CN-370000-HW686-DC015D.pdf

PDF 1003 KB Posted

Attached to
Master Agreement FL|HW686|26652fe61cf76d14a6798f2369f5dddb
Contract number
HW686
Issued by
Florida

About this file

This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Professional Service Industries, Inc. (Intertek-PSI) for environmental remediation services at the Quality Cleaners site (ERIC_4771) located at 14837 North Florida Avenue, Tampa, Hillsborough County. The task assignment is entered pursuant to Contract Number HW686 and is designated as TA Number DC015D. The Department Project Manager is Mary Uribe, while the Contractor's Project Manager is Joshua Newell.

The task involves the development of an Interim Source Removal Plan (ISRP) for soil vapor extraction remediation at the Quality Cleaners site, with a total task value of $12,974.96 on a fixed unit rate basis. The deliverables consist of two subtasks: Project Management and an Interim Source Removal Plan, with a final deliverable due date of January 31, 2026 and task completion date of February 27, 2026. The scope includes design calculations, specifications for soil vapor extraction wells, site plans, treatment system layouts, construction details, and engineering documents to be signed and sealed by a Florida Registered Engineer. PSI's costs include 83 hours of labor across multiple staff categories (Senior Engineer, Project Engineer, Project Scientist, GIS/CADD Specialist, and Administrative Assistant), vehicle use of $120.00, equipment costs of $400.00, and no subcontractor or laboratory costs. Payment is contingent upon FDEP approval of the Project Management deliverable and the Interim Source Removal Plan.

View the file

Other files

File Type Posted
CN-370000-HW686-DC001B.pdf PDF
CN-370000-HW686-DC002B.pdf PDF
CN-370000-HW686-DC002D.pdf PDF
CN-370000-HW686-DC003F.pdf PDF
CN-370000-HW686-DC004D.pdf PDF
CN-370000-HW686-DC005B.pdf PDF
CN-370000-HW686-DC006A.pdf PDF
CN-370000-HW686-DC006D.pdf PDF
CN-370000-HW686-DC007B.pdf PDF
CN-370000-HW686-DC009B.pdf PDF
CN-370000-HW686-DC009D.pdf PDF
CN-370000-HW686-DC010B.pdf PDF
CN-370000-HW686-DC010D.pdf PDF
CN-370000-HW686-DC011B.pdf PDF
CN-370000-HW686-DC014B.pdf PDF
CN-370000-HW686-DC014C.pdf PDF
CN-370000-HW686-DC015C.pdf PDF
CN-370000-HW686-DC016B.pdf PDF
CN-370000-HW686-DC017A.pdf PDF
CN-370000-HW686-DC018B.pdf PDF
CN-370000-HW686-DC018C.pdf PDF
CN-370000-HW686-DC019A.pdf PDF
CN-370000-HW686-DC01ACO2.pdf PDF
CN-370000-HW686-DC020B.pdf PDF
CN-370000-HW686-DC022A.pdf PDF
CN-370000-HW686-DC026A.pdf PDF
CN-370000-HW686-DC027B.pdf PDF
CN-370000-HW686-DC02ACO1.pdf PDF
CN-370000-HW686-DC02HCO1.pdf PDF
CN-370000-HW686-DC04DCO1.pdf PDF
CN-370000-HW686-DC05ACO1.pdf PDF
CN-370000-HW686-DC05CCO3.pdf PDF
CN-370000-HW686-DC06BCO1.pdf PDF
CN-370000-HW686-DC06CC03.pdf PDF
CN-370000-HW686-DC06CCO1.pdf PDF
CN-370000-HW686-DC06CCO2.pdf PDF
CN-370000-HW686-DC09ECO1.pdf PDF
CN-370000-HW686-DC10DCO1.pdf PDF
CN-370000-HW686-DC14BCO2.pdf PDF
CN-370000-HW686-DC14DCO2.pdf PDF
CN-370000-HW686-DC21ACO2.pdf PDF
CN-370000-HW686-DC23ACO1.pdf PDF
CN-370000-HW686-FIL13.pdf PDF
CN-370000-HW686-FIL2.pdf PDF
CN-370000-HW686-FIL8.pdf PDF
CN-370000-HW686-HW001A.pdf PDF
CN-370000-HW686-HW003A.pdf PDF
CN-370000-HW686-HW004A.pdf PDF
CN-370000-HW686-HW005A.pdf PDF
CN-370000-HW686-HW005B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW686

DC015D February 27, 2026

SVE Interim Source Removal Plan

Mary Uribe 850-245-8990 Professional Service Industries, Inc. (Intertek-PSI)

Joshua Newell 863-712-4342

ERIC_4771

14837 North Florida Avenue Tampa, Hillsborough County

Quality Cleaners

$ 12,974.96

$ 12,974.96

Scope of Work

Professional Service Industries, Inc. (Intertek-PSI)

Douglas Coleman PMP, CHMM, REM

Contract Manager

Douglas Coleman Digitally signed by Douglas Coleman Date: 2025.09.11 09:25:22 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.09.11 08:20:23 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Quality Cleaners ERIC_4771 SubTask 2 ISR Plan

DATE: 9/5/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities

Senior Engineer, G Robinson Coordinate with tenant, property owner 2 Review bid documents for subcontractors 2 Review calculations 2 Review text 3 Review tables 1 Review figures 1 Sign and seal documents 1

Total Hours 12

Project Engineer, J Newell Travel to Site, roundtrip 3 Meet on-site with tenant/owner to evaluate equipment locations 3 Evaluate electrical requirements with power company 3 Prepare remediation calculations (SV & AI - flow rates and friction loss) 6 Equipment specification selection - SVE/AI blowers 8 Prepare ISRP text 12 Develop tables 4

Prepare ISR checklist 2 Develop bid documents for subcontractors 6

Total Hours 59

Project Scientist, J Daugherty Obtain subcontractor quotes 6 Total Hours 6

GIS/CADD Specialist, D Grove Create and prepare final figures 3

Administrative Assistant, B Meynardie Compile documents 3

TOTAL LABOR 83.00

VEHICLE TYPE RATE UNIT USEAGE

$0.00 Equipment Van / Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC IDW

$0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Expendables $40.00 day 1 $40.00 Construction Test Kit $360.00 day 1 $360.00

#REF!

TOTAL EQUIPMENT $400.00

Develop figures (site plan, treatment system layout, trenching cross sections, well construction details, manifold details, piping and instrumentation diagram (P&ID), fence detail, trailer tie down detail, and equipment layout as needed)

FINAL --7/24/96

Page 4 Quality Cleaners ERIC_4771 ISR Plan SVE 0552-446333r1

FDEP – Quality Cleaners ERIC_4771 PSI Proposal 0552-446333r1

September 5, 2025 www.intertek.com/building

1. Project Management

This scope is provided for in the template worksheets.

2. Interim Source Removal Plan (ISR Plan)

The design of the ISRP will address VOH concentrations in the soil and will not directly address groundwater quality. The presumptive remedy for remediation of impacted soil at the Quality Cleaners site is soil vapor extraction, based on previous experience, feasibility, ease of implementation, reliability, operations and maintenance (O&M) requirements, and cost. PSI will also coordinate with the building tenant, property management company, and the property owner for suggested locations of piping, lines, and equipment compound.

Calculations will be generated to determine the design, construction details and specifications of the system (number of SVE wells, radius of influence, estimated time to cleanup, etc.). Figures will include site plan, treatment system layout, trenching cross sections, well construction details, manifold details, piping and instrumentation diagram (P&ID), fence detail, trailer tie down detail, and equipment layout, as necessary.

The SVE design will include a summary of the MAGS survey. The report will include pertinent information to include a detailed description of the remedial system, operation details, start-up testing, site schedule for O&M, tables summarizing proposed samples and analysis, and itemized cost estimates for project capital, and the implementation schedule. The design will be signed and sealed by a Florida Registered Engineer in accordance with Chapters 471, Florida Statues. The report will incorporate specific recommendations and provide opinions based on professional experience in order to achieve the most efficient endpoints. We understand that the Department’s goal is to achieve aggressive contaminant reduction in an efficient and cost-effective method.

The deliverable and invoice schedule are presented below and are based on receipt of a Task Assignment prior to September 15, 2025.