About this file
This document is a safety policies and procedures attachment for a construction contract at Ellington Field, Houston, Texas, issued by the Texas Air National Guard (TXANG). The attachment establishes comprehensive safety requirements that contractors must follow during all work activities at the installation. Contractors are required to submit a Statement of Qualification for a land surveyor or civil engineer, a health and safety plan, a construction hazard plan, and a temporary utility plan for approval by the Contracting Officer prior to work commencement. A qualified, OSHA-trained safety representative must be designated and present on-site whenever work is in progress, and all employees must receive training and certification in 29 CFR 1926 procedures appropriate to their job duties. The contractor must develop and present a Job Hazard Analysis and Job Safety and Health Plan at a preconstruction conference, with weekly safety briefings documented for all personnel.
The Health and Safety Plan must meet fourteen minimum requirements, including written site-specific hazard analyses for each task and operation, personal protective equipment specifications, medical surveillance provisions, air and environmental monitoring protocols, site control programs, decontamination procedures for chemical materials, emergency response plans, confined space entry procedures, and spill containment measures coordinated with the installation. A qualified safety and health supervisor meeting 29 CFR 1926 training requirements must provide written verification of plan adherence, with deficiencies corrected immediately upon discovery in consultation with the Project Manager and Contracting Officer. Additionally, contractors must maintain Safety Data Sheets on-site for all materials, submit a temporary utility hookup plan for coordination and approval, and conduct monthly safety meetings with all personnel, documenting attendance and meeting minutes for submission at progress meetings.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.E - ELLINGTON AFB (EF) SAFETY POLICIES AND
PROCEDURES
PART 1 – GENERAL
1. SECTION INCLUDES
A. Statement of Qualification (SOQ) for land surveyor or civil engineer.
B. Contractor required health and safety plan.
C. Contractor required construction hazard plan.
D. Contractor required temporary utility plan.
2. RELATED DOCUMENTS
A. Drawings and general provisions of the Contract apply to this section.
B. The publication listed below is a part of this specification to the extent referenced.
The publication is referred to in text by the basic designation only.
a. OSHA 1926 R.E.G. – 29 CFR, OSHA, 1926.
3. SUBMITTALS
A. Submittals the following items for KO approval:
a. Designation of safety representative: the contractor shall submit in writing a qualified employee OSHA trained in 29 CFR 1926 (1926 | Occupational
Safety and Health Administration (osha.gov)) responsible for the overall supervision of all accident prevention activities. Duties shall include ensuring applicable safety requirements are incorporated into work methods and inspecting the jobsite to ensure that safety measures and instruction are being applied. The person shall be always on site that work is in progress.
b. The contractor shall be trained/certified in 29 CFR 1926 procedures. All employees performing work will meet 29 CFR 1926 training requirements for their job capacity.
c. Records shall be kept of all weekly safety briefings and who was in attendance.
B. Submittal for information only: The following items shall be contractor certified:
a. Job Hazard Analysis: Contractor shall develop a job hazard analysis for presentation at the preconstruction conference. The Contractor’s job hazard analysis shall list potential hazards that could arise during the work.
b. Job Safety and Health Plan:
i. The Contractor shall develop a Job Safety and Health Plan for presentation at the preconstruction conference. The Contractor’s
Safety Plan shall make whatever provision are necessary to conduct his work in accordance with current OSHA standards.
c. The following are minimum requirements for the Health and Safety Plan:
i. Safety Plans: Safety Plans will be the responsibility of the Contractor for construction areas identified by the installation and /or TXANG as areas of known hazards only. These plans are required by 29 CFR
1926 and are the responsibility of the Contractor. This requirement shall be coordinated with the Health and Safety Program of the
Military installation by the Contractor.
https://osha-safety-training.net/product/1926-osha-construction-industry-regulations-2024-edition/?utm_term=&utm_campaign=Sales-Performance+Max-New-Best-Performers&utm_source=adwords&utm_medium=ppc&hsa_acc=8236925820&hsa_cam=20512594485&hsa_grp=&hsa_ad=&hsa_src=x&hsa_tgt=&hsa_kw=&hsa_mt=&hsa_net=adwords&hsa_ver=3&gad_source=1&gclid=CjwKCAjw65-zBhBkEiwAjrqRMP7E8ru73uFwonCkyc5WuI5maWCG8keup2kQJj8Q05xzvLRcYu3vkBoCbSUQAvD_BwE
ELLINGTON FIELD, HOUSTON, TX 21 May 2024
ii. Minimum requirements for the Health and Safety Plan are as follows:
1. Must be kept on site and must be written.
2. Will contain a hazard analysis (safety and health risk) for each site task and operation.
3. Will include employee training and weekly safety update briefings (record kept on each employee and subcontractor)
4. Will include personal protective equipment to be used by employees for each of the site tasks and operations.
5. Will include provisions for medical surveillance.
6. Will include frequency and type of air monitoring, personal monitoring, environmental sampling instruments being used if required.
7. Will include a site control program to be coordinated with the installation.
8. Will include a decontamination procedure for the anticipated types of chemical materials to be used in the project
9. Will include an emergency response plan.
10. Will include a confines space entry procedure and pre-entry briefings.
11. Will include provisions for spill containment, to be coordinated with installation.
12. Will include telephone notifications for accidents and follow-on procedures for written reports of the accidents.
13. Written verification of adherence to the Plan by a safety and health supervisor is required (the supervisor must meet 29 CFR
1926 training requirements for supervisors).
14. Deficiencies will be corrected immediately upon discovery and after consultation with the Project Manager, KO as required.
d. Hazard Response Plan: The plan unplanned or non-predicted discovery of such hazards as transite pipe, contaminated soils, and other possible hazards will be addressed within an Emergency Response Plan (EMR) by all contractors. This requirement will be coordinated through the Health and
Safety Program of the Project Manager by the Contractor. Safety Data Sheets
(SDS) shall be maintained at the site for all materials in use.
e. Temporary Utility Plan: The Contractor shall submit a temporary utility hook up plan to be coordinated and approved by the Project Manager. The plan shall describe electrical, water, sanitary facilities, telephone/fax and/or gas.
4. MONTHLY SAFETY MEETINGS
A. The Contractor shall schedule subsequent safety meetings with all personnel, employees and subcontractor personnel on a monthly basis or as required by the
Project Manager. Minutes of the safety meetings shall be prepared and signed by the
Contractor. The meeting notes shall have a roll signed by all members present. This document shall be submitted to the Project Manager at each progress meeting and be a part of the itinerary.