This is a Task Assignment Change Order Form (Change Order No. 03) issued by the Florida Department of Environmental Protection (FDEP) for Contract CN335, Task Assignment 17, concerning dam safety inspection services at Lake Talquin (Jackson Bluff Dam) located in Taylor, Florida. The contracting parties are the FDEP and Taylor Engineering, Inc., with Ken Craig, PE serving as the consultant representative and Ralph Perkins as the FDEP Contract Manager.

Change Order No. 03 authorizes an additive scope of work for a special purpose topographic survey, stability analyses with increased factors of safety for toe reinforcement design, construction drawings for fence and berm placement, and the 2022 facility inspection and report. The net increase to the task amount is $1,800.00 in reimbursable expenses (per diem and lodging) and $45,984.06 in fixed fee costs, bringing the total change order value to $47,784.06. This increases the cumulative task amount from $181,177.55 to $228,961.61. The original task execution date was November 22, 2021, with an original end date of June 5, 2023. The change order extends the task end date by 180 days to January 31, 2024. Deliverables include an inspection report and construction drawings with design memoranda in PDF and AutoCAD formats. All signatures were executed on February 1-7, 2023, with funding allocated across three budget codes totaling $47,784.06.

View the file

Other files

File Type Posted
CN-370000-CN335-CMC1.pdf PDF
CN-370000-CN335-T10CO2.pdf PDF
CN-370000-CN335-T14.pdf PDF
CN-370000-CN335-T14CO1.pdf PDF
CN-370000-CN335-T14CO3.pdf PDF
CN-370000-CN335-T15.pdf PDF
CN-370000-CN335-T17CO4.pdf PDF
CN-370000-CN335-T18.pdf PDF
CN-370000-CN335-T20.pdf PDF
CN-370000-CN335-T20CO1.pdf PDF
CN-370000-CN335-T21.pdf PDF
CN-370000-CN335-T21CO3.pdf PDF
CN-370000-CN335-T25.pdf PDF
CN-370000-CN335-T5.pdf PDF
CN-370000-CN335-T5CO1.pdf PDF
CN-370000-CN335-T5CO3.pdf PDF
CN-370000-CN335-T6.pdf PDF
CN-370000-CN335-T6CO4.pdf PDF
CN-370000-CN335-T8.pdf PDF
CN-370000-CN335-TA4.pdf PDF
CN-370000-CN335-TA5 CO4.pdf PDF
CN-370000-CN335-A1.pdf PDF
CN-370000-CN335-CMC5.pdf PDF
CN-370000-CN335-T1.pdf PDF
CN-370000-CN335-T10CO1.pdf PDF
CN-370000-CN335-T11CO2.pdf PDF
CN-370000-CN335-T11CO3.pdf PDF
CN-370000-CN335-T17CO2.pdf PDF
CN-370000-CN335-T19CO1.pdf PDF
CN-370000-CN335-T1CO2.pdf PDF
CN-370000-CN335-T21CO1.pdf PDF
CN-370000-CN335-T21CO2.pdf PDF
CN-370000-CN335-T23CO1.pdf PDF
CN-370000-CN335-T6CO1.pdf PDF
CN-370000-CN335-T7.pdf PDF
CN-370000-CN335-T8CO2.pdf PDF
CN-370000-CN335-T8CO3.pdf PDF
CN-370000-CN335-T8CO4.pdf PDF
CN-370000-CN335-T8CO5.pdf PDF
CN-370000-CN335-T8CO7.pdf PDF
CN-370000-CN335-TA11 CO1.pdf PDF
CN-370000-CN335-TA8CO1.pdf PDF
CN-370000-CN335.pdf PDF
CN-370000-CN335-CMC2.pdf PDF
CN-370000-CN335-T12.pdf PDF
CN-370000-CN335-T13.pdf PDF
CN-370000-CN335-T16.pdf PDF
CN-370000-CN335-T17.pdf PDF
CN-370000-CN335-T17CO1.pdf PDF
CN-370000-CN335-T1CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN335 17 03 61259

Lake Talquin Dam Safety Inspections

Taylor Engineering, Inc.

Ken Craig, PE 904.256.1334 kcraig@taylorengineering.com

Ralph Perkins 850.245.2460 ralph.perkins@floridadep.gov

Additive scope for a special purpose survey and increased factors of safety to be applied to the toe reinforcement design, and the 2022 inspection and report per the attached proposal dated 10/17/2022.

$ 157,860.04 $ 157,860.04 $ 181,177.55 $ 181,177.55

$ 1,800.00 $ 45,984.06 $ 47,784.06 $ 1,800.00 $ 227,161.61 $ 228,961.61

11/22/2021

6/5/2023

8/4/2023

1/31/2024

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.01 11:34:34 -05'00'

Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.02.01 11:46:59 -05'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.01 12:00:07 -05'00'

Ken Craig, PE Digitally signed by Kenneth Craig Date: 2023.02.02 11:44:02 -05'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.02.07 10:45:29 -05'00'

61259 37501004093 080039/21 675002 U3200 131500 XR $ 720.20

61259 37501004093 080039/22 408001 U3200 131500 PF $ 3,241.41

61259 37501004093 080039/22 423001 U3200 131500 QK $ 43,822.45

$ 47,784.06

1019 9 SO UTHS I DE BLVD , S TE 310 | J ACKS ON V IL LE F L 32256 | T EL 904 . 73 1. 7040

WWW .TAYLO REN G INE ER I N G.C OM

October 17, 2022

Theresa R. Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: Jackson Bluff Dam Additional Services – Amendment #2

CN335 TA17

(Taylor Proposal #P2022-163)

Dear Mrs. Carron:

Attached, please find a proposal to complete the subject project. Please review the attached and let me know if you have any questions or comments.

Sincerely, Kenneth R. Craig, PE Senior Vice President

CO3

1019 9 SO UTHS I DE BLVD , S TE 310 | J ACKS ON V IL LE F L 32256 | T EL 904 . 73 1. 7040

WWW .TAYLO REN G INE ER I N G.C OM

Dam Safety Services Jackson Bluff Dam

Contract CN 335 TA17 Amendment No. 2 October 17, 2022

Reason for Amendment The Florida Department of Environmental Protection (FDEP) requested the Taylor Engineering team provide additional engineering services at the Jackson Bluff Dam (Project). These services include providing the design and drawings to add a filter and stability berm at the north embankment to increase the factors of safety (FOS) with regard to seepage and slope stability.

FDEP is also planning to install a fence to keep out wild hogs that damage the earthen embankment by rooting. This amendment also includes an inspection of the Project, which was not within our original scope of services.

Scope of Services CONSULTANT Taylor Engineering Inc. and their sub-consultant Mead & Hunt will provide the following amended services as follows:

Taylor Engineering will perform a topographic survey of the north embankment. The survey will extend from the edge of water to 30 feet west of the access road and from the north side of the auxiliary spillway to approximately 2,500 feet north. The survey will also include the elevation of the top of pipe at eighteen monitoring wells and locating ten culverts that drain seepage water away from the toe of the slope. A site plan with one-foot contours will be created from the survey and used to develop construction drawings for the fence and toe berm placement project.

The site plan will be used to develop drawings showing the fence’s location and the extent of the toe berm materials. Stability analyses will be performed using the updated survey information to determine the thickness and location of the toe berm necessary to satisfy the minimum factors of safety recommended by the Federal Energy Regulatory Commission (FERC) for normal, 100-year, and Inflow Design Flood (IDF) loading conditions. The toe berm will also act as a filter and be designed to be compatible with the existing soils. The added material will also reduce the vertical gradient and increase the FOS with regard to seepage.

A professional engineer will travel to the Project to inspect the dam. The inspection will entail visual observation of the water-retaining structures and photographic documentation of conditions at the time of the inspection. An inspection report will be prepared that presents findings from the inspection, recommendations for maintenance or repairs, and select photographs from the inspection. The report will include the FDEP’s Condition Assessment form as an appendix. While on-site, we will also coordinate with the dam operator to identify the location of the proposed fence and the location of the toe berm.

Deliverables The Taylor Engineering team will provide the following deliverables to the FDEP:

Inspection report ............................................................................... 1 copy via email (PDF file)

Construction drawings and design memo .......................................... 1 copy via email (PDF file)

Subtask 14 - Special Purpose Survey, Site Plan, and Applied Factors of Safety

Subtask 15 - 2022 Facility Inspection and Report

CO3

pdf and Autocad files

Subtask 15

Subtask 14

Jackson Bluff Dam Dam Safety Services Amendment No. 2

Performance Measures FDEP will review deliverables to confirm they are complete, accurate, and timely.

Fixed Price Cost

Subtask 10 – Filter Placement Design and Plans (Amendment No. 2)

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Mead & Hunt Project Engineer $203.01 48 $9,744.48

Mead & Hunt Senior Engineer $183.00 16 $2,928.00

Mead & Hunt Engineering Tech III $138.00 33 $4,554.00

Mead & Hunt Administrative Assistant $101.00 3 $303.00

Taylor Engineering Senior Advisor (Survey) $202.53 50 $10,126.50

Taylor Engineering Staff Professional $86.40 46 $3,974.40

Taylor Engineering Technical Support

(CAD)

$101.61 8 $812.88

Subtask Total $32,443.26

Reimbursable Expenses (Taylor Engineering)

Per Diem $600.00

Lodging $1,200.00

Reimbursable Total Cost $1,800.00

Total for Subtask 10 (Amendment No. 2) $34,243.26

Subtask 12 – 2022 Inspection (Amendment No. 2)

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Taylor Engineering Principal $200.94 6 $1,205.64

Mead & Hunt Project Engineer $203.01 16 $3,248.16

Mead & Hunt Senior Engineer $183.00 48 $8,784.00

Mead & Hunt Administrative Assistant $101.00 3 $303.00

Subtask Total $13,540.80

Project Schedule

The duration to perform the site visit and prepare the inspection report is 60 days after this amendment is executed.

The duration to design the fence and stability berm and complete construction drawings is 120 days after this amendment is executed.

Subtask 15 - 2022 Facility Inspection and Report

Subtask 15 - 2022 Facility Inspection and Report

CO3

Subtask 14 - Special Purpose Survey, Site Plan, and Applied Factors of Safety

Subtask 14 - Special Purpose Survey, Site Plan, and Applied Factors of Safety

Total $47,784.06

Taylor Engineering Contract CN335

File details come from the government source that posted it. Updated .