This is a Task Assignment (TA) document issued under Contract Number HW686 between the State of Florida Department of Environmental Protection (FDEP) and Professional Service Industries, Inc. (Intertek-PSI). The Task Assignment authorizes PSI to conduct a deep Modified Active Gas Survey (MAGS) at the Fashion Cleaners (Former) site located at 6502 Massachusetts Avenue, New Port Richey, Pasco County, Florida (ERIC_5245). The work is being performed under the FDEP's Drycleaning Solvent Cleanup Program, with Skylar Murphy serving as the Department's Project Manager and Nana G. Westmark as the Contractor's Project Manager.

The scope of work includes installation of eight MAGS monitoring wells at specified depths ranging from 1 to 28 feet below land surface, conducting deep zone MAGS testing to evaluate soil contamination, and preparing a Supplemental Site Assessment Report. The total task assignment value is $41,483.74 on a fixed unit rate basis. Project deliverables include IDW manifests, subcontractor receipts, field documentation of MAGS installation and testing, and a Supplemental Site Assessment Report, all due by February 23, 2023. Full invoice payment of $41,483.74 is due upon FDEP approval of all deliverables. The task assignment completion date is May 25, 2023. The cost estimate includes labor ($14,277.94), drilling services ($16,240.00), investigative derived waste disposal ($1,250.00), laboratory analysis ($2,014.00), travel and equipment expenses ($4,525.00), and a completion fee ($1,427.80).

View the file

Other files

File Type Posted
CN-370000-HW686-DC001D.pdf PDF
CN-370000-HW686-DC002A.pdf PDF
CN-370000-HW686-DC002F.pdf PDF
CN-370000-HW686-DC002G.pdf PDF
CN-370000-HW686-DC002H.pdf PDF
CN-370000-HW686-DC003A.pdf PDF
CN-370000-HW686-DC003B.pdf PDF
CN-370000-HW686-DC003E.pdf PDF
CN-370000-HW686-DC003G.pdf PDF
CN-370000-HW686-DC004C.pdf PDF
CN-370000-HW686-DC004E.pdf PDF
CN-370000-HW686-DC007A.pdf PDF
CN-370000-HW686-DC007C.pdf PDF
CN-370000-HW686-DC007D.pdf PDF
CN-370000-HW686-DC009C.pdf PDF
CN-370000-HW686-DC009E.pdf PDF
CN-370000-HW686-DC010C.pdf PDF
CN-370000-HW686-DC011A.pdf PDF
CN-370000-HW686-DC012B.pdf PDF
CN-370000-HW686-DC013A.pdf PDF
CN-370000-HW686-DC014A.pdf PDF
CN-370000-HW686-DC016A.pdf PDF
CN-370000-HW686-DC018A.pdf PDF
CN-370000-HW686-DC019B.pdf PDF
CN-370000-HW686-DC01ACO4.pdf PDF
CN-370000-HW686-DC020C.pdf PDF
CN-370000-HW686-DC023A.pdf PDF
CN-370000-HW686-DC024A.pdf PDF
CN-370000-HW686-DC025A.pdf PDF
CN-370000-HW686-DC026B.pdf PDF
CN-370000-HW686-DC028A.pdf PDF
CN-370000-HW686-DC03DCO2.pdf PDF
CN-370000-HW686-DC04ECO1.pdf PDF
CN-370000-HW686-DC07BCO1.pdf PDF
CN-370000-HW686-DC07BCO3.pdf PDF
CN-370000-HW686-DC09DCO1.pdf PDF
CN-370000-HW686-DC11BCO1.pdf PDF
CN-370000-HW686-DC13BCO1.pdf PDF
CN-370000-HW686-DC14BCO3.pdf PDF
CN-370000-HW686-DC14DCO1.pdf PDF
CN-370000-HW686-DC15BCO1.pdf PDF
CN-370000-HW686-DC15DCO1.pdf PDF
CN-370000-HW686-DC16BCO1.pdf PDF
CN-370000-HW686-DC18CCO1.pdf PDF
CN-370000-HW686-DC21BCO1.pdf PDF
CN-370000-HW686-DC27BCO1.pdf PDF
CN-370000-HW686-FIL10.pdf PDF
CN-370000-HW686-FIL6.pdf PDF
CN-370000-HW686-FIL9.pdf PDF
CN-370000-HW686-HW002A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW686

DC007B Completion May 25, 2023

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to conduct a deep MAGs Survey in accordance with the PSI scope of work, cost estimate, and schedule received on September 14 2022.

Skylar Murphy 850-245-8795 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Professional Service Industries, Inc. (Intertek-PSI)

Professional Service Industries, Inc. (Intertek-PSI)

Nana G. Westmark 813-886-1075

ERIC_5245

6502 Massachusetts Avenue New Port Richey, Pasco County, Florida 34653

Fashion Cleaners (Former)

✔ $ 41,483.74

$ 41,483.74

Scope of Work

Nana Westmark

Senior Geologist / Principal Consultant

Nana G Westmark Digitally signed by Nana G Westmark Date: 2022.09.23 15:22:47 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2022.09.16 10:03:50 -04'00'

N/A

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtasks 2 & 3: IDW Manifests, Subcontractor Receipts, and Field Documentation of MAGS installation and testing. 02/23/2023

Subtasks 4 &1: Supplemental Site Assessment Report and Project Management 02/23/2023

Subtasks 1-4 submittal and FDEP approval of the Supplemental Site Assessment Report AND IDW Manifests, Subcontractor Receipts, and Field Documentation of MAGS installation and testing AND PM

$ 41,483.74

$ 41,483.74

HW686

DC007B

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To: HW686 Contract Negotiation File Fashion Dry Cleaners New Port Richey, Pasco County

ERIC_5245

From: Skylar Murphy, Project Manager Date: September 15, 2022 Subject: Negotiation Summary

HW686 DC007B

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to conduct a Deep MAGs Survey in accordance with the PSI scope of work, cost estimate, and schedule received on September 14th, 2022.

PSI confirmed on September 14th, 2022, that an Access Agreement with the current real property owner of the Fashion Dry Cleaners (ERIC_5245) site has been executed.

Design approval was verbally received from Robert Huckaby P.E. following the recommended edits to the scope of work. the email is included on the following page.

The original Task Assignment totaled $40,681.52 with 156 labor hours but after negotiations and corrections with contractor costs are reflected as below:

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $41,483.74 with 159.5 labor hours. The increase in price is due modifications in the location and depth of MAGs wells.

PSI may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

Printed on recycled paper.

From: Huckaby, Robert To: Schwed, Skylar L Subject: RE: Fashion MAGs Proposal Date: Monday, September 12, 2022 9:21:07 AM

Skylar, I do have some edits that need to be made. I am going to list the MAGS Well Installation changes in PSI’s proposal format.

Eight MAGS wells should be installed and tested in the following locations:

1. New MAGs screened from 1 – 8 feet bls, near SB005

2. New MAGS screened from 9- 20 feet bls, near SB005

3. New MAGS screened from 1 - 8 feet bls, near SB006

4. New MAGS screened from 9 – 20 feet bls, near SB006

5. New MAGS screened from 22 – 27 feet bls, near SB006

6. New MAGS screened from 9 – 17 feet bls, near SB004

7. New MAGS screened from 18 - 28 feet bls, near SB004

8. New MAGS screened from 9 – 17 feet bls, near SB001

The key edits to PSI’s proposal are that:

A shallow MAGS well should be installed near SB005 since we may not be able to hook the interior shallow MAGS well in this area to a system in the future, and Because the existing shallow MAGS wells are screened to a depth of 8-feet bls, the intermediate depth MAGS wells screen should start at 9-feet bls. This will give a 1-foot buffer between the bottom of the shallow screen and the top of the intermediate screen which will hopefully prevent short circuiting between these wells.

Please let me know if you have any questions. Thanks

Robert

Robert Huckaby, P.E., BCEE Florida Department of Environmental Protection Waste Management/Waste Site Cleanup Section Professional Engineer I Robert.Huckaby@FloridaDEP.gov Office: 850-245-8956

From: Schwed, Skylar L <Skylar.Schwed@FloridaDEP.gov> mailto:Robert.Huckaby@FloridaDEP.gov mailto:Skylar.Schwed@FloridaDEP.gov mailto:Robert.Huckaby@FloridaDEP.gov

Sent: Wednesday, September 7, 2022 9:39 AM To: Huckaby, Robert <Robert.Huckaby@FloridaDEP.gov> Subject: Fashion MAGs Proposal

Hey Robert, Before I go ahead and look into tasking this I want to ensure all of your questions and concerns were accurately addressed. Please let me know if any edits should be made or if it looks good to you.

Best, Skylar Schwed Environmental Specialist II Florida Department of Environmental Protection Division of Waste Management Waste Cleanup Program Skylar.L.Murphy@FloridaDEP.gov Office: 850-245-8795 P Save a tree, please don't print this e-mail unless necessary mailto:Skylar.L.Murphy@FloridaDEP.gov

PSI Proposal Number: 0552-382310 – Rev 1

September 7, 2022, revised September 14, 2022 www.intertek.com/building

Professional Service Industries, Inc.

5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634

Phone: (813) 886-1075 Fax: (813) 249-4916

Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Attention: Ms. Skylar Schwed, Environmental Specialist II Phone: (850) 245-8705 main, (850) 245-8795 direct Email: Skylar.Schwed@FloridaDEP.gov

Re: Proposal for Supplemental Site Assessment – 2 – Revision 1 Deep MAGS Survey Fashion Cleaners (Former) 6502 Massachusetts Avenue New Port Richey, Pasco County, Florida 34653

ERIC_5245

Dear Ms. Schwed:

Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to provide a Supplemental Site Assessment – 2 to consist of a Modified Active Gas Survey (MAGS) for the predominately deeper vadose zone for the Fashion Cleaners at 6502 Massachusetts Avenue, New Port Richey, Florida. Included with this proposal is a discussion of project history to date, proposed scope of work, cost estimate and a proposed schedule for completion. A Site Access Agreement was signed by Mr. Trent Goss in June 2019, who is listed as the registered agent for the current property owner, according to the Pasco County Property Appraiser’s website.

PROJECT BACKGROUND

The Fashion Cleaners (Former) was located in the East Richey Square Shopping Center on the southeast corner of Massachusetts Avenue and Congress Street in New Port Richey, Pasco County, Florida. The Fashion Cleaner operated in the westernmost tenant space in the shopping center which currently houses a bar, the Home Saloon. Based on the FDEP records, drycleaning began at the facility in 1978 and utilized perchloroethene (PCE) as the drycleaning solvent. The drycleaner operated from 1978 to approximately 2007 or 2008. No drycleaning equipment remains on-site. A Site Screening Report dated January 30, 1997 was submitted which identified PCE in a soil sample at 57 ug/kg (0.057 mg/kg) at a depth of 2.5 feet below land surface (bls) outside the back door of the facility.

mailto:Skylar.Schwed@FloridaDEP.gov

FDEP – Fashion Cleaners ERIC_5245 PSI Proposal No. 0552-382310- Rev 1

September 7, 2022, revised September 14, 2022 www.intertek.com/building

PSI completed Site Assessment activities in November 2020 through February 2021, with a Site Assessment Report submitted in March 2021. The results identified low-level PCE concentrations (below SCTLs) within the 0.5-2 feet bls to 8-10 feet bls intervals from soil samples collected beneath the building and soil samples collected outside of the former drycleaning tenant space. A MAGS study from January 2021 was conducted in the upper vadose zone which revealed elevated PCE concentrations above the Department’s guidance value of 1.0 mg/m3 for SVE implementation.

A second round of MAGS testing was conducted in August 2021 which revealed similar VOH air concentrations. During recent technical discussions between the FDEP and PSI, it was agreed to evaluate the deeper vadose zone prior to any active remediation plans, and to augment any previous data gaps in the upper vadose zone.

PSI is, therefore, proposing to conduct a deeper MAGS study to address the data gaps.

PROPOSED SCOPE OF WORK

The proposal contained herein consists of installing MAGS wells at select locations and conducting a MAGS test at the Fashion Cleaners. The results will be used to confirm current soil quality conditions and to evaluate if a contaminant mass is located in the vadose zone at deeper areas. Specifically, the proposed scope of work consists of the following subtasks:

1. Project Management

This scope is provided for in the template worksheets.

2. MAGS Well Installation

PSI will provide oversight of a licensed water well contractor to install eight (8) MAGS wells. The MAGS are proposed to be installed and tested at the following locations.

1. New MAGs screened from 1 – 8 feet bls, near SB005

2. New MAGS screened from 9- 20 feet bls, near SB005

3. New MAGS screened from 1 - 8 feet bls, near SB006

4. New MAGS screened from 9 – 20 feet bls, near SB006

5. New MAGS screened from 22 – 27 feet bls, near SB006

6. New MAGS screened from 9 – 17 feet bls, near SB004

7. New MAGS screened from 18 - 28 feet bls, near SB004

8. New MAGS screened from 9 – 17 feet bls, near SB001

September 7, 2022, revised September 14, 2022 www.intertek.com/building

The proposed MAGS wells will be constructed of 2- inch diameter Schedule 40 PVC, with similar riser. A filter pack and bentonite seal will be emplaced, and the well will be constructed with a 10 – 12-inch manhole cover with an approximate 4 to 6 - inch clearance space between the grout and the manhole cover to allow a compression fitting to conduct the MAGS test. Once the MAGS wells are installed, a MAGS test will be conducted to evaluate potential contaminant sources.

Three drilling firms (Huss Drilling, Groundwater Protection, and Preferred Drilling) were solicited for price proposals to install the wells, which are attached. Groundwater Protection (a division of DrillPro) was selected to perform the work based on price and our previous experience with the firm.

The wells will be constructed such that the MAGS wells may be converted to Soil Vapor Extraction (SVE) wells in the event that an SVE remediation strategy is necessary. Any investigative derived waste (IDW) will be containerized in 55-gallons drums, labeled for date of generation, and transported off-site for disposal at an approved facility.

3. MAGS Test

PSI will conduct a deep zone MAGS test using the newly installed wells to evaluate the extent of soil contamination and contaminant source identification. A regenerative blower and generator will be utilized to conduct the MAGs test. Flexible hose will be brought on-site to allow for the extraction of each MAGs point by the system. A high-speed peristaltic pump will be connected to the vapor sampling point to allow for continuous vapor screening with a MiniRAE 3000 OVA-PID or equivalent.

During each MAG point test, flow rate, well-head vacuum, and vacuum influence (measured from other MAG points, existing vacuum monitoring points and the horizontal SVE wells) will be measured at select time intervals.

The vacuum will be varied at the well head, starting from a low applied vacuum and incrementally increasing the vacuum. During each applied vacuum, the vapor flow rate will be measured for the purpose of determining the relationship of applied vacuum to flow rate. During this test, at each vacuum level, the vacuum influence will be measured from the nearby MAGs points to assess the Radius of Influence

(ROI).

Vapor samples will be collected using SUMMA® canisters for analysis of volatile organic compounds using EPA Method TO-15. It is anticipated that one vapor sample will be collected for each well head test. The sample will be at the end of the test.

4. Data Evaluation and Report Development

A Supplemental Site Assessment Report – 2 will be generated for the MAGS well installation and testing event. The data generated from the above described services will be tabulated and inserted onto maps at each specific test point. Tables will be generated summarizing the data collected from each MAG point and monitoring well. Conclusions and recommendations will be provided for the next appropriate action.

The reports will be signed and sealed by a Professional Engineer or Professional Geologist certified in the State of Florida.

September 7, 2022, revised September 14, 2022 www.intertek.com/building

The deliverable and invoice schedule is as follows.

Fashion ERIC_5245 Deliverables

Deliverables Deliverable Due Date SubTask 1 Project Management Upon completion of Task Assignment SubTask 2 MAGS Well Installation February 25, 2023 SubTask 3 MAGS Testing February 25, 2023 SubTask 4 Supplemental Site Assessment Report - 2 February 25, 2023

Invoice Schedule

Requirements for Invoice Submittal Amount to be Invoiced SubTasks 1, 2, 3, & 4- Submittal & approval of SSA-2, & IDW manifest

$41,581.46

COST ESTIMATE AND SCHEDULE

The estimated cost to perform the MAGS Well Installation and Test is shown on the attached Cost Estimate and Level of Effort sheets, which includes the report deliverable. All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No. HW686, Bureau of Waste Cleanup, dated December 21, 2021. We anticipate performing the MAGS well installation and testing in November 2022, depending on driller availability and the tenant schedule, and a report deliverable will be provided in February 2023. The IDW manifest copy will be provided upon receipt.

PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075 or (813) 267-2519.

Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.

Michael Rothenburg, PE, CIH Nana Westmark, PG, CHMM Senior Engineer Senior Geologist / Contract Manager

Enclosures: Cost Estimate Level of Effort Drilling Bids

Z:\552-Env\FDEP HW 686 Drycleaning, Main Contract\0552------Fashion Deep MAGs\Proposals\Fashion ERIC_5245 Deep MAGS 0552-382310.docx

FDEP COST ESTIMATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date:

Task #: SubTask 1 Project Management SubTask 6

Site: Fashion ERIC_5245 SubTask 2 MAGS Well Installation SubTask 7

Activity/Phase: MAGS - Deep Zone SubTask 3 MAGS Testing SubTask 8

Project Manager: Nana Westmark SubTask 4 Supplemental Site Assessment Report - 2 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$56.99 Project Manager 12 11.5 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0

$62.64 Senior Engineer, MR 8.5 0 4 4.5 0 0 0 0 0 0 $56.99 Senior Geologist, NW 4 4 0 0 0 0 0 0 0 0

$0.00 Senior Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Certified Industrial Hygientist 0 0 0 0 0 0 0 0 0 0 $0.00 Certified Hazardous Materials Manager 0 0 0 0 0 0 0 0 0 0 $0.00 Florida Licensed Asbestos Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Manager 0 0 0 0 0 0 0 0 0 0

$36.06 Project Engineer 0 0 0 0 0 0 0 0 0 0 $38.20 Project Engineer, IK 51 0 29 22 0 0 0 0 0 0 $30.56 Project Engineer, MK 0 0 0 0 0 0 0 0 0 0 $37.02 Project Engineer, SJ 0 0 0 0 0 0 0 0 0 0 $33.74 Project Scientist, SB 0 0 0 0 0 0 0 0 0 0 $29.86 Project Scientist 0 0 0 0 0 0 0 0 0 0 $29.77 Project Scientist, RF 27 27 0 0 0 0 0 0 0 0

$0.00 QA Officer 0 0 0 0 0 0 0 0 0 0 $31.51 Remediation Specialist, RH 27 0 27 0 0 0 0 0 0 0 $24.94 GIS / CAD Specialist, BW 3 0 0 3 0 0 0 0 0 0

$0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0 $0.00 Staff Geologist 0 0 0 0 0 0 0 0 0 0

$24.94 Staff Scientist, BW 0 0 0 0 0 0 0 0 0 0 $30.91 Environmental Specialist, CC 0 0 0 0 0 0 0 0 0 0 $22.06 Environmental Specialist, MZ 27 0 27 0 0 0 0 0 0 0

$20.81 Administrative Assistant, BM 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 159.5 12 31 87 29.5 0 0 0 0 0 0

Direct Labor $5,687.97 $654.37 $1,031.75 $2,804.75 $1,197.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 151.02% $8,589.97 $988.23 $1,558.15 $4,235.73 $1,807.86 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $14,277.94 $1,642.60 $2,589.90 $7,040.48 $3,004.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

9/7/2022 revised 9/14/2022, and 9/15/2022

REV: 02/03 CEF Intertek-PSI Page 1

FDEP COST ESTIMATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date:

Task #: SubTask 1 Project Management SubTask 6

Site: Fashion ERIC_5245 SubTask 2 MAGS Well Installation SubTask 7

Activity/Phase: MAGS - Deep Zone SubTask 3 MAGS Testing SubTask 8

Project Manager: Nana Westmark SubTask 4 Supplemental Site Assessment Report - 2 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

9/7/2022 revised 9/14/2022, and 9/15/2022

Travel Vehicle Rental $1,320.00 $240.00 $1,080.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,320.00 $240.00 $1,080.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $16,240.00 $16,240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $1,250.00 $1,250.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $17,490.00 $17,490.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,749.00 $1,749.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $19,239.00 $19,239.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $1,864.00 $0.00 $1,864.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,014.00 $0.00 $2,014.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $200.00 $80.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $3,005.00 $650.00 $2,355.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,205.00 $730.00 $2,475.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $40,055.94 $1,642.60 $22,798.90 $12,609.48 $3,004.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,427.80 $164.26 $258.99 $704.05 $300.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $41,483.74 $1,806.86 $23,057.89 $13,313.53 $3,305.46 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF Intertek-PSI Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Fashion ERIC_5245 SubTask 2 MAGS Well Installation DATE: 9/7/2022 revised 9/14/2022, and 9/15/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist, N Westmark Technical Assistance 3 Notification to tenants 1

Project Scientist, R Fetter Field preparation 1 Travel (4 hr roundtrip) 8 Provide oversight for MAGS well installation 16 Stage IDW 2

TOTAL LABOR 31

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck $120.00 day 2 $240.00

$0.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

Groundwater Protection Well installation 1 $16,240.00 $16,240.00

Petrotech Southeast 10 $125.00 $1,250.00

$0.00

TOTAL $17,490.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00

$0.00 0 $0.00

$0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00

Well installtion kit $325.00 day 2 $650.00

$650.00 Expendables $40.00 day 2 $80.00

TOTAL EQUIPMENT $730.00

IDW pickup, transport, disposal, water, per drum

FINAL --7/24/96

Page 3 Rev 2 Fashion ERIC_5245 Deep MAGS 0552-382310

SubTask 3 MAGS Testing DATE: 9/7/2022 revised 9/14/2022, and 9/15/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg Technical Assistance 3 Notification to tenants 1

Environmental Specialist, M Zilske Travel (3 roundtrip) 12 Set up existing system for MAGS 3 Well head assembly set-up 1 Operate MAGS event (1 hrs - 8 points) 8 Collect measurements from other wells 3

Remediation Specialist, R Hanson

Travel (3 roundtrip) 12 Set up existing system for MAGS 3 Well head assembly set-up 1 Operate MAGS event (1 hrs - 8 points) 8 Site Restoration outside building 3

Project Engineer, I King Travel (3 roundtrip) 12 Technical review of data during testing 3 Collect vacuum and flow readings (1 hrs / point - 8 points) 8 Dismantle MAGS equipment 2 Written documentation of data collection 4

TOTAL LABOR 87

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck Environmental Specialist $120.00 day 3 $360.00 Equipment Van / Truck Remediation Specialist $120.00 day 3 $360.00 Equipment Van / Truck Project Engineer $120.00 day 3 $360.00

$0.00

TOTAL VEHICLE $1,080.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00

TO-15 $200.00 8 $1,600.00

Summa Canister $33.00 8 $264.00

$1,864.00 $0.00 Sample Shipping Large, overnight $150.00 1 $150.00

$0.00

TOTAL LAB $2,014.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00

Construction Pilot Test Kit $360.00 day 3 $1,080.00 Portable Generator $70.00 day 3 $210.00 Regen Blower $180.00 day 3 $540.00 GPS $175.00 day 3 $525.00

$2,355.00 Expendables $40.00 day 3 $120.00

TOTAL EQUIPMENT $2,475.00

Page 4 Rev 2 Fashion ERIC_5245 Deep MAGS 0552-382310

SubTask 4 Supplemental Site Assessment Report - 2 DATE: 9/7/2022 revised 9/14/2022, and 9/15/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg Evaluate data 2 Make Recommendations for report 2 Sign and seal document 0.5

4.5

Project Engineer, I King Data reduction/evaluation 8 Preparation of Supplemental Assessment report 8 Report - Prepare final tables and figures 5 Provide ADaPT package 1

GIS/CADD Specialist, B Walker Develop maps 3

TOTAL LABOR 29.5

VEHICLE TYPE RATE UNIT USEAGE

$0.00

$0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL EQUIPMENT $0.00

Page 5 Rev 2 Fashion ERIC_5245 Deep MAGS 0552-382310

Professional Service Industries, Inc. (PSI) Request for Quotation

Facility Name Fashion Cleaners (Former) Facility Location 6502 Massachusetts Avenue, New Port Richey, Pasco County Facility ID ERIC_5245 FDEP Drycleaning Solvent Cleanup Program

GP Proposal #822080 - Rev 2

Units Unit Rate Extended Price

1 1,500.00$ 1,500.00$

Per Diem (3 Man Crew) 2 375.00$ 750.00$

2 4,250.00$ 8,500.00$

145 12.00$ 1,740.00$

2' x 2' Concrete Pad w/12" BD Completion 8 175.00$ 1,400.00$

Well Development (up to 1/2 hour w/Air) 8 75.00$ 600.00$

Bobcat for IDW and Tooling Management 1 1,000.00$ Included

Water Meter Rental and Use (If Needed) 500.00$

Ground Penetrating Radar for utility locate 1 800.00$ 800.00$

New 55-gallon DOT approved drums (each) 10 95.00$ 950.00$

Completion: 2 Days Total: 16,240.00$

Company Name: Groundwater Protection Address: 2300 Silver Star Road, Orlando, FL 32804 Phone: 407-426-7885 Email: todd@drillprollc.com Contact: Todd Hodgson

Todd Hodgson, Partner

Utility locates on Private Property are the responsibility of the client Damage to utilities on private property during borehole clearance are the responsibility of the client

Deep wells are to be installed approximately one foot above water table if water table is encountered.

Water table estimated at ~30 feet bls.

Leave 6 inch clearance between grout and manhole cover (so that a compression fitting can be installed later) Install well pipe in the center of manhole to allow room to modify later.

Proposed Scope of Work: Sonic Drilling Required Installation of eight (8) MAGS Wells (vapor monitoring wells).

(2) 2" x 8' Sch 40 PVC Mag Well w/7' of .010 Slot Screen, 12" BD Completion w/2' x 2' Pad.

(2) 2" x 20' Sch 40 PVC Mag Well w/11' of .010 Slot Screen, 12" BD Completion w/2' x 2' Pad.

(2) 2" x 17' Sch 40 PVC Mag Well w/8' of .010 Slot Screen, 12" BD Completion w/2' x 2' Pad.

(1) 2" x 28' Sch 40 PVC Mag Well w/10' of .010 Slot Screen, 12" BD Completion w/2' x 2' Pad.

(1) 2" x 27' Sch 40 PVC Mag Well w/5' of .010 Slot Screen, 12" BD Completion w/2' x 2' Pad.

Mobilization (lump sum)

Sonic Rig and Crew

Materials: 2" Sch 40 PVC Well Installation

Note: It is Groundwater Protection policy that if 'Pea Gravel' is encountered, ANY type of boring/drilling will be terminated immediately and the boring location will need to be relocated to a clear location by the client.

Borehole Clearance to 5’ bgs beyond 20 minutes may require a change order for additional time and cost.

Page 1 of 3 Rev 2 Groundwater Protection Intertek Revised 822080 Bid Form

Professional Service Industries, Inc. (PSI) Request for Quotation

Facility Name Fashion Cleaners (Former) Facility Location 6502 Massachusetts Avenue, New Port Richey, Pasco County Facility ID ERIC_5245 FDEP Drycleaning Solvent Cleanup Program

Units Unit Rate Extended Price

1 950.00$ 950.00$

Ground Penetrating Radar for utility locate 1 1,375.00$ 1,500.00$

2 4,500.00$ 9,000.00$

137 25.00$ 3,425.00$

7 200.00$ 1,400.00$

55-gallon DOT approved drums (each) 10 70.00$ 700.00$

Total: 16,975.00$

Facility is a saloon and parking is tight.

Asphalt surface.

Signed PSI Purchase Order with General Conditions (attached) is required before working.

All equipment to be decontaminated prior to boring / well installation.

OSHA HazWOPER trained crew required.

Include per diem in cost, if necessary.

Estimated start date: November 2022

Company Name: Preferred Drilling Solutions, Inc.

Address: 8820 66th Street North, Pineallas Park, FL 33782 Phone: 727-561-7477 Email: kevin@pdsflorida.com Contact: Kevin Bonacum

Name, Title.

Vault Construction

6. All wells will be two inch diameter, with Schedule 40 PVC, with filter pack and bentonite seal.

7. Deep wells are to be installed approximately one foot above water table if water table is encountered.

8. Water table estimated at ~30 feet bls.

9. Needs 12" manhole cover.

10. Leave 6 inch clearance between grout and manhole cover (so that a compression fitting can be installed later)

11. Install well pipe in the center of manhole to allow room to modify later.

Proposed Scope of Work: Sonic Drilling Required Installation of seven (7) MAGS Wells (vapor monitoring wells).

1. One well - screened from 1 - 8 feet bls.

2. Two wells - screened from 8 - 20 feet bls.

3. Two wells - screened from 8 - 17 feet bls.

4. One well - screened from 18 - 28 feet bls.

5. One well - screened from 22 - 27 feet bls.

Mobilization (lump sum)

Gas Wells (Materials and Install), per foot

Rig Charge (per day)

Page 1 of 3 Intertek-PSI, Fashion Cleaners, New Port Richey, FL

From: Stephanie Stallsmith To: Nana Westmark; Kevin Bonacum; Brian Shutts Subject: [External] RE: Invitation to provide price quote for sonic drilling in New Port Richey for PSI under drycleaning program Date: Monday, August 29, 2022 10:13:37 AM Attachments: image001.png

Hello, Thank you for reaching out to Huss Drilling Inc concerning your environmental project. At this time we are suspending our Environmental Drilling Operations until further notice. We will continue to focus on our Exploration, Water Resources, Residential Water Wells, and Well Abandonment Services. We apologize for any inconvenience this may cause. Feel free to call our office with any questions at 352-567-9500. Thank you. – RJ Huss

Stephanie Stallsmith Huss Drilling, Inc.

35920 SR 52

Dade City, Fl. 33525

(352) 567-9500

From: Nana Westmark <nana.westmark@intertek.com> Sent: Thursday, August 25, 2022 3:43 PM To: Stephanie Stallsmith <stephanie@hussdrilling.com>; Kevin Bonacum <kevin@pdsflorida.com>;

Brian Shutts <brian@drillprollc.com> Subject: Invitation to provide price quote for sonic drilling in New Port Richey for PSI under drycleaning program

Good Afternoon – Hope everyone is well these crazy days.

PSI is working for the FDEP under the Drycleaning Solvent Cleanup Program and will be installing 7 vapor monitoring wells near an old drycleaner.

The site is now a bar, but we will be outside. The area of work is asphalt, near the side of the building. See attached map.

Project: Fashion Cleaners (now the Home Saloon) 6502 Massachusetts Avenue New Port Richey, Pasco County, Florida 34653

ERIC_5245

Since we will be drilling into the limestone, I think we need a sonic rig.

If you are interested, please fill out the attached sheet and send back to me. I would like to have this to me by next Thursday, September 1, 2022, by COB.

mailto:stephanie@hussdrilling.com mailto:nana.westmark@intertek.com mailto:kevin@pdsflorida.com mailto:brian@drillprollc.com

Feel free to contact me with any question. I have attached an Excel spreadsheet for ease of calculation, but when sending back to me, please pdf it and sign.

Kind Regards, Nana Westmark, PG, CHMM Senior Geologist / Principal Consultant Building & Construction Intertek-PSI

Please Note: As of October 12, 2018, my email address will change to:

Nana.Westmark@intertek.com.

Direct 813 – 886 – 1075 Ext 219 Mobile 813 - 267 - 2519 Office 813 – 886 – 1075 Email Nana.Westmark@intertek.com Skype Nana.Westmark.Intertek www.intertek.com/building [gcc02.safelinks.protection.outlook.com] [gcc02.safelinks.protection.outlook.com]

Intertek-PSI 5801 Benjamin Center Drive, Suite 112 Tampa, Florida 33634

Join BBEB.com to build back an ever better world!

[bbeb.com]

Total Quality. Assured.

CONFIDENTIALITY NOTICE

This email may contain confidential or privileged information, if you are not the intended recipient, or the person responsible mailto:Nana.Westmark@intertek.com mailto:Nana.Westmark@intertek.com https://urldefense.com/v3/__https:/gcc02.safelinks.protection.outlook.com/?url=https*3A*2F*2Furldefense.com*2Fv3*2F__https*3A*2Fgcc02.safelinks.protection.outlook.com*2F*3Furl*3Dhttp*3A*2F*2Fwww.intertek.com*2Fbuilding*26data*3D04*7C01*7C*7Ce6e60d91fd384023f38108d9fc50956c*7Cf82250c421b643ada0095dbf5b6ad62d*7C0*7C0*7C637818245314857152*7CUnknown*7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0*3D*7C3000*26sdata*3DvRbGaonR2CbnFAS0Dca4ptkjW7icXh66E0j0*2Fp*2BJ13I*3D*26reserved*3D0__*3BJSUlJSUlJSUlJSUlJSUlJSUl!!Ie6nUkZk!8l7e3Y_9sJi7T5snTt9AB9T_Ax7YUUjuMGVVA-7CA4KCgIJ_Ne3ClV4iOvUZ8FSSn-xc*24&data=04*7C01*7C*7Cc4fcae041bcf49265f2808d9fc6ec1a8*7Cf82250c421b643ada0095dbf5b6ad62d*7C0*7C0*7C637818374916215896*7CUnknown*7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0*3D*7C3000&sdata=dPp*2BTVIDjNbYdwX0119sREuLath0qcAcEMHjGoPCymU*3D&reserved=0__;JSUlJSUlJSUlJSoqKiolJSoqKioqKioqKioqJSUqKiolJSUlJSUlJSUlJSUlJSUlJQ!!Ie6nUkZk!95zq0GPNR51LtfeZmnlqP7itfu4z7831lpWaoMqh49FmYhrXRV39llJQruqRDrG0SAP6$ https://urldefense.com/v3/__https:/gcc02.safelinks.protection.outlook.com/?url=https*3A*2F*2Furldefense.com*2Fv3*2F__https*3A*2Fgcc02.safelinks.protection.outlook.com*2F*3Furl*3Dhttp*3A*2F*2Fwww.intertek.com*2Fbuilding*26data*3D04*7C01*7C*7Ce6e60d91fd384023f38108d9fc50956c*7Cf82250c421b643ada0095dbf5b6ad62d*7C0*7C0*7C637818245314857152*7CUnknown*7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0*3D*7C3000*26sdata*3DvRbGaonR2CbnFAS0Dca4ptkjW7icXh66E0j0*2Fp*2BJ13I*3D*26reserved*3D0__*3BJSUlJSUlJSUlJSUlJSUlJSUl!!Ie6nUkZk!8l7e3Y_9sJi7T5snTt9AB9T_Ax7YUUjuMGVVA-7CA4KCgIJ_Ne3ClV4iOvUZ8FSSn-xc*24&data=04*7C01*7C*7Cc4fcae041bcf49265f2808d9fc6ec1a8*7Cf82250c421b643ada0095dbf5b6ad62d*7C0*7C0*7C637818374916215896*7CUnknown*7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0*3D*7C3000&sdata=dPp*2BTVIDjNbYdwX0119sREuLath0qcAcEMHjGoPCymU*3D&reserved=0__;JSUlJSUlJSUlJSoqKiolJSoqKioqKioqKioqJSUqKiolJSUlJSUlJSUlJSUlJSUlJQ!!Ie6nUkZk!95zq0GPNR51LtfeZmnlqP7itfu4z7831lpWaoMqh49FmYhrXRV39llJQruqRDrG0SAP6$ https://urldefense.com/v3/__https://www.bbeb.com/__;!!Ie6nUkZk!oD-JNQR6D4GGmxE4Ex1sVJvFlJ28guMeTS11UFiGD0LjhmrwwjY0LPiBZUjNN7qbuZX3RajHnGoLZsiCJDXbGCT6avA$ https://urldefense.com/v3/__https://www.bbeb.com/__;!!Ie6nUkZk!oD-JNQR6D4GGmxE4Ex1sVJvFlJ28guMeTS11UFiGD0LjhmrwwjY0LPiBZUjNN7qbuZX3RajHnGoLZsiCJDXbGCT6avA$ for delivering the message to the intended recipient then please notify us by return email immediately. Should you have received this email in error then you should not copy this for any purpose nor disclose its contents to any other person.

http://www.intertek.com

This message is from an EXTERNAL SENDER - please be CAUTIOUS, particularly with links and attachments.

http://www.intertek.com/

PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment

Advantage Environmental IDW

Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various

Description of Service

Tampa Area Orlando - Central

Florida Jacksonville Area, North Florida

South Florida (Miami, Fort

Myers, Naples) Florida Panhandle water $235.00 $235.00 --- --- ---soil $235.00 $235.00 --- --- ---low volume fee (< 6 drums) --- --- --- Pick-up fee --- --- --- Per diem --- --- --- ---

Water, per drum $235.00 $235.00 --- --- --- Soil, per drum $235.00 $235.00 --- --- ---

1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.

2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste

5. ) Waste is considered not hazardous.

6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.

7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.

State of Florida

Description 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.

3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.

The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.

4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Bureau of Waste Cleanup,Hazardous Waste Cleanup Section.

Page 1 of 3 PSI IDW Quotes 3-29-2022

&ƌŽŵ͗�ŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵ ^ĞŶƚ͗�dŚƵƌƐĚĂLJ͕�:ĂŶƵĂƌLJ�Ϯϳ͕�ϮϬϮϮ�ϭ͗Ϭϭ�WD dŽ͗�EĂŶĂ�tĞƐƚŵĂƌŬ ^ƵďũĞĐƚ͗�Z�͗��džƚĞƌŶĂů�Z�͗��ŶŶƵĂů�/�t�ƉƌŝĐĞƐ�ĨŽƌ�&��W��ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚ�ĨŽƌ�W^/�dĞĂŵ� dŚĞ�ůŽǁ�ǀŽůƵŵĞ�ƉŝĐŬ�ƵƉ�ŝƐ�ƚŚĞ�ΨϮϯϱ�ŝƚ�ŝŶĐůƵĚĞƐ�ƐƚŽƉ�ĐŚĂƌŐĞ�ĂŶĚ�ůŽǁ�ǀŽůƵŵĞ

&ƌŽŵ͗ EĂŶĂ�tĞƐƚŵĂƌŬ�фŶĂŶĂ͘ǁĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵх� ^ĞŶƚ͗tĞĚŶĞƐĚĂLJ͕�:ĂŶƵĂƌLJ�Ϯϲ͕�ϮϬϮϮ�ϲ͗ϱϵ��D dŽ͗ ƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵ �Đ͗ ŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵ ^ƵďũĞĐƚ͗ Z�͗��džƚĞƌŶĂů�Z�͗��ŶŶƵĂů�/�t�ƉƌŝĐĞƐ�ĨŽƌ�&��W��ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚ�ĨŽƌ�W^/�dĞĂŵ�

'ŽŽĚ�DŽƌŶŝŶŐ�ʹ tĂƐŶ͛ƚ�ƐƵƌĞ�ŝĨ�LJŽƵ�ǁĂŶƚĞĚ�ƚŽ�ĐůĂƌŝĨLJ�ƚŚŝƐ͍

WůĞĂƐĞ�ůĞƚ�ŵĞ�ŬŶŽǁ͘ dŚĂŶŬƐ

EĂŶĂ

EĂŶĂ�tĞƐƚŵĂƌŬ͕�W'͕��,DD ^ĞŶŝŽƌ�'ĞŽůŽŐŝƐƚ�ͬ�WƌŝŶĐŝƉĂů��ŽŶƐƵůƚĂŶƚ �ƵŝůĚŝŶŐ�Θ��ŽŶƐƚƌƵĐƚŝŽŶ /ŶƚĞƌƚĞŬͲW^/

WůĞĂƐĞ�EŽƚĞ͗ �Ɛ�ŽĨ�KĐƚŽďĞƌ�ϭϮ͕�ϮϬϭϴ͕�ŵLJ�ĞŵĂŝů�ĂĚĚƌĞƐƐ�ǁŝůů�ĐŚĂŶŐĞ�ƚŽ͗ EĂŶĂ͘tĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵ͘�

�ŝƌĞĐƚ ϴϭϯ�ʹ ϴϴϲ�ʹ ϭϬϳϱ��džƚ�Ϯϭϵ DŽďŝůĞ ϴϭϯ�Ͳ Ϯϲϳ�Ͳ Ϯϱϭϵ KĨĨŝĐĞ ϴϭϯ�ʹ ϴϴϲ�ʹ ϭϬϳϱ �ŵĂŝů EĂŶĂ͘tĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵ ^ŬLJƉĞ EĂŶĂ͘tĞƐƚŵĂƌŬ͘/ŶƚĞƌƚĞŬ ǁǁǁ͘ŝŶƚĞƌƚĞŬ͘ĐŽŵͬďƵŝůĚŝŶŐ

^ĞŶƚ�ĨƌŽŵ�DĂŝů�ŐŽ͘ŵŝĐƌŽƐŽĨƚ͘ĐŽŵ ĨŽƌ�tŝŶĚŽǁƐ

&ƌŽŵ͗ EĂŶĂ�tĞƐƚŵĂƌŬ�фŶĂŶĂ͘ǁĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵх ^ĞŶƚ͗DŽŶĚĂLJ͕�:ĂŶƵĂƌLJ�ϭϳ͕�ϮϬϮϮ�ϰ͗Ϯϳ͗ϯϲ�WD dŽ͗ ƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵ фƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵх �Đ͗ ŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵ фŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵх ^ƵďũĞĐƚ͗ Z�͗��džƚĞƌŶĂů�Z�͗��ŶŶƵĂů�/�t�ƉƌŝĐĞƐ�ĨŽƌ�&��W��ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚ�ĨŽƌ�W^/�dĞĂŵ� dŚĂŶŬ�LJŽƵ�ĨŽƌ�ƌĞƐƉŽŶĚŝŶŐ�ƐŽ�ƋƵŝĐŬůLJ͘

:ƵƐƚ�ƚŽ�ĐůĂƌŝĨLJ͗

/Ĩ�ǁĞ�ŚĂǀĞ�ŽŶĞ�ĚƌƵŵ�ŽĨ�/�t�ƐŽŝů�ŽŶ�Ă�ƐŝƚĞ�ǁŝƚŚ�ϭ�ĚƌƵŵ�ŽŶůLJ͕�ƚŚĞ�ĐŽƐƚ�ĨŽƌ�ƚŚĞ�ĐŽŵƉůĞƚĞ�ƉŝĐŬͲƵƉ͕�ƚƌĂŶƐƉŽƌƚ͕� ĂĚ�ĚŝƐƉŽƐĂů�ǁŽƵůĚ�ďĞ͗

ΨϭϱϬ�Ͳ ƐŽŝů� ΨϮϯϱ�ʹ ůŽǁ�ǀŽůƵŵĞ�ĨĞĞ ΨϭϭϬ�ʹ ƉŝĐŬͲƵƉ�ĨĞĞ dŽƚĂů�ĨŽƌ�ŽŶĞ�ĚƌƵŵ͗ Ψϰϵϱ͍ dŚĂŶŬƐ

EĂŶĂ�

^ĞŶƚ�ĨƌŽŵ�DĂŝů�ŐŽ͘ŵŝĐƌŽƐŽĨƚ͘ĐŽŵ ĨŽƌ�tŝŶĚŽǁƐ

&ƌŽŵ͗�ƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵ ^ĞŶƚ͗�DŽŶĚĂLJ͕�:ĂŶƵĂƌLJ�ϭϳ͕�ϮϬϮϮ�ϰ͗ϭϯ�WD dŽ͗�EĂŶĂ�tĞƐƚŵĂƌŬ �Đ͗�ŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵ ^ƵďũĞĐƚ͗��džƚĞƌŶĂů�Z�͗��ŶŶƵĂů�/�t�ƉƌŝĐĞƐ�ĨŽƌ�&��W��ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚ�ĨŽƌ�W^/�dĞĂŵ�

'ŽŽĚ�ĂĨƚĞƌŶŽŽŶ͘�WůĞĂƐĞ�ĨŝŶĚ�ĂƚƚĂĐŚĞĚ�ŽƵƌ�ƉƌŝĐĞƐ�ĨŽƌ�ƚƌĂŶƐ�ĂŶĚ�ĚŝƐƉŽƐĂů�ŽĨ�LJŽƵƌ�ŶŽŶͲŚĂnjĂƌĚŽƵƐ�Ěƌŝůů� ĐƵƚƚŝŶŐƐ͘�/Ĩ�LJŽƵ�ŚĂǀĞ�ĂŶLJ�ƋƵĞƐƚŝŽŶƐ͕�ƉůĞĂƐĞ�ůĞƚ�ŵĞ�ŬŶŽǁ͘� tĞ�ůŽŽŬ�ĨŽƌǁĂƌĚ�ƚŽ�ǁŽƌŬŝŶŐ�ǁŝƚŚ�LJŽƵ�ŽŶ�ƚŚŝƐ�ƉƌŽũĞĐƚ͘ dŚĂŶŬ�LJŽƵ͕ dĞƌĞƐĂ�EŝdžŽŶ ͮ�WƌŽũĞĐƚ��ŝƌĞĐƚŽƌ �ĚǀĂŶƚĂŐĞ��ŶǀŝƌŽŶŵĞŶƚĂů�^ĞƌǀŝĐĞƐ͕�/ŶĐ͘ ϮϯϮϱ�ϱƚŚ �ǀĞŶƵĞ�EŽƌƚŚ ͮ�^ƚ͘�WĞƚĞƌƐďƵƌŐ͕�&ůŽƌŝĚĂ�ͮ�ϯϯϳϭϯͮ K͗ ϳϮϳ͘ϯϮϯ͘ϭϵϬϮ ͮ�D͗ ϴϭϯ͘ϵϭϴ͘ϵϱϳϲ ƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵ ƌĞƐƚŽƌŝŶŐ͘ƚŽŵŵŽƌŽǁ͘ƚŽĚĂLJ �ĞƌƚŝĨŝĞĚ�DŝŶŽƌŝƚLJ��ƵƐŝŶĞƐƐ

ͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲͲ

7KH�LQIRUPDWLRQ�FRQWDLQHG�LQ�WKLV�HPDLO�PD\�EH�FRQILGHQWLDO�DQG�RU�OHJDOO\�SULYLOHJHG��,W�KDV�EHHQ�VHQW�IRU�WKH�VROH�XVH�RI�WKH� LQWHQGHG�UHFLSLHQW�V���,I�WKH�UHDGHU�RI�WKLV�PHVVDJH�LV�QRW�DQ�LQWHQGHG�UHFLSLHQW��\RX�DUH�KHUHE\�QRWLILHG�WKDW�DQ\�XQDXWKRUL]HG UHYLHZ��XVH��GLVFORVXUH��GLVVHPLQDWLRQ��GLVWULEXWLRQ��RU�FRS\LQJ�RI�WKLV�FRPPXQLFDWLRQ��RU�DQ\�RI�LWV�FRQWHQWV��LV�VWULFWO\�SURKLELWHG��

,I�\RX�KDYH�UHFHLYHG�WKLV�FRPPXQLFDWLRQ�LQ�HUURU��SOHDVH�UHSO\�WR�WKH�VHQGHU�DQG�GHVWUR\�DOO�FRSLHV�RI�WKH�PHVVDJH��7R�FRQWDFW�XV�

GLUHFWO\��VHQG�WR�VDOHV#DHVHQY�FRP��7KDQN�\RX��

&ƌŽŵ͗ EĂŶĂ�tĞƐƚŵĂƌŬ�фŶĂŶĂ͘ǁĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵх� ^ĞŶƚ͗ dŚƵƌƐĚĂLJ͕�:ĂŶƵĂƌLJ�ϭϯ͕�ϮϬϮϮ�ϯ͗Ϭϴ�WD dŽ͗ ŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵ �Đ͗ ƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵ ^ƵďũĞĐƚ͗ Z�͗��ŶŶƵĂů�/�t�ƉƌŝĐĞƐ�ĨŽƌ�&��W��ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚ�ĨŽƌ�W^/�dĞĂŵ�

/ƚ�ũƵƐƚ�ŽĐĐƵƌƌĞĚ�ƚŽ�ŵĞ�ƚŚĂƚ�ŝƚ�ŵŝŐŚƚ�ďĞ�ĞĂƐŝĞƌ�ŝĨ�/�ƐĞŶĚ�LJŽƵ�ƚŚĞ�ƐƉƌĞĂĚƐŚĞĞƚ͘ dŚĂŶŬƐ

^ĞŶƚ�ĨƌŽŵ�DĂŝů�ŐŽ͘ŵŝĐƌŽƐŽĨƚ͘ĐŽŵ ĨŽƌ�tŝŶĚŽǁƐ

&ƌŽŵ͗�EĂŶĂ�tĞƐƚŵĂƌŬ ^ĞŶƚ͗�dŚƵƌƐĚĂLJ͕�:ĂŶƵĂƌLJ�ϭϯ͕�ϮϬϮϮ�ϴ͗Ϯϳ��D dŽ͗�ŶƐŚŝŶŐůĞΛĂĞƐĞŶǀ͘ĐŽŵ �Đ͗�ƚŶŝdžŽŶΛĂĞƐĞŶǀ͘ĐŽŵ͖�EĂŶĂ�tĞƐƚŵĂƌŬ ^ƵďũĞĐƚ͗��ŶŶƵĂů�/�t�ƉƌŝĐĞƐ�ĨŽƌ�&��W��ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚ�ĨŽƌ�W^/�dĞĂŵ�

'ŽŽĚ�DŽƌŶŝŶŐ�EĂƚŚĂŶ�ʹ dŚĂŶŬ�LJŽƵ�ĨŽƌ�ƐƉĞĂŬŝŶŐ�ǁŝƚŚ�ŵĞ�ƚŚŝƐ�ŵŽƌŶŝŶŐ͘ dŚĞ�W^/�dĞĂŵ�;W^/�ĂŶĚ��ŚĂƐƚĂŝŶ�^ŬŝůůŵĂŶͿ�ŚĂǀĞ�ďĞĞŶ�ĂǁĂƌĚĞĚ�ŽŶĞ�ŽĨ�ƚŚĞ�&��W�͞�ƌLJĐůĞĂŶŝŶŐ��ŽŶƚƌĂĐƚƐ͟� ĂŶĚ�ǁĞ�ĂƌĞ�ĂŶdžŝŽƵƐ�ƚŽ�ŐĞƚ�ƐƚĂƌƚĞĚ͘ tĞ�ĂƌĞ�ŝŶǀŝƚŝŶŐ�LJŽƵƌ�Ĩŝƌŵ�ƚŽ�ƉƌŽǀŝĚĞ�ĐŽƐƚƐ�ĨŽƌ�ƉŝĐŬͲƵƉ͕�ƚƌĂŶƐƉŽƌƚ͕�ĂŶĚ�ĚŝƐƉŽƐĂů�ƚŽ�ĂŶ�ĂƉƉƌŽǀĞĚ�ĨĂĐŝůŝƚLJ�ŽĨ� /ŶǀĞƐƚŝŐĂƚŝŽŶͲ�ĞƌŝǀĞĚ�tĂƐƚĞ�;/�tͿ�ŽŶ�Ă�ƉĞƌ�ϱϱͲŐĂůůŽŶ�ĚƌƵŵ�ďĂƐŝƐ�ĨƌŽŵ�ĚƌLJĐůĞĂŶŝŶŐ�ƐŝƚĞƐ�ĂŶĚ�ƐƚĂƚĞ� ĨƵŶĚĞĚ�ƐŝƚĞƐ͕�ĂŶĚ�ƐŝƚĞ�ŝŶǀĞƐƚŝŐĂƚŝŽŶ�ƐŝƚĞƐ�ƚŚĂƚ�ĂƌĞ�ŝŶ�ƚŚĞ�ƉƌŽŐƌĂŵƐ͘

/Ĩ�LJŽƵ�ĂƌĞ�ŝŶƚĞƌĞƐƚĞĚ�ŝŶ�ƉƌŽǀŝĚŝŶŐ�Ă�ƋƵŽƚĞ͕�ǁĞ�ǁŽƵůĚ�ĂƉƉƌĞĐŝĂƚĞ�ŝƚ͘ /�Ăŵ�ĂƚƚĂĐŚŝŶŐ�Ă�ĨŽƌŵ�ŝŶ�ǁŚŝĐŚ�ƚŽ� ƐƵďŵŝƚ�ďĂĐŬ�ƚŽ�ƵƐ͕�ĂůŽŶŐ�ǁŝƚŚ�ƚŚĞ�'ĞŶĞƌĂů��ŽŶĚŝƚŝŽŶƐ͘

/Ĩ�LJŽƵ�ĐŽƵůĚ�ƉƌŽǀŝĚĞ�ƚŚĞƐĞ�ƉƌŝĐĞƐ�ƚŽ�ƵƐ�ďLJ�:ĂŶƵĂƌLJ�Ϯϭ͕�ϮϬϮϮ͕�ǁĞ�ǁŽƵůĚ�ĂƉƉƌĞĐŝĂƚĞ�ŝƚ͘ dŚĂŶŬ�LJŽƵ͕

EĂŶĂ

EĂŶĂ�tĞƐƚŵĂƌŬ͕�W'͕��,DD ^ĞŶŝŽƌ�'ĞŽůŽŐŝƐƚ�ͬ�WƌŝŶĐŝƉĂů��ŽŶƐƵůƚĂŶƚ �ƵŝůĚŝŶŐ�Θ��ŽŶƐƚƌƵĐƚŝŽŶ /ŶƚĞƌƚĞŬͲW^/

WůĞĂƐĞ�EŽƚĞ͗ �Ɛ�ŽĨ�KĐƚŽďĞƌ�ϭϮ͕�ϮϬϭϴ͕�ŵLJ�ĞŵĂŝů�ĂĚĚƌĞƐƐ�ǁŝůů�ĐŚĂŶŐĞ�ƚŽ͗ EĂŶĂ͘tĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵ͘�

�ŝƌĞĐƚ ϴϭϯ�ʹ ϴϴϲ�ʹ ϭϬϳϱ��džƚ�Ϯϭϵ DŽďŝůĞ ϴϭϯ�Ͳ Ϯϲϳ�Ͳ Ϯϱϭϵ KĨĨŝĐĞ ϴϭϯ�ʹ ϴϴϲ�ʹ ϭϬϳϱ �ŵĂŝů EĂŶĂ͘tĞƐƚŵĂƌŬΛŝŶƚĞƌƚĞŬ͘ĐŽŵ ^ŬLJƉĞ EĂŶĂ͘tĞƐƚŵĂƌŬ͘/ŶƚĞƌƚĞŬ ǁǁǁ͘ŝŶƚĞƌƚĞŬ͘ĐŽŵͬďƵŝůĚŝŶŐ

^ĞŶƚ�ĨƌŽŵ�DĂŝů�ŐŽ͘ŵŝĐƌŽƐŽĨƚ͘ĐŽŵ ĨŽƌ�tŝŶĚŽǁƐ ďďĞď͘ĐŽŵ

7RWDO�4XDOLW\��$VVXUHG��

&21),'(17,$/,7<�127,&(�

7KLV�HPDLO�PD\�FRQWDLQ�FRQILGHQWLDO�RU�SULYLOHJHG�LQIRUPDWLRQ��LI�\RX�DUH�QRW�WKH�LQWHQGHG�UHFLSLHQW��RU�WKH�SHUVRQ�UHVSRQVLEOH�IRU� GHOLYHULQJ�WKH�PHVVDJH�WR�WKH�LQWHQGHG�UHFLSLHQW�WKHQ�SOHDVH�QRWLI\�XV�E\�UHWXUQ�HPDLO�LPPHGLDWHO\��6KRXOG�\RX�KDYH�UHFHLYHG�WKLV� HPDLO�LQ�HUURU�WKHQ�\RX�VKRXOG�QRW�FRS\�WKLV�IRU�DQ\�SXUSRVH�QRU�GLVFORVH�LWV�FRQWHQWV�WR�DQ\�RWKHU�SHUVRQ�

KWWS���ZZZ�LQWHUWHN�FRP

ĂǀĂƐƚ͘ĐŽŵ dŚŝƐ�ĞŵĂŝů�ŚĂƐ�ďĞĞŶ�ĐŚĞĐŬĞĚ�ĨŽƌ�ǀŝƌƵƐĞƐ�ďLJ��ǀĂƐƚ�ĂŶƚŝǀŝƌƵƐ� ƐŽĨƚǁĂƌĞ͘� ǁǁǁ͘ĂǀĂƐƚ͘ĐŽŵ�ĂǀĂƐƚ͘ĐŽŵ dŚŝƐ�ŵĞƐƐĂŐĞ�ŝƐ�ĨƌŽŵ�ĂŶ��yd�ZE�>�^�E��Z�Ͳ ƉůĞĂƐĞ�ďĞ���hd/Kh^͕�ƉĂƌƚŝĐƵůĂƌůLJ�ǁŝƚŚ�ůŝŶŬƐ�ĂŶĚ� ĂƚƚĂĐŚŵĞŶƚƐ͘

PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment

Clark Environmental Inc. IDW

Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various

Description of Service

Tampa Area Orlando - Central

Florida Jacksonville Area, North Florida

South Florida (Miami, Fort

Myers, Naples) Florida Panhandle water $60.00 $60.00 $60.00 $60.00 $60.00 soil $80.00 $80.00 $80.00 $80.00 $80.00 low volume fee (< 6 drums) $50.00 $50.00 $50.00 $50.00 $200.00 Pick-up fee $30.00 $30.00 $40.00 $40.00 $50.00 Per diem --- --- --- --- 200.00$

Water $140.00 $140.00 $150.00 $150.00 $510.00 Soil $160.00 $160.00 $170.00 $170.00 $530.00

1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.

2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste

5. ) Waste is considered not hazardous.

6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.

7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.

Description 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.

State of Florida

3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.

The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.

4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Page2 of 3 PSI IDW Quotes 3-29-2022

PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment

IDW

Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Various

Petrotech Southeast

Facility Name Facility Location Facility ID Various

Description of Service

Tampa Area Orlando - Central

Florida Jacksonville Area, North Florida

South Florida (Miami, Fort

Myers, Naples) Florida Panhandle water $125.00 $125.00 soil $150.00 $150.00 low volume fee (< 6 drums) Pick-up fee Per diem --- --- --- ---

Water, per drum $125.00 $125.00 $0.00 $0.00 $0.00 Soil, per drum $150.00 $150.00 $0.00 $0.00 $0.00

1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.

2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste

5. ) Waste is considered not hazardous.

6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.

7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.

State of Florida

Description 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.

3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.

The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.

4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Page 3 of 3 PSI IDW Quotes 3-29-2022

Nana Westmark

From: Natacha Jackson <natacha.jackson@petrotechse.com> Sent: Wednesday, January 26, 2022 10:15 AM To: Nana Westmark Subject: [External] Re: Annual IDW prices for FDEP Drycleaning Contract for PSI Team Attachments: PSI IDW Quotes Response 01.26.22.pdf

Good Morning, Here you go, I was waiting on the final OK from Jason..

On Wed, Jan 26, 2022 at 7:03 AM Nana Westmark <nana.westmark@intertek.com> wrote:

Good Morning Natacha – Wasn’t sure if you received this.

Are you interested in providing a quote for our annual contract?

Thanks

Nana

Sent from Mail [go.microsoft.com] for Windows

From: Nana Westmark Sent: Thursday, January 13, 2022 3:08 PM To: Natacha Jackson Subject: RE: Annual IDW prices for FDEP Drycleaning Contract for PSI Team

It just occurred to me that it might be easier if you had the spreadsheet!

Thanks

From: Nana Westmark Sent: Thursday, January 13, 2022 8:14 AM To: Natacha Jackson Cc: Greg Lassi Subject: Annual IDW prices for FDEP Drycleaning Contract for PSI Team

Good Morning Natacha – Hope you are doing well these days.

The PSI Team (PSI and Chastain Skillman) have been awarded one of the FDEP “Drycleaning Contracts” and we are anxious to get started.

We are inviting your firm to provide costs for pick-up, transport, and disposal to an approved facility of Investigation- Derived Waste (IDW) on a per 55-gallon drum basis from drycleaning sites and state funded sites, and site investigation sites that are in the programs.

If you are interested in providing a quote, we would appreciate it. I am attaching a form in which to submit back to us, along with the General Conditions.

If you could provide these prices to us by January 21, 2022, we would appreciate it.

Thank you, Nana

Nana Westmark, PG, CHMM

Senior Geologist / Principal Consultant

Building & Construction

Please Note: As of October 12, 2018, my email address will change to: Nana.Westmark@intertek.com.

Direct 813 – 886 – 1075 Ext 219

Mobile 813 - 267 - 2519

Office 813 – 886 – 1075

Email Nana.Westmark@intertek.com

Skype Nana.Westmark.Intertek www.intertek.com/building

5801 Benjamin Center Drive, Suite 112

Tampa, Florida 33634

To help protect you r priv acy, Microsoft Office prevented automatic download of this picture from the Internet.

Jo in BBEB.com to build back an ever better world!

[bbeb.com]

Total Quality. Assured.

CONFIDENTIALITY NOTICE

This email may contain confidential or privileged information, if you are not the intended recipient, or the person responsible for delivering the message to the intended recipient then please notify us by return email immediately. Should you have received this email in error then you should not copy this for any purpose nor disclose its contents to any other person.

http://www.intertek.com

Natacha Mitchell-Jackson Email: natacha.jackson@petrotechse.com Phone: 407-656-8114 or 407-367-9997 Fax: 407-358-5030

This message is from an EXTERNAL SENDER - please be CAUTIOUS, particularly with links and attachments.

PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment

PROJECT BID TABULATIONS IDW

Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various

Description of Service

Tampa Area Orlando - Central

Florida Jacksonville Area, North Florida

South Florida (Miami, Fort

Myers, Naples)…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .