ESBD_452864_1774290899410_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf

PDF 63 KB Posted

Attached to
EXTEND BARRIER ACCESS ROADS ELLINGTON AFB
Solicitation number
TMD25-ANG-WJ-24150011
Issued by
Harris County, Texas

About this file

This is a material equipment specification attachment for Ellington Air Force Base located in Houston, Texas, establishing general requirements for the procurement, handling, and management of products and equipment. The document outlines comprehensive procedures for transportation, handling, storage, and protection of materials throughout the project lifecycle, including mandatory compliance with manufacturer instructions, prompt inspection of shipments for quality and quantity verification, and appropriate handling methods to prevent damage or deterioration. Storage requirements specify that sensitive products must be maintained in weather-tight, climate-controlled enclosures, while exterior storage of fabricated products requires placement on sloped supports above ground. The specification addresses three categories of product options: products specified by reference standards or description only, products specified by naming one or more manufacturers with no substitution allowed, and products specified by naming manufacturers with provisions for substitution requests.

Substitution requests are considered only during the submittal phase and when products become unavailable through no fault of the contractor, with the contractor required to submit three copies of a substitution request form along with supporting shop drawings, product data, and certified test results demonstrating equivalence to the specified product. The Project Manager retains authority to accept or reject substitution requests in writing, and contractors remain responsible for supplying items as originally specified or providing acceptable substitutions at no additional cost to the government if requests are denied. Payment for on-site stored materials is limited to actual material costs and requires submission of an inventory list accompanied by supplier invoices, and all products must be arranged to permit access for periodic inspection to verify continued acceptable condition.

View the file

Other files

File Type Posted
ESBD_452864_1780091827962_Attachment G.5 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_452864_1779205491588_Addendum 2 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1777473605426_Addendum 1 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1779913011683_Addendum 3 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1780322077414_Addendum 5 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1780091806262_Addendum 4 - TMD25-ANG-WJ-24150011.pdf PDF
ESBD_452864_1774290608978_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_452864_1774290857018_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_452864_1774290974494_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_452864_1774290754031_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_452864_1774290933038_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_452864_1774290960900_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_452864_1774290554718_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_452864_1774290870767_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_452864_1774290993298_ATE420~1.PDF PDF
ESBD_452864_1774290799347_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_452864_1774291008049_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_452864_1774290721468_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_452864_1774290768389_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_452864_1774291105912_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (05OCT25).pdf PDF
ESBD_452864_1774290690863_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_452864_1774290829874_ATF409~1.PDF PDF
ESBD_452864_1774290574288_ATTACHMENT G.2 Application for Texas Identification Number #_AP_152.pdf PDF
ESBD_452864_1774290945955_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_452864_1774290920126_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_452864_1774290843236_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_452864_1774290592459_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 7.pdf PDF
ESBD_452864_1774291027426_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_452864_1774291122889_ATTACHMENT G.Z - Example of Contractor Cost Estimate 2026.pdf PDF
ESBD_452864_1774290885606_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_452864_1774290623533_ATTACHMENT G.6 FAA Form 7460-1.pdf PDF
ESBD_452864_1774290638971_ATTACHMENT G.7 Location Photo Aids.pdf PDF
ESBD_452864_1774291073896_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_452864_1774290738406_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_452864_1774290786162_ATE180~1.PDF PDF
ESBD_452864_1774290813335_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_452864_1774290705618_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_452864_1774291060898_ATBB18~1.PDF PDF
ESBD_452864_1774291091775_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_452864_1774291046904_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_452864_1774290672414_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_452864_1774290518021_TMD25-ANG-WJ-24150011 EXTEND BARRIER ACCESS ROADS ELLINGTON AFB.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.M - ELLINGTON AFB (EF) MATERIAL EQUIPMENT

PART 1 – GENERAL

1. RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions, apply to this Section.

2. SUMMARY

A. This Section includes:

a. Transportation and handling

b. Storage and protection

c. Product options

d. Substitutions

3. TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

4. STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers' instructions, with seals and labels intact and legible.

B. Store sensitive Products in weather tight, climate-controlled enclosures.

C. For exterior storage of fabricated Products, place on sloped supports, above ground.

D. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

E. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to avoid condensation or potential degradation of Product.

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

G. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

H. Arrange storage of Products to permit access for inspection. Periodically inspect to verify Products are undamaged and are maintained in acceptable condition.

I. Payment for materials stored on site will be made only when the request is accompanied by an inventory of stored materials along with copies of the supplier invoices for the stored materials. Only actual cost of the materials stored will be compensated.

5. PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following article.

6. SUBSTITUTIONS

A. Project Manager will consider requests for Substitutions during the submittal phase of the project.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

a. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

b. Will provide the same warranty for the Substitution as for the specified

Product.

c. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

d. Waives claims for additional costs or time extension which may subsequently become apparent.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

a. Submit three copies of request for Substitution for consideration on

Substitution Request Form attached to this section. Limit each Substitution

Request Form to one proposed Substitution.

b. Submit shop drawings, product data, and certified test results attesting to the proposed Product equivalence.

c. The Project Manager will notify Contractor in writing of decision to accept or reject re- quest.

G. If request for substitution is not accepted by the government, Contractor is responsible for sup- plying item as originally specified or an acceptable substitution without additional cost to the Owner.