), newest first.
File Type Posted
B6 Task Order Proposal Coversheet (Template).docx DOCX document
B4 WD MO20250089 Mod 8_20250613.pdf PDF
Solicitation - W50S8K25RA002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT

[4]

TOTAL

[5]

MANHOURS

[6]

AVERAGE

RATE

[7]

TOTAL [8]

1 $ - $ - $ - -$ 2 $ - $ - $ - -$ 3 $ - $ - $ - -$ 4 $ - $ - $ - -$ 5 $ - $ - $ - -$ 6 $ - $ - $ - -$ 7 $ - $ - $ - -$ 8 $ - $ - $ - -$ 9 $ - $ - $ - -$

10 $ - $ - $ - -$ 11 $ - $ - $ - -$ 12 $ - $ - $ - -$ 13 $ - $ - $ - -$ 14 $ - $ - $ - -$ 15 $ - $ - $ - -$ 16 $ - $ - $ - -$ 17 $ - $ - $ - -$ 18 $ - $ - $ - -$ 19 $ - $ - $ - -$ 20 $ - $ - $ - -$ 21 $ - $ - $ - -$ 22 $ - $ - $ - -$ 23 $ - $ - $ - -$ 24 $ - $ - $ - -$ 25 $ - $ - $ - -$ 26 $ - $ - $ - -$ 27 $ - $ - $ - -$ 28 $ - $ - $ - -$ 29 $ - $ - $ - -$ 30 $ - $ - $ - -$ 31 $ - $ - $ - -$ 32 $ - $ - $ - -$ 33 $ - $ - $ - -$ 34 $ - $ - $ - -$ 35 $ - $ - $ - -$

OTHER

DIRECT

COSTS

[9]

LABOR COSTS

LINE

NO.

MATERIAL COSTS

ITEM [1]

UNIT OF

MEASURE

[2]

QUANTITY

[3]

$0.00 CONTRACT FOR (Work to be performed ):

PURCHASE REQUEST NUMBER: PROJECT NUMBER: WORK LOCATION:

LINE TOTAL

[10]

CONSTRUCTION COST ESTIMATE BREAKDOWN OMB NO 9704-0193

Expires 31 October 1989

CONTRACTOR: ADDRESS:

PROPOSED TOTAL CONTRACT PRICE

AF Form 3052, JAN 88 (PREVIOUS EDITION IS OBSOLETE) FOR OFFICIAL USE ONLY

TOTAL MATERIAL COSTS

TOTAL LABOR COSTS

TOTAL OTHER DIRECT COSTS

TOTAL DIRECT COSTS

OVERHEAD

SUBTOTAL

PROFIT

SUBTOTAL

BONDING

TOTAL PRICE

DATE FIRM NAME

TITLE BY

a. The existing, verifiable data.

b. The Judgmental factors applied in projecting from known data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

1. The purpose of this form is to provide a standard format by which the offeror submits to the government a summary of incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a project resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3-807.4) .

2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and analysis in the light of of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of:

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computation and projections used therein. This right may be exercised in connection with any negotiations prior to the contract award.

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract and of significant dollar value.

Col 10 Line Total. Self-explanatory.

NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows.

Col 2 Unit of Measure. Description of the units in wich each item is to be estimated (examples-square yards-SY, cubic yards-CY, square feet-SF, linear feet- LF, board feet-BF, each-EA, pound-LB) .

Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column2). Items and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost..

INSTRUCTIONS FOR COMPLETING AF FORM 3052

INSTRUCTIONS TO OFFERORS

(Reverse of AF Form 3052, Jan 88) FOR OFFICIAL USE ONLY