CN-370000-HW686-DC024B.pdf

PDF 688 KB Posted

Attached to
Master Agreement FL|HW686|26652fe61cf76d14a6798f2369f5dddb
Contract number
HW686
Issued by
Florida

About this file

This document is a Task Assignment (TA) under Contract Number HW686 between the State of Florida Department of Environmental Protection (FDEP) and Professional Service Industries, Inc. (Intertek-PSI). The task assignment, numbered DC024B, is for groundwater monitoring services at Dryclean World (ERIC_5498), located at 3895 Lake Emma Road, Lake Mary, Seminole County, Florida. The FDEP Project Manager is Mary Uribe, and the contractor's Project Manager is Joshua Newell, PE. The contract is executed under the FDEP's Waste Cleanup Program Services (Contract HW686), dated December 21, 2021.

The scope of work consists of groundwater monitoring for volatile organic hydrocarbons (VOHs) and perfluoroalkyl and polyfluoroalkyl substances (PFAS), with subsequent reporting. Services include project management, collection of groundwater elevation measurements from nine monitoring wells, collection and analysis of groundwater samples via EPA Method 8260, preparation and shipment of PFAS samples to the FDEP Central Laboratory, and containerization and disposal of purge water. The total Task Assignment value is $13,583.62 on a fixed unit rate basis. The final deliverable—submittal and FDEP approval of the project management and groundwater monitoring report—is due July 31, 2025, with task completion scheduled for August 29, 2025. Invoicing occurs upon submittal and approval of the groundwater monitoring report. Labor costs total $9,811.02, with additional expenses for travel ($918.00), laboratory analysis ($657.00), field equipment ($1,090.00), and subcontractor services ($126.50).

View the file

Other files

File Type Posted
CN-370000-HW686-DC001B.pdf PDF
CN-370000-HW686-DC002B.pdf PDF
CN-370000-HW686-DC002D.pdf PDF
CN-370000-HW686-DC003F.pdf PDF
CN-370000-HW686-DC004D.pdf PDF
CN-370000-HW686-DC005B.pdf PDF
CN-370000-HW686-DC006A.pdf PDF
CN-370000-HW686-DC006D.pdf PDF
CN-370000-HW686-DC007B.pdf PDF
CN-370000-HW686-DC009B.pdf PDF
CN-370000-HW686-DC009D.pdf PDF
CN-370000-HW686-DC010B.pdf PDF
CN-370000-HW686-DC010D.pdf PDF
CN-370000-HW686-DC011B.pdf PDF
CN-370000-HW686-DC014B.pdf PDF
CN-370000-HW686-DC014C.pdf PDF
CN-370000-HW686-DC015C.pdf PDF
CN-370000-HW686-DC016B.pdf PDF
CN-370000-HW686-DC017A.pdf PDF
CN-370000-HW686-DC018B.pdf PDF
CN-370000-HW686-DC018C.pdf PDF
CN-370000-HW686-DC019A.pdf PDF
CN-370000-HW686-DC01ACO2.pdf PDF
CN-370000-HW686-DC020B.pdf PDF
CN-370000-HW686-DC022A.pdf PDF
CN-370000-HW686-DC026A.pdf PDF
CN-370000-HW686-DC027B.pdf PDF
CN-370000-HW686-DC02ACO1.pdf PDF
CN-370000-HW686-DC02HCO1.pdf PDF
CN-370000-HW686-DC04DCO1.pdf PDF
CN-370000-HW686-DC05ACO1.pdf PDF
CN-370000-HW686-DC05CCO3.pdf PDF
CN-370000-HW686-DC06BCO1.pdf PDF
CN-370000-HW686-DC06CC03.pdf PDF
CN-370000-HW686-DC06CCO1.pdf PDF
CN-370000-HW686-DC06CCO2.pdf PDF
CN-370000-HW686-DC09ECO1.pdf PDF
CN-370000-HW686-DC10DCO1.pdf PDF
CN-370000-HW686-DC14BCO2.pdf PDF
CN-370000-HW686-DC14DCO2.pdf PDF
CN-370000-HW686-DC21ACO2.pdf PDF
CN-370000-HW686-DC23ACO1.pdf PDF
CN-370000-HW686-FIL13.pdf PDF
CN-370000-HW686-FIL2.pdf PDF
CN-370000-HW686-FIL8.pdf PDF
CN-370000-HW686-HW001A.pdf PDF
CN-370000-HW686-HW003A.pdf PDF
CN-370000-HW686-HW004A.pdf PDF
CN-370000-HW686-HW005A.pdf PDF
CN-370000-HW686-HW005B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW686

DC024B Completion August 29, 2025

Groundwater monitoring for VOHs and PFAS with subsequent reporting.

Mary Uribe 850-245-8990 Contractor Professional Service Industries, Inc. (Intertek-PSI) Contractor

Contractor Joshua Newell Contractor 863-712-4342

ERIC_5498

3895 Lake Emma Road Lake Mary, Seminole County

Dryclean World

Contractor Contractor

✔ $ 13,583.62

$ 13,583.62

Scope of Work

Professional Service Industries, Inc. (Intertek-PSI) Contractor

Digitally signed by Joshua S Newell Date: 2025.05.05 14:35:51-04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.05.05 14:11:26 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtasks 1 and 2: Submittal and DEP approval of project management and groundwater monitoring report. 07/31/2025

Subtasks 1 and 2: Submittal and DEP approval of project management and groundwater monitoring report. $ 13,583.62

$ 13,583.62

HW686

DC024B

FFLORIDA DEPARTMENT OF

EEnvironmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Alexis A. Lambert

Secretary

Memorandum

TO: ERIC_5498

Dryclean World

FROM: Mary Uribe, Project Manager

SUBJECT: Negotiation Summary

HW686 DC024B

DATE: April 24th, 2025

PSI will perform Groundwater Monitoring activities at Dryclean World, as detailed in the March 10th, 2025 proposal. Tasking consists of sampling for VOHs, PFAS, and subsequent reporting.

Total task amount is $13,583.62. PSI’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is July 31st, 2025.

Task completion date is August 29th, 2025.

FDEP COST ESTIMATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: 3/10/2025

Task #: SubTask 1 Project Management SubTask 6

Site: SubTask 2 Groundwater Monitoring and Report SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 PFAS Monitoring SubTask 8

Project Manager: Josh Newell, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$48.00 Project Manager 9 9.4 $64.90 Principal Consultant, DC 0 0.0 0 0 0 0 0 0 0 0 $62.50 Senior Engineer, GR 4 4.0 0 0 0 0 0 0 0 0 $48.00 Project Engineer, JN 21 9.0 12 0 0 0 0 0 0 0 $40.87 Project Scientist, JD 50 46.5 3 0 0 0 0 0 0 0 $34.03 GIS / CAD Specialist, DG 4 2.0 2 0 0 0 0 0 0 0 $25.48 Staff Scientist, MM 0 0.0 0 0 0 0 0 0 0 0 $20.81 Administrative Assistant, BM 2 2.0 0 0 0 0 0 0 0 0 $39.42 Project Scientist, SL 0 0.0 0 0 0 0 0 0 0 0

Total Hours 90 9 63.5 17 0 0 0 0 0 0 0

Direct Labor $3,908.46 $449.65 $2,692.14 $766.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 151.02% $5,902.56 $679.06 $4,065.67 $1,157.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $9,811.02 $1,128.71 $6,757.81 $1,924.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Dryclean World ERIC_5498

REV: 02/03 CEF ARCADIS Page 1

FDEP COST ESTIMATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: 3/10/2025

Task #: SubTask 1 Project Management SubTask 6

Site: SubTask 2 Groundwater Monitoring and Report SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 PFAS Monitoring SubTask 8

Project Manager: Josh Newell, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Dryclean World ERIC_5498

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $558.00 $558.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $918.00 $918.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $115.00 $115.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $115.00 $115.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.50 $11.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $126.50 $126.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $870.00 $870.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,090.00 $1,090.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $12,602.52 $1,128.71 $9,549.31 $1,924.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $981.10 $112.87 $675.78 $192.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $13,583.62 $1,241.58 $10,225.09 $2,116.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Dryclean World ERIC_5498 SubTask 2 Groundwater Monitoring and Report

DATE: 3/10/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities Senior Engineer, G Robinson Event lab kit request, equipment selection 2

Tenant / owner notification 1 Technical oversight 1

Total Hour 4

Project Scientist, J Daugherty Prepare for field event 1 Mobilize to site (6 hour round trip x 1) 6 Obtain DTW from 9 wells 1 Collect groundwater samples at 9 deep wells 13.5 Documentation of groundwater sampling & measurements 2 Stage IDW drum 1 Pick-up, drop off samples 2 Mobilize to hotel (1 hour round trip x 2) 2

Total Hour 28.5 Report Project Scientist, J Daugherty Prepare tables and draft maps 10

Data reduction / evaluation, prepare report 8 Total Hour 18.0

Project Engineer, J Newell Provide evaluation and edits to report 8 Sign and seal GW monitoring report 1

Total Hour 9.0

GIS / CAD Specialist, D Grove Create maps, figures 2 Total Hour 2.0

Administrative Assistant, B MeynardFinalize report, process invoices 2 Total Hour 2.0

TOTAL LABOR 63.5

VEHICLE TYPE RATE UNIT USEAGE

Equipment Van / Truck (GW Sampling) $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Project Scientist, J Daugherty Lodging Groundwater Sampling $150.00 days 3 $450.00 Meals Groundwater Sampling $36.00 days 3 $108.00

TOTAL PER DIEM $558.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USEAGE

Petrotech Southe $115.00 LS 1 $115.00

TOTAL $115.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC #IDW

Halocarbons Via EPA Method 8260 73 9 0 0 $657.00

TOTAL LAB $657.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Shallow Groundwater Sampling Kit $290.00 day 3 $870.00 Deep Groundwater Sampling Kit $415.00 day 0 $0.00

$870.00 Drum $100.00 each 1 $100.00

$100.00 Expendables $40.00 day 3 $120.00

$120.00

TOTAL EQUIPMENT $1,090.00

IDW management, treatment, disposal

FINAL --7/24/96

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Dryclean World ERIC_5498 SubTask 3 PFAS Monitoring

DATE: 3/10/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities PFAS Sampling Project Engineer, J Newell Request PFAS sample kit via FDEP Lab Form 1

Data reduction/evaluation 1

Provide evaluation within letter/GWMR/SRCR 4

Report - Prepare final tables and figures 6 Total Hour 12

Project Scientist, J Daugherty Additional decontamination for PFAS 1 Documentation of PFAS groundwater sampling 1 Inventory cooler, prepare cooler for shipping to FDEP 1

Total Hours: 3

GIS/CADD Specialist, D Grove Create and prepare figures 2 Total Hour 2

TOTAL LABOR 17

VEHICLE TYPE RATE UNIT USEAGE

$0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL EQUIPMENT $0.00

FINAL --7/24/96

PSI Proposal 0552-444418 Rev 1 FDEP – Dryclean World, ERIC_5498

March 10, 2025 www.intertek.com/building

PSI conducted annual groundwater monitoring events from 2011 to 2022, identifying chlorinated solvent impacts extending hydraulically downgradient to the southeast of the drycleaning business. Additional parameters, specifically Perfluoroalkyl and polyfluoroalkyl substances (PFAS) compounds, were identified at the property at elevated concentrations, therefore, these compounds are included in the annual monitoring program.

The proposal contained herein consists of conducting groundwater sampling and analysis for VOH parameters for the routine annual groundwater monitoring, and sampling and analyses for PFAS compounds at select wells, along with one deliverable. The results will be used to evaluate current groundwater quality conditions. Specifically, the proposed scope of work consists of the following subtasks:

1. Project Management

This scope is provided for in the template worksheets.

2. Annual Groundwater Sampling and Analysis, and Groundwater Monitoring Report

The field activities for the VOH monitoring will be conducted concurrently with the PFAS sampling.

a. Mobilization to the site.

b. Collect groundwater elevation measurements of 9 monitoring wells.

c. Collect groundwater samples from the following monitoring wells for analyses by EPA Method 8260 for VOHs:

i. Deep: DMW003, DMW006, DMW007, DMW012, DMW0013, DMW014, DMW019 and;

ii. Deeper Wells: DMW021 and DMW022.

The groundwater samples will be submitted to a National Environmental Laboratory Accreditation Conference (NELAC) approved laboratory for analysis.

d. Containerize purge water into a 55-gallon drum, label appropriately, and upon waste characterization, have transported to an approved facility for treatment. The manifest will be submitted to the Department upon receipt.

e. Evaluation of data and develop an Annual Groundwater Monitoring Report to include current groundwater elevation maps, and current groundwater quality data. Conclusions and recommendations will be made which will include any modifications to the proposed annual groundwater sampling event.

3. PFAS Groundwater Sampling and Analysis

The PFAS groundwater sampling event will be conducted concurrently with the routine VOH sampling.

a. Collect groundwater samples from the following monitoring wells:

PSI Proposal 0552-444418 Rev 1 FDEP – Dryclean World, ERIC_5498

March 10, 2025 www.intertek.com/building

i. Deep wells: DMW003, DMW006, DMW012, DMW014.

ii. Deeper well: DMW022.

b. Preparation of sample coolers and ship to the FDEP Central Laboratory in Tallahassee for analyses for PFAS analyses.

c. Containerize purge water into a 55-gallon drum, label appropriately, and upon waste characterization, have transported to an approved facility for treatment. The manifest will be submitted to the Department upon receipt.

COST ESTIMATE AND SCHEDULE

The estimated cost to perform the described services is shown in the attached Cost Estimate. All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No. HW686, Waste Cleanup Program Services, dated December 21, 2021. An invoice and deliverable schedule is presented as follows:

Dryclean World ERIC_5498 Deliverables Deliverable Due Date

SubTask 1 Project Management Upon completion of Task Assignment

SubTask 2 Groundwater Monitoring and Report July 31, 2025

Invoice Schedule Amount to be Invoiced SubTasks 1 & 2 - Submittal & approval of Groundwater Monitoring Report $13,647.35

PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075

Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.

Josh Newell, PE John Daugherty, CES Senior Engineer, Contract Manager Environmental Project Scientist

Enclosure: Cost Estimate, Level of Effort, IDW Bids

\\tampa-fs\PROJECTS\552-Env\FDEP HW 686 Drycleaning, Main Contract\0552-444418 Dryclean World VOH & PFAS GW\DC World ERIC_5498, 0552-444418.docx

PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment

PROJECT BID TABULATIONS IDW

Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various

Description of Service

Tampa Area Orlando - Central

Florida Jacksonville Area, North Florida

South Florida (Miami, Fort

Myers, Naples) Florida Panhandle water $115.00 $115.00 N/A N/A N/A soil $165.00 $165.00 N/A N/A N/A low volume fee N/A N/A N/A Pick-up fee $0.00 $0.00 N/A N/A N/A

$280.00 $0.00 $0.00 $0.00 $0.00

1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.

2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste

5. ) Waste is considered not hazardous.

6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.

7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.

Description 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.

State of Florida

3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.

The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.

4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Bureau of Waste Cleanup,Hazardous Waste Cleanup Section.

Petrotech Southeast Quote

$115/water drum - Low Bid - WINNING BID

PSI - Intertek Request for Annual Investigative Derived Waste (IDW) IDW Pick-up, transport, Disposal and Treatment

PROJECT BID TABULATIONS IDW

Facility Name Various Drycleaning Sites under FDEP Drycleaning Solvent Cleanup Program in Florida Facility Location Various Facility ID Various

Description of Service

Tampa Area Orlando - Central

Florida Jacksonville Area, North Florida

South Florida (Miami, Fort

Myers, Naples) Florida Panhandle water $100.00 $100.00 $100.00 $200.00 $100.00 soil $100.00 $100.00 $100.00 $200.00 $100.00 low volume fee $0.00 $0.00 $0.00 $0.00 $0.00 Pick-up fee $0.00 $0.00 $0.00 $0.00 $0.00

Profile Fee: $50.00. There is one fee per generator that allows multiple locations contigent on the material.

Administration Fee: $25 per Invoice

$200.00 $0.00 $200.00 $400.00 $200.00

1. ) Please include all costs for pick-up, transport, fuel costs, stoppage fee, disposal, based on per drum cost.

2.) PSI is neither the generator nor transporter for hazardous or non-hazardous waste

5. ) Waste is considered not hazardous.

6. ) Analytical results of waste will be provided by a NELAP -approved laboratory.

7.) A PSI Purchase Order referencing Terms & Conditions (attached) will be issued and must be signed prior to pick-up.

Description 55-Gallon Drum Pick-up, Transport, Disposal at an approved facility.

State of Florida

3. Waste generated is from assessment / remediation of drycleaner sites under the State of Florida Drycleaning Solvent Cleanup Program with funding provided by the FDEP.

The Generator is the Florida Department of Environmental Protection, 2600 Blair Stone Road, Tallahassee, FL 32399, MS 4512 or 4505.

4. ) PSI is under contract with FDEP for the assessment and remediation of drycleaner projects, and hence signs profiles and manifests on behalf of FDEP, Bureau of Waste Cleanup,Hazardous Waste Cleanup Section.

GCVT Quote

$175/drum - High Bid

04/24/2024 01:44 PM PAGE 1 OF 7

Scope of Work pricing is based on an approved non hazardous facility in to Enviroserve Mulberry

4600 BROOKPARK ROAD, CLEVELAND,

OHIO, 44134

(216) 642-1311

(216) 642-1474

QUOTE #: 0042802

DATE: 04/24/2024 PROJECT PROPOSAL

CLIENT

JOSH NEWELL

INTERTEK/PSI - PLANT CITY

607 SOUTH ALEXANDER ST, SUITE 202, PLANT CITY, FLORIDA,

33563 P: (863) 712-4342

E-MAIL:JOSHUA.NEWELL@INTERTEK.COM

PROJECT DESCRIPTION

FDEP DRY CLEANING DRUMS

FDEP

THE FOLLOWING DESCRIBES OUR UNDERSTANDING OF THE SCOPE OF SERVICES TO BE PERFORMED BY ENVIROSERVE, FOR THE

CLIENT, AT THE ABOVE REFERENCED LOCATION KNOWN AS THE JOB SITE.

FEE STRUCTURE

TRANSPORTATION

ITEM EST.QTY. UNIT PRICE UNIT TOTAL

TRANSPORTATION - LTL DRUM (6 - 55 GAL) - 251-400 MILES 1.00 $50.00 DRUM $50.00

LOW STOP FEE (LESS THAN 6 DRUMS) 1.00 $50.00 55 GAL DRUM $50.00

ENERGY SURCHARGE (APPLIES TO TOTAL INVOICE) - $15.00 % -

TRANSPORTATION SUBTOTAL: $100.00

DISPOSAL

ITEM EST.QTY. UNIT PRICE UNIT TOTAL

55 GAL DRUM / SOLID 1.00 $80.00 EACH $80.00

DISPOSAL SUBTOTAL: $80.00

JOB ESTIMATE: $180.00

ENVIRONMENTAL FEE: $9.00

TOTAL JOB ESTIMATE: $189.00

$189/drum - High Bid