This is Addendum 4 to an Invitation for Bids (IFB) issued by the Texas Military Department for construction services at Ellington Field in Houston, Texas. The project requires contractors to extend eight existing concrete barrier access roads to provide adequate turn radius for maintenance vehicles and mobile crane operations. Work includes demolition of damaged concrete sections, excavation, soil stabilization, and construction of six-inch-thick, 4000 PSI reinforced concrete pavement with proper drainage and tie-ins to existing grades. The addendum extends the original bid due date to June 8, 2026, at 2:00 p.m. Central Time and provides a comprehensive Question and Answer document addressing 81 contractor inquiries regarding specifications, site conditions, logistics, and construction requirements. The original mandatory site visit dates were April 14 or 16, 2026, with written questions due by April 23, 2026. The successful contractor must demonstrate at least five years of experience in similar pavement work and provide a qualified superintendent with five years of general contractor experience, Quality Check certification, and OSHA 30-hour certification on-site during all construction phases.

Construction shall comply with multiple governing standards including UFC 3-250-01, UFC 3-201-01, UFGS 32 13 13.06, ACI 318, ACI 330R, TxDOT Standard Specifications, and FAA AC 150/5320-6, with the most stringent requirement prevailing when conflicts exist. The contractor is responsible for all site verification, GPR and utility locating prior to excavation, removal and proper disposal of demolition spoils, restoration of all disturbed areas with topsoil and sod, and adherence to FAA Foreign Object Debris (FOD) control protocols. Contractors must utilize the government-designated Projectmates project management software at a monthly cost of $125 and a one-time setup fee of $750. All personnel working on the flightline require background checks and badging, with escort training costing $16 per badge and taking approximately three hours; employees required daily on-site must obtain badges. A Historically Underutilized Business (HUB) Subcontracting Plan is mandatory. The contract is firm fixed price with no liquidated damages provisions, no Buy American requirements, and no specific budget disclosure; contractors shall assume runway closures will be coordinated four to five weeks in advance and that only one runway may be closed at a time.

View the file

Other files

File Type Posted
ESBD_452864_1780091827962_Attachment G.5 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_452864_1779205491588_Addendum 2 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1777473605426_Addendum 1 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1779913011683_Addendum 3 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1780322077414_Addendum 5 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1774290608978_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_452864_1774290857018_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_452864_1774290974494_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_452864_1774290754031_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_452864_1774290899410_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_452864_1774290933038_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_452864_1774290960900_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_452864_1774290554718_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_452864_1774290870767_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_452864_1774290993298_ATE420~1.PDF PDF
ESBD_452864_1774290799347_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_452864_1774291008049_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_452864_1774290721468_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_452864_1774290768389_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_452864_1774291105912_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (05OCT25).pdf PDF
ESBD_452864_1774290690863_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_452864_1774290829874_ATF409~1.PDF PDF
ESBD_452864_1774290574288_ATTACHMENT G.2 Application for Texas Identification Number #_AP_152.pdf PDF
ESBD_452864_1774290945955_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_452864_1774290920126_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_452864_1774290843236_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_452864_1774290592459_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 7.pdf PDF
ESBD_452864_1774291027426_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_452864_1774291122889_ATTACHMENT G.Z - Example of Contractor Cost Estimate 2026.pdf PDF
ESBD_452864_1774290885606_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_452864_1774290623533_ATTACHMENT G.6 FAA Form 7460-1.pdf PDF
ESBD_452864_1774290638971_ATTACHMENT G.7 Location Photo Aids.pdf PDF
ESBD_452864_1774291073896_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_452864_1774290738406_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_452864_1774290786162_ATE180~1.PDF PDF
ESBD_452864_1774290813335_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_452864_1774290705618_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_452864_1774291060898_ATBB18~1.PDF PDF
ESBD_452864_1774291091775_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_452864_1774291046904_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_452864_1774290672414_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_452864_1774290518021_TMD25-ANG-WJ-24150011 EXTEND BARRIER ACCESS ROADS ELLINGTON AFB.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM OF SOLICITATION

1. SOLICITATION NO.

TMD25-ANG-WJ-24150011

2. ADDENDUM NO.

3. EFFECTIVE DATE

05/29/2026

4. ISSUED BY

Texas MilitaryDepartment 2200 W. 35th Street Austin, Texas 78703

5. NAME AND ADDRESS OF OFFEROR

6. The above numbered solicitation is an addendum as set forth in Item 4. The hour and date specified for receipt of Bids X is extended, is not extended.

Bidders should acknowledge receipt of this addendum prior to the hour and date specified in the solicitation or, by one of the following methods:

(a) By completing Items 5 and 8, and returning 1 copy of the addendum; (b) By acknowledging receipt of this addendum on each copy of the bid submitted; or (c) By separate letter or e-mail which includes a reference to the solicitation and addendum numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF BIDS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID. If by virtue of this addendum, you desire to change a bid already submitted, such change may be made by e-mail or letter, provided each e-mail or letter makes reference to the solicitation and this addendum, and is received prior to the opening hour and date specified.

7. DESCRIPTION OF ADDENDUM

TMD has issued this Addendum 4 in order to post the Question and Answer document and Attachment G.5 HUB Subcontracting Plan (HSP) for this Project and to extend the bid response due date.

New dates and Times:

06/8/2026 2:00 P.M. Deadline for TMD to receive Bids

Except as provided herein, all terms and conditions of the solicitation, as heretofore changed, remain unchanged and in full force and effect.

8a. NAME AND TITLE OF SIGNER (Type or Print)

8b. OFFEROR

(Signature of Person Authorized to Sign) Date Signed

TEXAS MILITARY DEPARTMENT

INVITATION FOR BIDS (IFB) #

TMD25-ANG-WJ-24150011 EXTEND BARRIER ACCESS ROADS ELLINGTON AFB

Question and Answer Document

1. The bid documents reference the contractor is to follow various applicable codes and standards in section C.4.2 During site meeting we were told we were to follow TxDOT specifications.

Can we please get clarification on what specifications and standards we are to follow?

a. Please provide specification package.

b. Please clarify the following:

i. Specifications for concrete. Any retardants? Mix design? Depth? Rebar? Strength?

ii. Specifications for base material. Compaction? Material selection? Depth?

iii. Specifications for expansion and control joints.

iv. Specifications for silt fence and erosion control.

v. Specifications for any stabilization.

vi. Maximum and minimum slopes on concrete.

vii. Turning radius for maintenance vehicles.

Answer:

The Contractor shall comply with all applicable codes and standards identified in Section C.2 of the solicitation. The contractor shall comply with all the contracted specifications and regulations within the scope and contract. The governing framework for this project shall consist of but not limited to:

• UFC 3-250-01, UFC 3-201-01, UFC 3-260-02 (airfield-adjacent work)

• WBDG and UFGS (32 13 13.06)

• ACI 318, ACI 330R

• TxDOT Standard Specifications (Items 360, 421, 247, 260, 275, 506)

• FAA AC 150/5320-6 (as applicable to airfield operations)

Where conflicts exist, the most stringent requirement shall govern.

Specifications for concrete? : 4,000 PSI @28 days. Concrete to comply with contract specification and regulation.

• Thickness: 6 inches

Reinforcement: Contractor to submit reinforcement drawings to government prior to purchase and installation. (#4 bars @ 12–15” OCEW – Grade 60). Comply with contract specifications and regulations.

Any retardants? Yes. Comply with contract specifications and regulations. Contractor to submit to

Government for review and approval.

Mix design? Comply with contract specifications and regulations. Contractor to submit to

Government for review and approval.

Depth? Follow Contractor to match existing depth. Ensure top finish grade is consistent and level.

ii. Specifications for base material – Contractor to comply with Contract specifications and regulation. Contractor to submit to Government for review and approval.

Compaction? 95% compaction minimum per (ASTM D698), UFC and TXDOT.

Material selection? Contractor to comply with Contract specifications and regulation. Contractor to submit to Government for review and approval.

Depth? The Contractor shall field verify existing concrete depth and match existing elevations and tie-ins; however, the new concrete pavement shall not be less than 6 inches thick.

The pavement section, base, subbase, subgrade preparation, reinforcement, jointing, drainage, and testing shall comply with but not limited with: UFC 3-250-01, UFC 3-201-01, UFGS 32 13 13.06, ACI 318, ACI 330R, TxDOT Item 360, TxDOT Item 421, TxDOT Item 247, TxDOT Item 260, and TxDOT Item 275.

The intent of the project is to construct reinforced concrete pavement extensions with proper tie-ins to existing pavement. The typical section shall consist of 6-inch reinforced concrete pavement over a 6-inch stabilized base, compacted to 95% Standard Proctor. Reinforcement shall be #4 bars at 12-15” O.C. each way. Joint spacing, base preparation, and subgrade compaction shall follow the requirements outlined above. Contractor shall field verify all existing conditions and ensure proper drainage and tie-ins.

Work shall comply with:

• UFC 3-250-01 – Pavement Design

• UFC 3-270-01 – Pavement Maintenance

• TxDOT Standard Specifications (Items 247, 360, etc.)

• ACI 301 / ACI 330

• Applicable FAA AC 150/5370-10 (if within airfield influence)

See Typical Concrete Roadway Pavement Section Detail (For Reference Only)

iii. Specifications for expansion and control joints. Contractor is responsible for constructing.

Designing, implementing, tie-ins, expansion joints and control joints.

• Control joints: 10–12 ft spacing

• Expansion joints at tie-ins. Per UFC 3-250-04 and TxDOT Item 360

Contractor shall comply with but not limited with: UFC 3-250-01, UFC 3-201-01, UFGS 32 13

13.06, ACI 318, ACI 330R, TxDOT Item 360, TxDOT Item 421, TxDOT Item 247, TxDOT Item

260, and TxDOT Item 275. Where conflicts exist, the most stringent requirement shall govern.

iv. Specifications for silt fence and erosion control.

v. Specifications for any stabilization. Contractor shall comply with specifications. Required where subgrade fails proof-roll, TxDOT Item 260 (lime) or 275 (cement). UFC 3-250-11 Soil

Stabilization for Pavements and UFGS 32 113.13 Lime Treated Subgrade, UFGS 32 11 13.16

Stabilized subgrade and UFC 3-250-01. Where conflicts exist, the most stringent requirement shall govern.

vi. Maximum and minimum slopes on concrete.

The Contractor shall design and construct all pavement grades, slopes, and elevations in accordance with UFC 3-201-01 (Civil Engineering) and UFC 3-250-01 (Pavement Design) as published through the WBDG.

At a minimum, the Contractor shall:

• Provide positive drainage across all new pavement surfaces

• Maintain a minimum 1.5%–2% cross slope, unless otherwise justified and approved

• Ensure all elevations properly tie into existing grades without creating ponding, low spots, or abrupt transitions

• Account for existing site conditions, including known drainage deficiencies, and not rely on existing pavement performance

The Contractor is solely responsible for:

• Field verification of existing elevations and drainage patterns

• Development of grading design necessary to meet UFC performance requirements

• Ensuring the finished pavement is free of standing water and performs as intended

Failure to achieve proper drainage and grading shall require corrective action at no additional cost to the Government.

vii. Turning radius for maintenance vehicles.

Contractor shall construct based on:

• Maintenance trucks

• Mobile crane loading

The Contractor shall design and construct all pavement geometry, including turning radii and maneuvering areas, to safely accommodate maintenance vehicles and mobile crane operations.

Thickened edge where required.

Design shall be based on the most restrictive vehicle expected and shall comply with:

• UFC 3-250-01 and UFC 3-201-01 (WBDG)

• UFC 3-260-02 (airfield-adjacent operations, where applicable)

• AASHTO Green Book (latest edition) for vehicle turning templates

• TxDOT Roadway Design Manual and applicable standard specifications

At a minimum, the Contractor shall design for:

• Standard maintenance trucks and pickup vehicles

• Equipment required to service barrier systems

• Mobile crane operations, including turning, positioning, and load distribution effects.

compliance with:

• UFC 3-250-01

• ACI 330R

• TxDOT Item 360 and Item 247

2. C4.1.J states that Contractor must provide a qualified superintendent with five years of experience as a general contractor on pavement work, Quality Check (QC) qualified, OSHA 30 hrs. to be onsite during all phases of work. Can you please clarify if superintendent needs to have any specific quality check certifications?

The superintendent must demonstrate experience in:

• Pavement construction

• Quality control implementation

• TxDOT or equivalent QC processes

The superintendent shall be competent personnel and will be the POC for the field. The

Government reserves the right to reject unqualified personnel.

3. From page 37-E.8.2.D Please clarify what you guys require for biographical information.

Answer: Short history of your company

4. On E.8.2. E it states The Respondent must specifically address, within its response, the following requests for information as detailed throughout this solicitation. TMD has endeavored to include a complete listing of such submittal requests; however, in the event

TMD omitted a requirement, Respondent is responsible for ensuring that all such information is included within its response. Can we verify that contractor is not responsible for including information that was not clearly requested in the RFP documents.

Answer: Respondent will not be penalized for information not included in response if it is not specifically requested.

5. Please confirm contractor is to perform GPR in work areas prior to digging.

Answer:

Yes. Contractor shall perform GPR and utility locating prior to excavation. Contractor to submit result to the Government.

6. Please confirm contractor does not need to haul earthwork spoils out of site. They can be left on site and graded.

Answer: No. The spoils need to be removed unless the something is worked out with the Houston

Airport System to fill and grade current low spots in need of repair. It is discouraged to leave on site as to not negatively change the drainage of in the barrier locations.

7. Please confirm contractor will not be responsible for resod any damaged areas during construction.

Answer: Contractor shall restore all disturbed areas, including topsoil and sod. Any existing utility damaged is the contractor responsibility. Contractor to submit material submittal for Sodding and topsoil prior to purchase.

8. Bid documents state that contractors are responsible for positive drainage on new barrier roads.

During walkthrough we discovered that existing barrier roads that are to remain are already holding water. Contractor will not be able to get positive drainage on existing barrier roads that are to remain. Would it be possible to demo all existing barrier roads back to runway transition and regrade for positive drainage? If barrier roads are demo back to runway transition can you guys advise on how many inches we are to raise new installations for positive drainage?

Answer:

The photo and drawing are for reference only. The contractor is responsible for field verification.

The Contractor shall include demolition and reconstruction at the following identified locations

(see attachments/annotated photos):

• Low point areas exhibiting standing water / ponding

• Sections with visible cracking, settlement, or edge failure

• Tie-in zones where existing pavement prevents achieving required drainage slopes

At these locations, the Contractor shall:

• Perform full-depth removal to the nearest joint or as required to reach stable subgrade

• Reconstruct pavement section in accordance with:

o UFC 3-250-01 o UFC 3-201-01 o UFGS 32 13 13.06 o TxDOT Items 360, 421, and 247

• Regrade to achieve positive drainage (minimum 1.5%–2% slope) within reconstructed areas

The Contractor shall:

• Determine required elevation adjustments based on field conditions

• Ensure proper tie-in to runway transitions and existing grades

• Avoid abrupt grade changes or impacts to adjacent operations

Contractor Responsibility

The Contractor is responsible for:

• Verifying all identified locations prior to construction

• Extending demolition limits as necessary to achieve stable subgrade and proper drainage within approved limits

• Providing a grading plan demonstrating compliance with UFC drainage requirements

Failure to address drainage deficiencies within the reconstructed areas shall require correction at no additional cost to the Government.

The identified locations represent minimum required areas for reconstruction. The Contractor shall include sufficient scope in the bid to address all visibly distressed and drainage-deficient areas within these limits.

9. During site walk it was discovered that limits of concrete demo in bid documents do not match existing conditions onsite. More concrete is damaged/cracked/spalling/missing than what is depicted on bid documents drawing scope. Please reference runway specific RFI below. Can the demo limits be expanded/modified in the bid documents? Can scope be changed to demo.

See above.

10. Excel estimate sheet in bid documents states that contractors are responsible to install adequate turn radius for maintenance vehicles. Can you please provide turn radius requirements and specifications? Bid documents photos show some turning radius to remain as is. Please confirm if existing turning radius are to be demo and repoured to meet specifications.

Answer: See above responses.

11. Please clarify if contractor will have to have personnel badged to work in Ellington Airport.

a. Any badging costs? No cost for Military, but Per Houston airport systems There is $16 per badge for all trained escorts. Training is conducted by airport operations and takes approximately 3 hours. All can attend training but only leads and escorts will receive badges.

b. Any training is needed? Cost and time allotted to training? Yes. Contractor to ensure and comply with FAA guidelines, Houston Airport Systems, Air Force Regulations as it relates to FOD control and debris.

c. Background Checks? Required.

d. Any other requirements for badging. Required. Whichever contractor wins the contractor will need to submit all workers to the Government for review and approval and investigation.

e. Does every employee need to be badged or just superintendent? All.

Concrete mixer drivers, haul trucks will be escorted and will not require an badge. All drivers vehicles will be searched. Employees that will be working daily will required background checks and badging.

Answer:

12. Please provide a site plan for access and routing.

Answer: Map overview is attached. Contractor utilizes the maps included in SOW. Whichever contractor wins the bid will coordinate with the government regarding routing. For bidding purposes contractor shall assume for the

13. During sitewalk we were escorted by military personnel. Personnel was in constant radio communication with airport operations and tower. Please confirm we will have a full time client provided escort to handle radio communication with airport operations and tower during all phases of construction.

This is a military project so the military will provide an escort if necessary. Construction workers may be left on site with no escort if lead is given a briefing and there is no movement from the work site. All vehicle movement to and from the work site requires an escort.

14. Runway 4 was shutdown during site walk. Is contractor to assume Runway 4 will be shutdown during construction or are we to assume we will be working in an active runway?

Answer:

Construction in the safety area of an open runway is prohibited. The runway will require a closure during construction. The runway will need to be made safe and in compliance before opening.

As of now the runway 4 is shutdown, Contractor shall assume work will occur in an active airfield environment unless otherwise directed.

Runway 4/22 is scheduled to be closed until mid-October. Construction is only permitted in closed areas or out of the safety area of the Runways.

15. Please confirm depth of existing concrete and base we are to demo?

Answer: See SOW.

16. Will contractors have to go through any training or certifications to work in runways? If so, please provide cost for training/certifications and time needed for training.

Answer:

There is no charge for training except $16 per badge for all trained escorts. Training is conducted by airport operations and takes approximately 3 hours. All can attend training but only leads and escorts will receive badges.

17. Will contractors have to purchase licenses to any software for project management? Please provide costs associated with this.

Answer:

Yes. Please SOW. The software is called Projectmates. The Contractor shall utilize the

Government-designated project management software, Projectmates, for all project administration, documentation, and communications with the Project Manager and Government stakeholders.

Use of Projectmates shall be mandatory for, but not limited to, the following:

• Requests for Information (RFIs)

• Submittals and material approval workflows

• Project schedules and schedule updates

• Meeting minutes and action items

• Cost proposals, modifications, and pay applications

• Daily reports and field documentation

• Quality control and testing reports

• Correspondence and document tracking

Email communications shall be limited to notifications only; all official project records and approvals shall be maintained within Projectmates. The Contractor shall be responsible for the

Projectmates monthly licensing fee of $125 per project and a one-time system setup fee of

$750. Coordination and account setup shall be completed with the Project Manager at project startup an additional cost are with the Contractor and Projectmates Company.

18. Will any scheduling software be required? Can contractor provide any scheduling requirements on standard Microsoft projects?

Answer: See response to questions 17.

19. Please confirm intent is to have barrier road be 12’ wide.

Answer: Yes. Contractor to field verify and match existing road width.

20. Please advise on how wide the access road to the pits needs to be? From site meeting it appeared the intent was 20’ wide.

Answer: The barrier extension road is 12ft wide. Contractor to field verify.

21. Please advise if there is any minority or SBE goals on this project.

Answer: See Attachment G.5 HUB Subcontracting Plan (HSP) (required for response submission)

22. Please advise if there is any buy American Standard requirements on this job.

Answer: no there is not

23. Is there any liquidated damages on this project?

Answer: no there is not

24. Please provide expected completion date.

Answer: Respondent is responsible for estimating their completion time and annotating that on

ATTACHMENT G.4 Mandatory Pricing Schedule

Runway Specific Questions

25. Runway 17 North -West Side

a. During site visit we discovered more damaged concrete that needs to be demo. Please modify limits of demo or modify replacing entire barrier road from runway transition.

Access to pit also needs to be added.

Answer:

RW 17 North (Controlled) West Side (See Attachment Visual Aid for reference):

o Sawcut, breakout, and remove existing concrete sidewalk section, approximately 12

FT L x 15 FT W. Reconstruct and pour section. Tie into existing pavement smoothly.

o Sawcut, breakout, and remove existing concrete pavement section, approximately

50 FT L x 12 FT W, as shown in yellow on the map. Reconstruct and pour section.

o Haul off and legally dispose of all demolition debris and waste materials.

o Construct new concrete driveway extension, approximately 110 FT L x 12 FT W.

o Stabilize as required o Provide and install 6-inch thick, 4,000 PSI concrete pavement.

o Dowel and epoxy new concrete into the existing slab at 12 inches on center.

o Install #4 Grade 60 rebar at 12 inches on center each way.

o Install 1x6 redwood expansion joints at no more than 45 FT on center.

o Install sawcut control joints at no more than 15 FT on center.

o Tool all expansion joints and pavement edges.

o Apply final concrete finish to match existing adjacent pavement and provide positive drainage.

o Contractor shall field verify all dimensions, elevations, existing conditions, and final quantities prior to construction.

Example Only:

RW 17 North (Non Controlled) East Side (See Attachment Visual Aid for reference):

o Sawcut, breakout, and remove existing concrete sidewalk section, approximately

20ft L x 5ft W. Reconstruct and pour section.

o Sawcut, breakout, and remove existing concrete pavement section, approximately

25 FT L x 12 FT W, as shown in yellow on the map. Reconstruct and pour section.

o Haul off and legally dispose of all demolition debris and waste materials.

o Construct new concrete driveway extension, approximately 75 FT L x 12 FT W.

o Stabilize as required o Provide and install 6-inch thick, 4,000 PSI concrete pavement.

o Dowel and epoxy new concrete into the existing slab at 12 inches on center.

o Install #4 Grade 60 rebar at 12 inches on center each way.

o Install 1x6 redwood expansion joints at no more than 45 FT on center.

o Install sawcut control joints at no more than 15 FT on center.

o Tool all expansion joints and pavement edges.

o Apply final concrete finish to match existing adjacent pavement and provide positive drainage.

o Contractor shall field verify all dimensions, elevations, existing conditions, and final quantities prior to construction.

Contractor shall field verify all dimensions, elevations, existing conditions, and final quantities prior to construction

26. Runway 17 South -West and East Side

a. During site visit we discovered more damaged concrete that needs to be demo. Please modify limits of demo or modify replacing entire barrier road from runway transition.

Access to pit also needs to be added.

b. Area where 120’ expansion is proposed goes into an existing low spot. During site walk it appeared to be a swale. Please advise on where to slope new installations for positive drainage.

27. Runway 4 Northeast- West and East Side

a. During site visit we discovered more damaged concrete that needs to be demo. Please modify limits of demo or modify replacing entire barrier road from runway transition.

Access to pit also needs to be added.

Answer:

Contractor to field verify. Contractor is responsible for tying into exiting concrete and ensuring smooth transition.

28. Runway 4 Southwest- West and East Side

a. During site visit we discovered more damaged concrete that needs to be demo. Please modify limits of demo or modify replacing entire barrier road from runway transition.

Access to pit also needs to be adde

b. Cracked Asphalt installations were found at these locations. Please modify scope to demo asphalt and pour back concrete.

29. Area where 90’ expansion is proposed goes into an existing low spot. During site walk it appeared to be a swale. Please advise on where to slope new installations for positive drainage.

This area on the east side has the highest elevation from all locations at the runway transition.

Please advise if we are to sawcut at runway transition and raise new installations for drainage will a sweeper be required for the duration of this project?

30. Will GPR be required for this project?

Answer: YES

31. Will sod need to be laid in all disturbed areas?

32. Will the contractor be responsible for watering the sod after installation?

Answer: Yes. An escort will be needed. The runway will not be closed for strictly watering sod

33. What size and spacing of rebar will be required?

Answer: Answered above in opening questions.

34. Will all excavated materials need to be hauled and disposed of off-site?

Answer: The spoils need to be removed unless the something is worked out with the Houston

Airport System to fill and grade current low spots in need of repair. It is discouraged to leave on site as to not negatively change the drainage of in the barrier locations.

35. Will a temporary restroom be allowed on the work sites?

Answer: Preferably on a trailer to be moved on and off airfield for work. Can be left in place if there is an extended runway closure.

36. Will we have a dedicated escort for going to and from the job sites?

Answer: Yes. Military provided. Unless a trained badge holder has a route to and from the work site not that does not transition through open areas and not requiring contact with the tower

37. Will a vapor barrier be required under the proposed concrete?

Answer: No.

38. What is the existing concrete thickness?

Answer: See SOW. Contractor

39. Are the additional failed areas going to be included in the SOW? If so, what are the sizes of these areas?

Answer: Contractor shall see approx. dimensions and failed areas. For RW 17 North - East and

West and RW 4 N – East and West.

40. Can you provide a site map for routing traffic to and from the jobsite?

Answer: See attached.

41. Can you provide a site map for alternative entry points?

42. Can the construction equipment be left on the work sites or does it have to be relocated off site each night?

Answer: Relocated off the movement area unless a long-term closure does not require it.

43. Can we weed eat the work sites to prevent the lawn crews from damaging the underground locate markers/flagging?

Answer: Yes but please discuss with airport operations on FAA 139 grass height requirements and pavement lips.

44. What kind of barricades are acceptable to put around the work sites?

Answer: Low profile barricades with lights

45. Could you please provide recent photographs of the job site? During the site walk, photography was not permitted.

Answer: Photos were permitted. Contractors angled photos towards the concrete surface only as it is policy not to take photos of the flightline. See below example photos.

Example of failed section to be removed:

46. Are scalable drawings, blueprints, or CAD files available for the project? If so, kindly share the latest versions.

47. What is the total square footage designated for replacement?

Answer: Contractor to verify.

48. What compressive strength (PSI rating) is specified for the concrete to be used?

Answer: 4000 psi.

49. Will there be a designated staging or storage area provided for the contractor’s equipment and materials?

Answer: Yes, but contractor shall assume.

50. Has a project budget been established? If so, could you share the allocated range or estimate?

Answer: The State does not give out it’s budget

51. What is the required thickness for the new pavement system?

52. What are the existing site conditions (e.g., subgrade stability, drainage issues, prior pavement type)?

53. Are there any known underground utilities or obstructions that may impact construction?

Answer: A Tenant Improvement form and a Work area notification will need to be filed to determine hazards and so lines can be located before digging. Forms can be found at

Fly2houston.com

54. What are the drainage requirements for the site?

determine drainage requirements. Forms can be found at Fly2houston.com

55. Are there grading plans available to ensure proper slope and runoff?

determine requirements. Forms can be found at Fly2houston.com

56. Is there a required warranty period for the completed work?

Answer: Yes. See SOW and contract. Contractor responsible for all deliverables to include but not limited to:

57. Can you provide a pavement section for the new barrier access roads?

Answer: The attachment is an example only. The contractor is responsible for providing electronic drawings and as built. Contractor to follow TXDOT and UFC specification for typical pavement detail.

58. During the site visit, the existing barrier roads show a lot of cracks and breaks. Can for provide limits of removal, if any, for each of the existing barrier roads? This will keep all bidders looking at the same requirements.

Answer: Please see responses to Questions 25–29 for additional clarification regarding limits of removal and replacement at each barrier road location.

All provided dimensions, quantities, and sketches are for informational/reference purposes only and are approximate (+/-). Contractor shall field verify all existing conditions, dimensions, limits, elevations, and quantities prior to bidding and construction.

59. There is an upcoming project on Runway 4-22 that will be to widen the shoulders to 30 FT.

Does the length of the new barrier roads take the new width of the shoulders into account?

Answer: Yes. Contractor shall field verify. The New limits as indicate don the attachment is approx. only.

60. Will night work be allowed for the work on Runway 17-35?

Answer: The airport has no objection to night work. Coordination with the Government is required

2 weeks prior.

61. Will a runway shut down be required for the work?

Answer: Yes. Contractor is required to adequately coordinate 4-5 Weeks prior due to the amount.

62. All work is taking place in the object free area. Will the Military or Operations have a person at the work site/sites full time to communicate with the tower?

Answer: No construction work is permitted in the safety area. Work outside the safety area will require a trained and badged individual but no tower contact is necessary.

63. Can more than one site be worked on at a time?

Answer: Yes if determined safe. Please note sites must be on same runway as only one runway closure will be permitted at a time.

64. Will the airport allow for “open” excavations in the Runway Object free area while the runway is open?

Answer: Construction, including excavations, may be permitted in the ROFA. However, equipment must be removed from the ROFA when not in use, and material should not be stockpiled in the

ROFA if not necessary.

65. Will we be able to work on the barrier roads on Runway 17-35 while Runway 4-22 is shut down?

Answer: No. Not in the safety area.

66. Will a full time Vacuum Broom be required?

Answer: Contractor is required to adhere that the area must be free of debris (FOD) before an area is open for aircraft. Means and methods. After each work day and throughout daily production.

67. Will the contractor be allowed to use the runways to access the work areas?

Answer: Yes, if closed or escorted. Repeated movement on and off an open runway is not permitted due to the stress on air traffic and negative effects on aircraft movement.

68. Is there a designated gate for this project?

Answer: There will be. Gate will be determined based on the location of the work. Contractor shall assume distance and drive time from concrete batch plants and vendors for bidding purposes.

69. Will all employees need to be Badged?

For Flightline: Training is conducted by airport operations and takes approximately 3 hours. All can attend training but only leads and escorts will receive badges.

For Ellington Field: Contractor will submit visitor passed for background check, biometric screening approval or rejection.

70. For escorts, how many trucks can be escorted at a time by one escort?

As many as the escort can effectively control.

For Flightline: Training is conducted by airport operations and takes approximately 3 hours. All can attend training but only leads and escorts will receive badges.

For Ellington Field: Contractor will submit visitor passed for background check, biometric screening approval or rejection.

71. Is there room between the Runway Object Free Area and the Taxiway Object Free Area to store equipment or will the contractor be required to move all equipment off “site” at the end of shift?

Off site unless a suitable area is determined by Airport Ops. Will not be near a runway.

72. Is there a laydown yard provided for this project?

Answer: This is a military project so probably on military property unless the military and City

Airport agree on more suitable location.

73. Have all known utility conflicts and other conflicts in the right of way for construction been removed or relocated?

Answer: contractor is responsible for 811 dig permits. Contractor is responsible for GPR.

74. Will the Contractor be compensated for additional costs and/or allowed additional time due to errors and omissions in the plans and specifications?

Answer: Only if it is unforeseen and not able to discern the need during the site visits. If the need is determined during the site visit and is not included in the specifications of the solicitation, Respondent should add the extra work as a separate line items and explanation as to why is it needed.

75. If the Contractor encounters a delay to the critical path because of a utility company’s delay in relocating a conflicting utility, will the Contractor be compensated in both time and cost for the delay?

76. Please confirm that Contractor’s review of the dimensions, elevations and quantities in the bid package is made in its capacity as a construction contractor (as opposed to a licensed design professional) and that as a construction contractor, Contractor is not liable for failing discovering design errors or omissions or ascertaining the project's design compliance with applicable laws or codes.

Answer: Contractor is responsible for a complete and usable quality product.

77. Is the Contractor allowed to rely-on reports, plans and specifications provided by the Owner or

Engineer, and receive a change order for both time and additional costs if the information provided is incorrect?

Answer: See answer 74

78. If the critical path is delayed because of the Owner or the Engineer, will the Contractor be compensated in both time and cost for the delay?

Answer: Time yes, cost will be discussed on a case by case basis

79. If during the construction of the project, underground utilities and unforeseen site conditions not shown on the plans are discovered, will the Contractor be compensated in both time and cost for the critical path delay caused by their relocation or removal?

Answer: See answer 74

80. The Texas Military Department Standard Terms and Conditions (Revision 7) contain alternate clauses that could be applicable to this project such as in Section 4, 17, 25, 73, 75, 79, 85 and

91. Which of the alternate clauses are applicable for this project?

Answer: Upon award, the Contractor’s legal team can submit any discussion required on these alternate clauses.

81. The Texas Military Department Standard Terms and Conditions (Revision 7) gives a standard of care for architectural and engineering contractors. What is the standard of care for construction contractors?

Answer: Construction contractors will be governed instead by performance, warranty, safety, coordination, and quality-control requirements found in the solicitation general requirements, SOW, and specifications.