This document is a Task Assignment Change Order Form and supplemental scope of work between the Florida Department of Environmental Protection (FDEP) and Taylor Engineering, Inc. for improvements to Silver Springs State Park in Taylor County, Florida. The project involves design and permitting services related to swimming area improvements, paddle boat building rehabilitation, restroom facility construction, and associated infrastructure modifications. Additional subconsultants include SAVANNAPUB, INC., EGS, Inc., and Mead and Hunt.
The contract scope comprises thirteen subtasks organized into four primary categories: Subtask 10 (Restroom Foundation Design Change), Subtask 11 (Sea Hunt Structure Demolition, ADA Accessible Ramp, and Floating Kayak Launch Design), Subtask 12 (Construction Administration Support), and Subtask 13 (Additional Geotechnical Investigation). Specific deliverables include design drawings at 60% and 100% completion stages, technical specifications, construction documents, bid administration support, contractor submittal reviews, request for information responses, site observation reports, and geotechnical investigation findings. The contract is fixed-price with a total cost of $75,415.65, consisting entirely of fixed fees with no reimbursable costs. Payment is contingent upon FDEP approval of deliverables for each subtask. The project schedule extends from May 2021 through October 2022, with construction administration services anticipated during an eight to ten-month construction period. The change order was executed on May 18, 2021, with a net increase of $75,415.65 and a task end date extension to June 30, 2023.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN 335 TA 8 1 61263C
Silver Springs State Park New Swim Area/Paddleboat Building
Taylor Engineering, Inc
Jenna Philips 941-702-5871 jphillips@taylorengineering.com
Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov
Consultant to provide design and permitting services for the rehabilitation of the paddle boat building, provide design, permitting and geotechnical services for the restroom foundation per proposal dated 5/18/21.
$ 4,595.00 $ 229,658.81 $ 234,253.81 $ 4,595.00 $ 229,658.81 $ 234,253.81
$ 0.00 $ 75,415.65 $ 75,415.65 $ 4,595.00 $ 305,074.46 $ 309,669.46
9/21/2020
6/30/2022
6/30/2022
6/30/2023
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.05.18 15:36:18 -04'00'
Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2021.05.18 15:42:06 -04'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.05.18 15:53:11 -04'00'
Johnathan Armbruster Digitally signed by Jonathan Armbruster Date: 2021.05.19 13:05:55 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2021.05.25 16:03:40 -04'00'
61263C 37503000203 080039/20 000286 U3200 131500 AD $ 75,415.65
$ 75,415.65
1800 2 N D S TR EE T , S U I TE 7 14 | SA RA SOTA , F L 3 4 23 6 | TEL 9 41 .7 02 . 58 71
WWW .T AYLO RENG IN E ER I N G.C OM
April 28, 2021 (Revised May 18, 2021)
Wayne D. Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: FDEP Agreement Number CN335 Silver Springs State Park Swimming Area Improvements Sea Hunt Structure Demolition, Ramp & Floating Dock Design, Restroom Foundation, Permitting and Construction Phase Support
Dear Mr. Thomas:
For your review, Taylor Engineering, has provided a revised proposal summary and labor-hour documentation for above-referenced project’s professional services tasks identified below:
Task 10 – Restroom Foundation Design Change Task 11 – Sea Hunt Structure Demolition, Ramp and Floating Kayak Launch Design Task 12 – Construction Administration Support Task 13 – Additional Geotechnical Investigation
Please let me know if you have any questions and when you would like to discuss.
Sincerely, Jenna N. Phillips Sr. Project Engineer/Office Manager
Supplemental Scope of Work Silver Springs State Park
Sea Hunt Structure Demolition, Ramp, Floating Dock, and Restroom Foundation Design, and Construction Administration Support
Introduction:
FDEP (Department) has contracted with Taylor Engineering (Consultant) to design improvements to Silver Springs State Park. These improvements include developing a new beach and swimming area, adding a restroom, installing a new seawall with handrailing, and renovating the paddleboat launch facility. This scope of work outlines additional engineering services to supplement the previous scope of work. These additional services include design and permitting for the paddleboat house modifications and floating kayak launch, design for restroom mini pile foundation, additional geotechnical survey, and limited construction phase support for the original project components and these additional features. Notably, the Consultant performed detailed data collection and site observation efforts which led to a more detailed analysis of the existing site conditions. As a result, the design team arrived at the following conclusions:
Mead and Hunt’s “Paddleboat House Field Assessment” report dated January 8, 2021 outlines the recommendations for renovations and rehabilitation of the existing Sea Hunt paddleboat house structure. The paddleboat house consists of two roofed and pile supported structures. The Department has decided to demolish the eastern portion of the facility and maintain the existing western structure in its current condition to serve as an observation platform.
This Department desires to construct a new ADA accessible ramp between the two existing paddleboat house structures to provide access to a floating kayak dock. All existing sidewalks adjacent to the Sea Hunt structure to remain.
Department desires to include an ADA friendly floating kayak dock along the waterward side of the existing paddleboat house, using the Ez Dock system or similar.
The Department desires to relocate the restroom building footprint to the southeast, on the other side of the proposed beach area. Additional geotechnical borings are needed within the proposed building footprint. This scope of work accounts for this change.
The initial geotechnical survey identified a silt and muck layer beneath the initially proposed restroom building footprint wherein a slab-on-grade foundation may not be a cost effective and viable option. Designers recommend a mini pile foundation design as the most viable and cost-effective design approach. If similar geotechnical conditions are found within the newly proposed building footprint location, this scope of work accounts for these necessary design change.
Upon completion of design and permitting, the Department has requested construction administration support for all the project improvements.
Subtask 10: Restroom Foundation Design Change
Description: FDEP has identified the location of the proposed restroom facility adjacent to the existing Town Center building. Based on survey’s provided by FDEP, existing utilities are located within this vicinity for connection. However, based on the findings from the geotechnical survey and the EGS report dated December 2020, a layer of silt and muck lies under the proposed restroom footprint. A slab-on-grade foundation design would require excavation and removal and replacement of the undesirable material.
However, due to the proximity of the proposed restroom to the existing adjacent building, this approach would result in high construction costs. Under this task, Consultant will expand the design to develop a mini pile foundation rather than the originally planned slab-on-grade design. Design and document submittals previously identified in the current work assignment will incorporate Subtask 10 deliverables.
The construction plans will include all architectural details as well as any general notes and building specification required for construction.
Deliverables:
Subtask 10 deliverables will incorporate into existing plan submittal deliverables as the schedule allows, and as follows:
Subtask 10.A – 60% Plans Design Drawings (PDF) Technical Specifications
Subtask 10.B – 100% Final Plans Adobe PDF and DWG electronic file of all construction documents
Performance Measures:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 10A: Restroom Foundation Design Change - 60%
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Taylor Engineering Director $178.02 4 $712.08 Taylor Engineering Senior Technical Support 139.23 4 $556.92
Subtotal: $1,269.00
SAVANNAPUB, INC. Structural Engineer $106.10 16 $1,697.60 SAVANNAPUB, INC. Senior Structural Engineer $165.28 4 $661.12
Subtotal: $2,358.72
Total for Subtask 10.A: $3,627.72
Subtask 10B: Restroom Foundation Design Change - 100%
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Taylor Engineering Director $178.02 2 $356.04 Taylor Engineering Senior Technical Support 139.23 2 $278.46
Subtotal: $634.50
SAVANNAPUB, INC. Structural Engineer $106.10 9 $954.90 SAVANNAPUB, INC. Senior Structural Engineer $165.28 3 $495.84
Subtotal: $1,450.74
Total for Subtask 10.B: $2,085.24
Subtask 11: Sea Hunt Demolition, ADA Accessible Ramp, and Floating Kayak Launch Design
Description: The paddleboat house consists of two roofed, pile supported structures. The Department has decided to demolish the eastern structure, maintain the existing western structure in its current condition to serve as an observation platform and construct an ADA accessible ramp. The ramp will provide access to a newly constructed floating kayak launch. No changes will be made to the western structure.
Under this task, Consultant will perform engineering analysis and design for new ramp and floating kayak dock adjacent to the existing Sea Hunt structure. The design will also include engineering drawings associated with demolition of the eastern Sea Hunt building. Specifically, design related to this task includes the following:
1. Removal and demolition of the east building.
2. A new ADA accessible ramp that extends from the existing upland sidewalk to the proposed floating kayak launch.
3. Consolidating the three entrance sidewalk ramps to one main ramp in the center leading to the newly proposed ADA ramp.
Consultant will also develop the design, technical specifications and cost estimates for a floating kayak launch system and gangway to be located at the south side of the existing Sea Hunt structures. The floating dock system’s designed will accommodate up to five (5) kayak launches, with one intended to provided ADA accessibility. Consultant will evaluate configurations provided by manufacturers such as EZ Dock, to develop an appropriate design layout. Consultant will also perform analysis to design the piling and anchoring of the floating kayak dock system against vertical and lateral loads.
Assumptions/Exclusions:
Design services do not include rehabilitation or replacement of the eastern or western buildings. The western building will remain in its existing condition. No design services will be performed for this portion of the Sea Hunt structure.
The proposed dock will not accommodate motorboat access.
The proposed floating kayak dock will not require additional permitting fees beyond those included in the previous scope of work. Should the permit fees exceed the estimated amount, Consultant will submit a change order in the amount of the difference.
This task excludes amenity designs.
Deliverables:
Structural drawing will include:
General Notes for the Sea Hunt Structure Demolition, Ramp and Floating Kayak Launch Typical Sections for Sea Hunt Structure Demolition Typical Sections for Ramp and Floating Kayak Launch Structural Details for Ramp structure and Floating Kayak Launch
Subtask 11 deliverables will incorporate into existing plan submittal deliverables as the schedule allows, and as follows:
Subtask 11.A – 60% Plans Design Drawings (PDF) Technical Specifications Opinion of Probable Construction Cost
Subtask 11.B –100% Final Plans Two (2) hard copy full-sized Signed and Sealed Drawings Adobe PDF and DWG electronic file of all construction documents transmitted electronically
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 11A: Sea Hunt Demolition, Ramp & Floating Kayak Launch Design - 60%
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Taylor Engineering Director $178.02 16 $2,848.32 Taylor Engineering Senior Professional 162.21 22 $3,568.62 Taylor Engineering Project Professional 116.58 56 $6,528.48 Taylor Engineering Staff Professional 86.40 22 $1,900.80 Taylor Engineering Senior Technical Support 139.23 34 $4,733.82
Subtotal: $19,580.04
$19,580.04 Subtask 11B: Sea Hunt Demolition, Ramp & Floating Kayak Launch Design - 100%
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Taylor Engineering Director $178.02 14 $2,492.28 Taylor Engineering Senior Professional $162.21 16 $2,595.36 Taylor Engineering Project Professional $116.58 50 $5,829.00 Taylor Engineering Staff Professional 86.40 16 $1,382.40 Taylor Engineering Senior Technical Support $139.23 24 $3,341.52
Subtotal: $15,640.56
Total for Subtask 11.B: $15,640.56
Subtask 12: Construction Administration Support
Description: Under previous task assignment, the Department contracted with Consultant to conduct Bid Administration Services (Task 9). Under this task, Consultant will incorporate additional bid administration services to support bidding for new project components. Upon completion of the bid administration and contractor award, Consultant will provide limited construction administration support. These services include a review of contractor’s request for information (RFI) during construction, and review of shop drawings and contractor submittals. Consultant will also perform site visits to the project site during construction phase to provide progress checks and periodically evaluate visual conformance with the construction drawings and technical specifications. These services will not include materials testing or quality control/quality assurance testing.
The expected construction duration is eight (8) months. If construction occurs over a period extending beyond this duration due to contractor delay or unforeseen conditions, Consultant will prepare a scope and fee proposal with a request for time extension, if needed and at the Department’s discretion, for Department consideration and approval.
Subtask 12 A: Bid Administration Support for Kayak Dock and Sea Hunt Structure
Description: Consultant will provide additional bid administration support for the sea hunt structure demolition, ADA accessible ramp and proposed floating kayak dock. Consultant will provide response for prospective bidder questions specifically related to those three elements of the project.
Assumptions:
The Department will supply daily construction administration to confirm overall conformance with the contract documents and permits.
Deliverables:
Subtask 12A: Consultant will transmit (via email) responses to bidder questions received during the bidding period.
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12A: Bid Administration for Kayak Dock, Ramp and Sea Hunt Structure Demolition
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Taylor Engineering Director $178.02 6 $1,068.12 Taylor Engineering Senior Professional $162.21 6 $973.26 Taylor Engineering Project Professional $116.58 8 $932.64
Subtotal: $2,974.02
Total for Subtask 12.A: $2,974.02
Subtask 12B: Review of Contractor Submittals
Description: Consultant will review contractor submittals, including shop drawings, for compliance with construction drawings and technical specifications and provide review action and comments as necessary.
This subtask includes sufficient labor hours to conduct a review for a maximum total of ten (10) contractor submittals requiring no more than two (2) reviews per submittal. Consultant may perform any additional submittal reviews via change order at the hourly rates described herein.
Deliverables:
Subtask 12B: Consultant will transmit (via email) in electronic format (PDF) review action cover page with comments and attached redline markups (if necessary). Consultant will apply its standard submittal review action page format.
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12B: Construction Administration - Submittal Reviews
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Taylor Engineering Director $178.02 8 $1,424.16 Taylor Engineering Senior Professional $162.21 10 $1,622.10 Taylor Engineering Project Professional $116.58 14 $1,632.12
Subtotal: $4,678.38
SAVANNAPUB, INC. Senior Architect $164.40 4 $657.60 Subtotal: $657.60
Total for Subtask 12.B: $5,335.98
Subtask 12C: Provide Contractor RFI Responses During Construction Phase
Description: Consultant will provide a response to technical Request for Information (RFI). Consultant RFI responses will only address questions that are technical in nature and relate to the design, permitting, and project construction drawings and technical specifications. This subtask includes sufficient labor hours to prepare a total of six (6) RFI responses. Consultant may prepare any additional RFI responses via change order at the hourly rates described herein.
Deliverables:
Subtask 12C: Consultant will transmit (via email) in electronic format (PDF) RFI responses with comments and attached redline markups (if necessary).
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12C: Construction Administration - Contractor RFIs
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Taylor Engineering Director $178.02 6 $1,068.12 Taylor Engineering Senior Professional $162.21 4 $648.84 Taylor Engineering Project Professional $116.58 18 $2,098.44
Subtotal: $3,815.40
Total for Subtask 12.C: $3,815.40
The fee for each RFI review is $641.92 per response for a maximum cost of $3,815.40 total of up to six (6) RFI responses. Consultant may address any additional RFI reviews/responses as part of a subsequent fee proposal.
Subtask 12D: Site Visits and Reporting
Description: Consultant will perform 6 site visits to evaluate construction progress and periodically evaluate visual conformance with the construction drawings and technical specifications.
Taylor Engineering will conduct five (5) visits to observe construction progress for the Sea Hunt structure demolition, ramp, kayak launch, seawall, stairs, vegetation clearing, and installation of the floating platform. SAVANNAHPUB will conduct one (1) visit to observe restroom facilities construction.
The engineering team will make general observations to evaluate general conformance with construction drawing, technical specifications, and permits. Because construction of all project elements may not occur simultaneously, site visits to document specific milestones may become necessary. The overall site visits will occur at the following milestone events:
- Two weeks after the start of construction
- Near completion of the restroom facilities foundation construction,
- At 30% completion for the sea hunt structure
- At 30% completion for the seawall installation
- At 60% completion for the general project scope
- At final completion of the general project scope
Consultant is not responsible for job site safety and will not directly contractor means, methods, or sequencing. Consultant will visit the site to report on construction contractor’s progress and conformance with the construction drawings and technical specifications. Consultant will take photographs for incorporation into the site observation reports. Consultant will prepare one construction observation report per site visit. Labor for each site visit includes eight (8) hours per visit plus two (2) additional labor hours for preparation for each site visit report.
Deliverable:
Consultant will transmit (via email) in electronic format (PDF) a site observation report and accompanying photographs for each site visit.
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12D: Construction Administration - Site Visits
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Taylor Engineering Director $178.02 8 $1,424.16 Taylor Engineering Senior Professional $162.21 14 $2,270.94 Taylor Engineering Project Professional $116.58 36 $4,196.88
Subtotal: $7,891.98
SAVANNAPUB, INC. Senior Architect $164.40 4 $657.60 SAVANNAPUB, INC. Electrical Engineer $97.10 8 $776.80 SAVANNAPUB, INC. Mechanical Engineer $99.17 2 $198.34 SAVANNAPUB, INC. Structural Engineer $106.10 4 $424.40
Subtotal: $2,057.14 Total for Subtask 12.D: $9,949.12
The fee for each site visit is $1,658.16 per visit for a maximum cost of $9,949.12 to be invoiced separately upon submittal of site observation reports.
Subtask 12E: Project Closeout and Completion Certification
Description: Consultant will perform one (1) site visit after the construction contractor achieves substantial completion. Following that visit, Consultant will prepare a substantial completion punch list letter. Consultant will perform one (1) site visit after the construction contractor addresses/corrects all punchlist items to confirm final construction completion. Consultant will prepare a letter certifying project completion to the regulatory agencies. The Consultant will review the contractor provided closeout documentation and as-built surveys for completeness.
Assumptions/Exclusions:
As built survey is not included as part of this scope of work.
Deliverables:
Consultant will transmit (via email) electronic format (PDF) the following deliverables
Substantial completion punch list Final completion certification forms/letter Comments on contractor closeout documents
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12E: Construction Administration - Project Closeout and Certification
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Taylor Engineering Director $178.02 12 $2,136.24 Taylor Engineering Senior Professional $162.21 12 $1,946.52 Taylor Engineering Project Professional $116.58 20 $2,331.60 Taylor Engineering Senior Technical Support 139.23 $0.00
Subtotal: $6,414.36
Total for Subtask 12.E: $6,414.36
Subtask 13: Additional Geotechnical Investigation
Description: The Department desires to relocate the proposed restroom building to a location to the southeast across from the existing Town Center building. Additional geotechnical survey is required within the building footprint of the newly proposed restroom location. Consultant will mobilize to the site to collect two (2) additional 15-foot deep SPT borings within the proposed restroom footprint with continuous sampling to boring termination. Samples will be collected every 5 feet (6 tests) for laboratory particle size analysis. The laboratory tests will also include two (2) Plastic Limit and Liquid Limit tests and two (2) Organic content tests. Consultant will prepare a geotechnical report to describe the subsurface materials encountered, measured groundwater and estimated seasonal high groundwater, and identify geotechnical design parameters for the new proposed restroom facility location.
Deliverables:
Consultant will transmit the report (via email) electronic format (PDF).
Performance Measure:
Department will review deliverables to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 13: Additional Geotechnical Investigation
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Taylor Engineering Director $178.02 4 $712.08 Taylor Engineering Senior Professional $162.21 1 $162.21
Subtotal: $874.29
EGS, Inc. Senior Engineer $194.76 1 $194.76 EGS, Inc. Engineering Intern $77.25 16 $1,236.00 EGS, Inc. Senior Engineering Technician $130.83 2 $261.66 EGS, Inc. Engineering Technician $32.49 16 $519.84
Subtotal: $2,212.26 Field Investigation
EGS, Inc. ATV Drill Mobilization $758.98 1 $758.98 EGS, Inc. SPT – ATV 0-50 Ft $23.91 30 $717.30
EGS, Inc. Grout Boreholes – ATV 0-50 Ft $9.12 30 $273.60
EGS, Inc. Extra SPT Samples – ATV 0-50 Ft $47.82 12 $573.84
Subtotal: $2,323.72 Laboratory Category
EGS, Inc. Full Grad Grain Analysis $48.58 6 $291.48 EGS, Inc. Liquid Limit $75.90 2 $151.80 EGS, Inc. Plastic Limit $30.36 2 $60.72 EGS, Inc. Organic Content $39.47 2 $78.94
Subtotal: $582.94 Total for Subtask 13: $5,993.21
Project Schedule: The following table identifies the estimated schedule for the following tasks. Notably, the schedule for construction administration services depends on receipt of permits and the contractor’s construction schedule. This scope of work assumes a construction schedule of 10 months; and subtask 12 incorporates this maximum construction duration.
Activity Duration (Calendar Days)
Work to begin upon receipt of Notice to Proceed (NTP). Schedule subject to change based on permit processing timelines and Department bidding and construction contract execution, reviews and approval.
Construction duration is estimated and subject to change.
Activity
Activity Duration (Calendar
Days)
Earliest Start Date
Latest Finish Date Notes
Subtask 10A: Restroom Foundation Design Change - 60% 30 5/10/2021 6/11/2021
Concurrent with Subtask 7A completion
Subtask 10B: Restroom Foundation Design Change - 100% 30 8/9/2021 10/15/2021
Concurrent with Subtask 7C completion
Subtask 11A: Sea Hunt Demo, Ramp & Floating Kayak Launch Design - 60% 30 5/10/2021 6/11/2021
To be combined with Task 8; following completion of Subtask 6A, concurrent with Subtasks 7A
Subtask 11B: Sea Hunt Demo, Ramp & Floating Kayak Launch Design - 100% 30 8/9/2021 10/15/2021
To be combined with Task 8; following completion of Subtask 6B, concurrent with Subtask 7C
Subtask 12A: Bid Administration for Ramp, Kayak Dock & Sea Hunt
Structure Demo 60 11/29/2021 1/7/2022
Following completion of Tasks 1-11 and consistent with prior project schedule
Subtask 12B: Review Contractor Submittals 90 1/10/2022 4/10/2022 Concurrent with
Tasks 12C, 12D
Subtask 12C: Review RFIs 245 1/10/2022 9/12/2022 Concurrent with Tasks 12B 12D
Subtask 12D: Site Visits & Reporting 245 1/10/2022 9/12/2022 Concurrent with Tasks 12C, 12B
Subtask 12E: Project Closeout 30 9/12/2022 10/12/2022 Following Completion of Task 12D
Subtask 13: Additional Geotechnical Investigation 45 5/14/2021 6/28/2021
Summary of Fees:
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Subtask Subtask Fixed Price Cost
Subtask 10: Restroom Foundation Design Change
Subtask 10A: Restroom Foundation Design Change - 60% $3,627.72
Subtask 10B: Restroom Foundation Design Change - 100% $2,085.24
Subtask 11: Sea Hunt Rehabilitation & Floating Kayak Launch
Subtask 11A: Sea Hunt Demo, Ramp & Floating Kayak Launch Design - 60% $19,580.04
Subtask 11B: Sea Hunt Demo, Ramp & Floating Kayak Launch Design - 100% $15,640.56
Subtask 12: Construction Administration Support
Subtask 12A: Bid Administration for Ramp, Kayak Dock & Sea Hunt Structure Demo $2,974.02
Subtask 12B: Review Contractor Submittals $5,335.98 Subtask 12C: Review RFIs $3,815.40 Subtask 12D: Site Visits & Reporting $9,949.12 Subtask 12E: Project Closeout $6,414.36
Subtask 13: Additional Geotechnical Investigation Subtask 13: Additional Geotechnical Investigation $5,993.21
Total Fixed Price Cost: $75,415.65 Total Reimbursable Cost: $0.00
Overall Total Cost: $75,415.65