Task Assignment Change Order Summary
This is a Task Assignment Change Order Form (Change Order No. 01) issued by the Florida Department of Environmental Protection (FDEP) for Contract CN335, Task Assignment 17, Project No. 61259. The contract involves Taylor Engineering, Inc. as the consultant, with Ken Craig, PE serving as the consultant representative. Jeffrey Whitfield acts as the FDEP Contract Manager. The project concerns Dam Safety Inspections at Lake Talquin, specifically addressing the Jackson Bluff Dam. The change order was executed on February 23, 2022, with approvals finalized by March 10, 2022.
The change order adds an additive scope of services for redesign of the radial gate lifting bracket assembly and anchor plate components at Jackson Bluff Dam to meet ASME BTH-1 industry standards. The amendment, executed February 18, 2022, increases the task amount by $7,709.93 in fixed fees, bringing the total task amount to $165,569.97. Services include structural analysis, redesign of the lifting cable assembly and anchor plate, preparation of a design memorandum with calculations, and construction drawings. The consultant team includes Taylor Engineering and sub-consultant Mead & Hunt, Inc., with labor costs itemized at hourly rates ranging from $101.00 to $203.01. The project schedule extends 60 days from execution, with a revised task end date of August 4, 2023. Deliverables consist of draft and final design memorandum and construction drawings provided via email in PDF format. Funding is allocated through FDEP's FLAIR coding system with Object Code 131500.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN335 17 01 61259
Lake Talquin Dam Safety Inspections
Taylor Engineering, Inc.
Ken Craig, PE 904.256.1334 kcraig@taylorengineering.com
Jeffrey Whitfield 850.245.2781 jeffrey.whitfield@FloridaDEP.gov
Additive scope to allow for additional services as described in the attached proposal dated 2/18/2022.
$ 157,860.04 $ 157,860.04 $ 157,860.04 $ 157,860.04 $ 7,709.93 $ 7,709.93
$ 0.00 $ 165,569.97 $ 165,569.97
11/22/2021
6/5/2023
6/5/2023
8/4/2023
Diane Langston A Diane Langston Digitally signed by A Diane Langston Date: 2022.02.23 13:05:47 -05'00'
Theresa Carron Theresa Carron Digitally signed by Theresa Carron Date: 2022.03.07 11:22:54 -05'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.03.07 11:43:53 -05'00'
Ken Craig, PE Digitally signed by Kenneth Craig Date: 2022.03.07 12:26:54 -05'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2022.03.10 16:13:33 -05'00'
61259 37501004093 080039/22 423001 U3200 131500 QK $ 7,709.93
$ 7,709.93
Dam Safety Services-Jackson Bluff Dam Contract CN 335 TA16, Change Order 1
February 18th, 2022
Subtask 12 – Radial Gate Lifting Bracket Analysis and Plans Description:
The Taylor Engineering team analyzed the structural components of the current lifting assembly and the anchor plate connecting it to the tainter gate for the radial gates at the Jackson Bluff dam to determine if the system meets the requirements of ASME BTH-1, which is the current industry standard. Based on these analyses, we determined that the current lifting cable assembly and anchor plate are structurally inadequate, and that the lifting assembly needs to be redesigned to meet current industry standards.
CONSULTANT Taylor Engineering Inc. and their sub-consultant Mead & Hunt, Inc. (Mead & Hunt) will provide the following amended services as follows: We will redesign the structural components of the current lifting cable assembly and the anchor plate connecting it to the gate to meet the requirements of
ASME BTH-1, which is the current industry standard. It is assumed that the design will be used only on gates that have the same gate hoists or have the same or less lifting capacity as Gate Nos. 5 – 7. We will prepare a new design memorandum that will include our design calculations. The Scope of Services of the original Task Order included time to prepare construction drawings for the current lifting cable assembly. This remaining time will be sufficient to prepare construction drawings for the strengthened lifting cable assembly. Our Amended Scope of Services does not include redesign or replacement of the existing cables that attach to the lifting cable assemblies.
Deliverables The Taylor Engineering Team will provide the following deliverables to the FDEP:
Draft and Final design memorandum and construction drawings ................ 1 copy via email (PDF file)
Performance Measures Deliverables will be reviewed by the FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost
Subtask 12 – Update EAP
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Taylor Engineering Principal $200.94 4 $803.75
Mead & Hunt Project Engineer $203.01 17 $3,451.17
Mead & Hunt Engineering I $129.00 26 $3,354.00
Mead & Hunt Administrative Assistant $101.00 1 $101.00
Subtask Total $7,709.93
Project Schedule The duration for this amendment to update the design and complete the drawings for the lifting assembly for the tainter gates is 60 days after this amendment is executed.