ESBD_452864_1774290920126_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf

PDF 132 KB Posted

Attached to
EXTEND BARRIER ACCESS ROADS ELLINGTON AFB
Solicitation number
TMD25-ANG-WJ-24150011
Issued by
Harris County, Texas

About this file

This specification document is an attachment for manufacturers' services at Ellington Field in Houston, Texas, establishing requirements for factory-trained manufacturer representatives to provide installation assistance, inspection, testing, and training services for specified equipment and systems. The contractor must submit a training schedule at least twenty-one days prior to equipment installation, a preliminary training plan within sixty days after Notice to Proceed, and a final training plan following a training coordination meeting. Manufacturers' services must include on-site assistance during product installation, inspection and adjustment to ensure equipment functions as warranted, resolution of assembly or installation problems, support during functional and performance testing, training of Ellington Field personnel on equipment operation and maintenance, and completion of manufacturer certificates of proper installation. Training must be completed at least fourteen days prior to equipment startup, and additional post-startup training may be required. The contractor is responsible for scheduling manufacturers' services to avoid conflicts with other on-site activities and for ensuring all conditions necessary for successful testing are met before services are scheduled.

The specification establishes that manufacturer representatives must be authorized, factory-trained personnel with experience in technical applications, installation, operation, and maintenance of the respective equipment, and all representatives are subject to approval by the Project Manager with no substitutions permitted without prior written approval. Training personnel must be trained and articulate, capable of coordinating with Ellington Field operating personnel and facilities staff, and instructors providing detailed classroom and hands-on training must have resumes submitted for approval. Training plans must include course titles, objectives, schedules, prerequisite qualifications, recommended attendee types, course descriptions with detailed content outlines, duration, location, format, instruction materials and equipment requirements, and detailed daily schedules showing time allocation for each topic.

View the file

Other files

File Type Posted
ESBD_452864_1780091827962_Attachment G.5 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_452864_1779205491588_Addendum 2 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1777473605426_Addendum 1 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1779913011683_Addendum 3 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1780322077414_Addendum 5 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1780091806262_Addendum 4 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1774290608978_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_452864_1774290857018_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_452864_1774290974494_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_452864_1774290754031_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_452864_1774290899410_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_452864_1774290933038_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_452864_1774290960900_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_452864_1774290554718_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_452864_1774290870767_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_452864_1774290993298_ATE420~1.PDF PDF
ESBD_452864_1774290799347_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_452864_1774291008049_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_452864_1774290721468_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_452864_1774290768389_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_452864_1774291105912_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (05OCT25).pdf PDF
ESBD_452864_1774290690863_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_452864_1774290829874_ATF409~1.PDF PDF
ESBD_452864_1774290574288_ATTACHMENT G.2 Application for Texas Identification Number #_AP_152.pdf PDF
ESBD_452864_1774290945955_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_452864_1774290843236_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_452864_1774290592459_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 7.pdf PDF
ESBD_452864_1774291027426_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_452864_1774291122889_ATTACHMENT G.Z - Example of Contractor Cost Estimate 2026.pdf PDF
ESBD_452864_1774290885606_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_452864_1774290623533_ATTACHMENT G.6 FAA Form 7460-1.pdf PDF
ESBD_452864_1774290638971_ATTACHMENT G.7 Location Photo Aids.pdf PDF
ESBD_452864_1774291073896_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_452864_1774290738406_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_452864_1774290786162_ATE180~1.PDF PDF
ESBD_452864_1774290813335_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_452864_1774290705618_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_452864_1774291060898_ATBB18~1.PDF PDF
ESBD_452864_1774291091775_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_452864_1774291046904_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_452864_1774290672414_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_452864_1774290518021_TMD25-ANG-WJ-24150011 EXTEND BARRIER ACCESS ROADS ELLINGTON AFB.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.N - ELLINGTON AFB (EF) MANUFACTURERS’

SERVICES

PART 1 – GENERAL

1. DEFINITIONS

Person-Day: One person for eight (8) hours within regular Contractor working hours.

2. SUBMITTALS

A. Training Schedule: Submit not less than twenty-one (21) days prior to start of equipment installation and revise as necessary for acceptance.

B. Preliminary Training Plan: Submit within sixty (60) days after Notice to Proceed for approval by the Project Manager.

C. Final Training Plan: Submit after training coordination meeting.

D. Training Materials:

a. Submit written outlines of proposed training sessions not less than twenty-one

(21) days prior to scheduled training to be approved by the Project Manager.

b. Furnish complete training materials, to include operation and maintenance data as required in this section to be retained by each trainee.

E. Quality Control Submittals: When specified in the individual Specifications, submit:

a. Qualifications of Manufacturer’s Representative performing specified services.

b. Manufacturer’s Certificate of Proper Installation: On form appended to this section.

3. QUALIFICATION OF MANUFACTURER’S REPRESENTATIVE

A. Authorized representative of the manufacturer shall be factory trained and experienced in the technical applications, installation, operation, and maintenance of respective equipment, subsystem, or system. Additional qualifications may be specified elsewhere.

B. Manufacturer’s Representative subject to acceptance by the Project Manager. No substitute representatives will be allowed unless prior written approval by the Project

Manager has been given.

4. FULFILLMENT OF SPECIFIED MINIMUM SERVICES

A. Where manufacturers’ services are specified, furnish manufacturer’s qualified representative. Where time is necessary in excess of that stated in the Specifications for manufacturers’ services, additional time required to perform the specified services shall be considered incidental work.

B. Schedule manufacturer’s services to avoid conflicting with other onsite testing or other manufacturer’s onsite services.

a. Determine that all conditions necessary to allow successful testing have been met before scheduling services.

C. Only those days of service approved by the Project Manager will be credited to fulfill the specified minimum services.

D. If specified, manufacturer’s onsite services shall include as a minimum:

a. Assistance during product (system, subsystem, or component) installation to

ELLINGTON FIELD, HOUSTON, TX 21 May 2024 include observation, guidance, instruction of Contractor’s assembly, erection, installation or application procedures.

b. Inspection, checking, and adjustment as required for product (system, subsystem, or component) to function as warranted by manufacturer and necessary to furnish written approval of installation.

c. Revisiting the site as required to correct problems and until installation and operation are acceptable to the Project Manager.

d. Resolution of assembly or installation problems attributable to, or associated with, respective manufacturer’s products and systems.

e. Assistance during functional and performance testing and startup demonstration, and until product acceptance by the Project Manager.

f. Training of EF personnel in the operation and maintenance of respective product as required.

g. Completion of Manufacturer’s Certificate of Proper Installation (form enclosed at end of this section) with applicable certificates for proper installation and initial, interim, and final test or service.

h. Additional requirements as may be specified elsewhere.

5. TRAINING SCHEDULE

A. List specified equipment and systems with respective manufacturers that require training services of manufacturers’ representatives and show:

a. Estimated dates for installation completion.

b. Estimated training dates to allow for multiple sessions when several shifts are involved.

B. Adjust training schedule to ensure training of appropriate personnel as deemed necessary by the Project Manager, and to allow full participation by manufacturers’ representatives. Adjust schedule for interruptions in operability of equipment.

6. TRAINING PLAN

A. Preliminary Training Plan: If specified, and within sixty (60) days after Notice to

Proceed, submit for each proposed course to be approved by the Project Manager:

a. Title and objectives.

b. Training schedule.

c. Prerequisite training and experience of attendees.

d. Recommended types of attendees (e.g., managers, engineers, operators, maintenance).

e. Course description and outline of course content.

f. Duration.

g. Location (e.g., training center or site).

h. Format (e.g., lecture, self-study, demonstration, hands-on).

i. Instruction materials and equipment requirements.

j. Final Training Plan: Submit the following after training coordination meeting, if specified.

k. Updated versions of course descriptions from preliminary training plan.

l. Personnel who will attend each course.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

m. Schedule of training courses including dates, durations, and locations of each class.

n. Detailed course schedule for each day showing time allocated to each topic.

o. Resumes of instructors providing the training.

7. TRAINING BASE PERSONNEL

A. Furnish trained, articulate personnel to coordinate and expedite training, to be present during training coordination meetings with EF Personnel, and familiar with operation and maintenance manual information specified in Division 1 Section, “Operation and

Maintenance Data”.

B. Furnish manufacturers’ representatives for detailed classroom and hands-on training to EF personnel on operation and maintenance of specified product (system, subsystem, component) and as may be required in applicable Specifications.

a. Manufacturer’s Representative: Familiar with facility operation and maintenance requirements as well as with specified equipment.

C. Prestart up Training:

a. Coordinate training sessions with EF operating personnel and manufacturers’ representatives, and with submission of operation and maintenance manuals in accordance with Division 1 Section “Operation and Maintenance Data”.

b. Complete at least fourteen (14) days prior to actual startup.

D. Post-Startup Training: If required in Specifications, furnish and coordinate training of

EF operating personnel by respective manufacturer’s representatives.

8. SUPPLEMENTS

A. The supplements listed below, following “END OF SECTION,” are part of this

Specification.

a. Forms: Manufacturer’s Certificate of Proper Installation.