CN-370000-HW686-SA253.pdf
PDF 1 MB Posted
- Contract number
- HW686
- Issued by
- Florida
About this file
Task Assignment Summary
This Task Assignment (TA SA253) is a contract vehicle issued by the State of Florida Department of Environmental Protection (FDEP) under Master Contract HW686 with Professional Service Industries, Inc. (Intertek-PSI) to provide equipment support services at the Collier-Hogan Study Site located at Everglades and Immokalee Road in Immokalee, Collier County, Florida. The project is identified as ERIC_6426 and involves coordination between the FDEP Site Investigation Section and PSI, with Nana Westmark serving as the contractor's project manager and Nicole Knutson/D. Meyers as the department project managers.
The contract covers the rental and management of a 21,000-gallon capacity frac tank (purge water storage container) for a one-quarter period (approximately 14 weeks from July through September 2023), with transportation back to the rental company for cleaning and storage. The total task value is $24,333.87, comprised of $213.99 for project management (Subtask 1) and $24,119.88 for equipment rental (Subtask 2). The equipment rental cost includes United Rentals' charges for weekly tank rental at $1,260 per week ($17,640 for 14 weeks), cleaning charges ($750), excess sediment disposal ($400), service fee ($140.70), and pick-up fee ($1,500). Task deliverables consist of subcontractor invoices and weight tickets for purge water disposal, with a final deliverable due October 20, 2023, and task completion date of November 28, 2023.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW686
SA253 Completion November 28, 2023
As outlined in the June 1, 2023 Proposal for Equipment Support Services-June 2023-September 2023, Collier-Hogan Site, PSI will provide a purge water storage container (i.e. 21,000 gallon capacity frac tank) for one quarter of the year and transportation back to the rental company for cleaning and storage. Task Assignment Deliverables to consist of subcontractor invoices and weight tickets for purge water disposal.
Nicole Knutson/D. Meyers 850-245-8763 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Professional Service Industries, Inc (Intertek-PSI)
Professional Service Industries, Inc (Intertek-PSI)
Nana Westmark 813-886-1075 Ext 2
ERIC_6426
Everglades and Immokalee Road, Immokalee, Collier County FL
Collier-Hogan Study - FracTank Rental - One Qtr
✔ $ 24,333.87
$ 24,333.87
Scope of Work
Nana Westmark
Senior Geologist / Principal Consultant
Nana G Westmark Digitally signed by Nana G Westmark Date: 2023.06.27 10:09:25 -04'00' David Phillips Digitally signed by David Phillips
Date: 2023.06.23 12:13:27 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 1 - Project Management; Subtask 2 - Equipment Rental 10/20/2023
FDEP Approval of Project Management; Subcontractor Invoice Package - Subtasks 1 & 2 $ 24,333.87
$ 24,333.87
HW686
SA253
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO:
FROM:
Site # ERIC_6426 Collier-Hogan Study Site File
David Meyers, Project Manager
SUBJECT: Negotiation Summary
HW686 SA253
DATE: June 22, 2023
As outlined in the June 1, 2023 Proposal for Equipment Support Services-June 2023- September 2023, Collier-Hogan Site, PSI will provide a purge water storage container (i.e. 21,000 gallon capacity frac tank) for one quarter of the year and transportation back to the rental company for cleaning and storage. Task Assignment Deliverables to consist of subcontractor invoices and weight tickets for purge water disposal.
Total task amount is $24,333.87. PSI’s time and labor for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable is due October 20, 2023. Task completion date is November 28, 2023.
FDEP COST ESTIMATEContractor: Professional Service Industries, Inc. (Intertek-PSI)
Date: 6/1/2023
Task #: SubTask 1 Project Management SubTask 6
Site: Collier Hogan ERIC_6426, 714-1 SubTask 2 Equipment Rental SubTask 7
Activity/Phase: Equipment Rental SubTask 3 SubTask 8
Project Manager: Nana Westmark SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$56.99 Project Manager 1 1.4 $64.90 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $60.00 Senior Engineer, MR 0 0 0 0 0 0 0 0 0 0 $56.99 Senior Geologist, NW 9 9 0 0 0 0 0 0 0 0
$0.00 Senior Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Certified Industrial Hygientist 0 0 0 0 0 0 0 0 0 0 $0.00 Certified Hazardous Materials Manager 0 0 0 0 0 0 0 0 0 0 $0.00 Florida Licensed Asbestos Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Manager 0 0 0 0 0 0 0 0 0 0
$43.27 Project Engineer, JN 0 0 0 0 0 0 0 0 0 0 $43.27 Project Engineer, IK 0 0 0 0 0 0 0 0 0 0 $40.87 Project Engineer, MK 0 0 0 0 0 0 0 0 0 0 $37.00 Project Scientist, SAM 0 0 0 0 0 0 0 0 0 0 $33.74 Project Scientist, SB 0 0 0 0 0 0 0 0 0 0 $29.86 Project Scientist, EL 0 0 0 0 0 0 0 0 0 0 $29.62 Project Scientist, RF 0 0 0 0 0 0 0 0 0 0
$0.00 QA Officer 0 0 0 0 0 0 0 0 0 0 $21.26 Environmental Specialist, DK 0 0 0 0 0 0 0 0 0 0 $29.86 GIS / CAD Specialist, CF 0 0 0 0 0 0 0 0 0 0 $28.85 Staff Scientist, RP 0 0 0 0 0 0 0 0 0 0 $24.04 Staff Scientist, OG 0 0 0 0 0 0 0 0 0 0 $25.00 Staff Scientist, QH 0 0 0 0 0 0 0 0 0 0 $30.91 Environmental Specialist, CC 0 0 0 0 0 0 0 0 0 0 $21.21 Environmental Specialist, MZ 0 0 0 0 0 0 0 0 0 0 $20.81 Administrative Assistant, BM 4 4 0 0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 14 1 13 0 0 0 0 0 0 0 0
Direct Labor $673.65 $77.50 $596.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 151.02% $1,017.35 $117.04 $900.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $1,691.00 $194.54 $1,496.46 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF Intertek-PSI Page 1
FDEP COST ESTIMATEContractor: Professional Service Industries, Inc. (Intertek-PSI)
Date: 6/1/2023
Task #: SubTask 1 Project Management SubTask 6
Site: Collier Hogan ERIC_6426, 714-1 SubTask 2 Equipment Rental SubTask 7
Activity/Phase: Equipment Rental SubTask 3 SubTask 8
Project Manager: Nana Westmark SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 United Rentals $20,430.70 $20,430.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $20,430.70 $20,430.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $2,043.07 $2,043.07 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $22,473.77 $22,473.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $24,164.77 $194.54 $23,970.23 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $169.10 $19.45 $149.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $24,333.87 $213.99 $24,119.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF Intertek-PSI Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Collier Hogan ERIC_6426, 714-1 SubTask 2 Equipment Rental
DATE: 6/1/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Geologist Call for Baker Tank pick-up, transport, and cleaning 3 Review receipts, trip charges, documentation 2 Develop Deliverable to FDEP 4
Total Hours: 9
Administrative Assistant Document set-up 2 Processing of receipts for payment 2
Total Hours: 4
TOTAL LABOR 13
VEHICLE TYPE RATE UNIT USEAGE
$0.00
$0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
United Rentals 21,000 gallon Frac tank 14 $1,260.00 $17,640.00 weekly rental at $1260 per week cleaning charge 1 $750.00 $750.00 does not include excess sediment over 25 gal, $8 per gallons for overage 50 $8.00 $400.00 Budget 50 gallons overage service fee 1 $140.70 $140.70 pick-up fee 1 $1,500.00 $1,500.00
TOTAL $20,430.70
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00
$0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
$0.00
TOTAL EQUIPMENT $0.00
FINAL --7/24/96
PSI Proposal: 0552-401082 June 1, 2032
Professional Service Industries, Inc.
5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634
Phone: (813) 886-1075 Fax: (813) 249-4916 www.intertek.com/building
Florida Department of Environmental Protection Site Investigation Section 2600 Blair Stone Road, MS 4515 Tallahassee, Florida 32399-2400
Attention: Ms. Nicole Knutson, Environmental Specialist II
(850) 245-8705 Nicole.Knutson@FloridaDEP.gov
Re: Proposal for Equipment Support Services – July 2023 – September 2023
Collier-Hogan Site Everglades and Immokalee Road Collier County, Florida
FDEP Site No. 714-1, ERIC_6426
Dear Ms. Knutson:
Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the following proposal for equipment support services for the Collier Hogan Site, near Everglades and Immokalee Road, Immokalee, Collier County, on behalf of the Florida Department of Environmental Protection (FDEP), Site Investigation Section (SIS). The purpose of this work is to arrange for rental for the purge water storage container (i.e. frac tank or Baker tank) at the above referenced site. Presented herein is a proposed scope of services, schedule and proposed costs associated with these services.
PROPOSED SCOPE OF WORK
A Request for Assistance was transmitted from the FDEP, Site Investigation Section to provide support for approximately one quarter (14 weeks) at the Collier Hogan Site. PSI will coordinate the rental of an approximate 21,000-gallon capacity frac tank. We understand that during the next quarter, the tank will be removed from the site and transported back to the rental company for cleaning and storage.
We will subcontract the tank rental, transportation, and cleaning to United Rentals (formerly Baker Corporation. No groundwater sampling or laboratory analysis will be performed by PSI or its subcontractors under this Task Assignment. An updated quote for 2023 from United is attached to this correspondence.
The Task Assignment Deliverable which will consist of all subcontractor invoices for associated services.
mailto:Nicole.Knutson@FloridaDEP.gov
PSI Proposal: 0552-401082 Collier-Hogan, FDEP Site No. 714-1
June 1, 2023 www.intertek.com/building
COST ESTIMATE AND SCHEDULE
A Cost Estimate spreadsheet and Level of Effort to provide the above described services is attached for your consideration. All PSI services will be conducted in accordance with the terms and conditions contained within the DEP Contract No. HW 686, Waste Cleanup Program Services, dated December 21, 2021. The equipment is currently stored on the project site and operating under TA SA187 under Contract HW 686. We anticipate the new rental services to start at the beginning of July 2023 under Contract HW 686 and run for one quarter (approximately three months, July, August, September 2023, or 14 weeks).
Due to the fiscal year ending, we are working to avoid any disruption of service and avoid any out of synch dates. An invoice and deliverable schedule is presented below.
Collier Hogan ERIC_6426, 714-1 Equipment Rental
Task Proposed Cost
Schedule / Deliverable Invoice Deliverable
SubTask 1 Project Management $213.99 October 20, 2023 November 28, 2023 SubTask 2 Equipment Rental $24,119.88 October 20, 2023 November 28, 2023
TOTAL COST: $24,333.87
PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075.
Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.
Michael Rothenburg, PE, CIH Nana Westmark, PG, CHMM Senior Engineer / Department Manager Senior Geologist / Contract Manager
Enclosure: Cost Estimate Level of Effort
Z:\552-Env\FDEP HW 686 Site Investigation\0552-3557 Collier Hogan tank rental, water July 2022-June 2023\Proposals\Equip Support 3 months July 2023 - Sep 2023\Collier Hogan Equip Support 0552-401082.docx
U1INVPDF
This is not an invoice Please do not pay from this document
RENTAL QUOTE
FLUID SOLUTIONS
Page: 1
RENTAL ITEMS:
_____ ___________ _______________________________________ _____________________________________________ _______________ Qty Equipment Description Minimum Day Week 4 Week Estimated Amt.
1 6055110 TANK 21K GAL FXDAXL VPR TIGHT LINED SM 45.00 45.00 315.00 1,260.00 1,260.00
Rental Subtotal: 1,260.00
SALES/MISCELLANEOUS ITEMS:
_______ ______________________________________________________________ _____________ _________________ _______________ Qty Item Price Unit of Measure Extended Amt.
1 CLEANING CHARGE [CLEAN CHRG/MCI] 750.000 EACH 750.00
TANK CLEANING FEE. DOES NOT INCLUDE
EXCESS HEEL/SEDIMENT OVER 25 GALLONS. $8
PER GALLON DISPOSAL FEE FOR ANYTHING
OVER.
1 PICKUP CHARGE 1500.000 EACH 1,500.00
Sales/Misc Subtotal: 2,250.00
Agreement Subtotal: 3,510.00 Tax: 140.70 Estimated Total: 3,650.70
COMMENTS/NOTES:
CONTACT: NANA WESTMARK
CELL#: 813-267-2519
PROFESSIONAL SERVICE IND.
COLLIER HOGAN OILFIELD SITE
NAPLES FL 34120
Office: 813-886-1075 Job: 813-886-1075
PSI PROFESSIONAL SVC IND FL
5801 BENJAMIN CENTER DR
TAMPA FL 33634-5206
BRANCH I40
1731 TAPPAN BLVD
TAMPA FL 33619-3001
813-685-9944
# 220079925
J o b
S i t e
J o b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i
Customer # :
Quote Date :
Estimated Out :
Estimated In :
UR Job Loc :
UR Job # :
Customer Job ID:
P.O. # :
Ordered By :
Written By :
Salesperson :
654698 05/25/23
05/25/23 10:00 AM
06/22/23 10:00 AM
COLLIER HOGAN OILFIE
TAM 1770402
TBD
NANA WESTMARK
THOMAS HOWE
LEE TAYLOR
This proposal may be withdrawn if not accepted within 30 days. The above referenced Rental Protection Plan, environmental, and tax charges are estimates and are subject to change.
NOTICE: This is not a rental agreement. The rental of equipment and any items listed above is subject to availability and subject to the terms and conditions of the Rental and Service Agreement, which are available at https://www.unitedrentals.com/legal/rental-service-terms-US and which are incorporated herein by reference. A COPY OF THE RENTAL AND SERVICE
AGREEMENT TERMS ARE AVAILABLE IN PAPER FORM UPON REQUEST.
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v1.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev1_12-12-22.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
| Utility Locate Bids_Compiled.pdf |
| Geosyntec Utility-272_Geotek_1500 |
| Geoview Utility Quote_2000_COT FTF SIS |
| Tallahassee Fire Training Division_V1_Bloodhound_3700 |
| Drilling Bids_Compiled.pdf |
| PDS_Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (sonic) |
| Direct Push |
| City of Tallahassee Fire Training Site_GW Protection PFAS Free Water Estimate Email |
| Cascade_Geosyntec Consultants, Inc. - City of Tallahassee Fire Training Facility - PN221026-118844 |
| GW Protection_Geosyntec (T) 1022060 S.pdf |
| Invoice |
| Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (MOT).xlsx.pdf |
| Sheet1 |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v1.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v2.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev2.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
File details come from the government source that posted it. Updated .