This document is a Task Assignment Change Order (Change Order No. 5) issued by the Florida Department of Environmental Protection (FDEP) for the Oak Shore Drive Fishing Pier project located in Earl Gilbert Park in the City of Parker, Bay County, Florida. The contract is with Taylor Engineering, Inc., a consulting firm providing engineering and construction administration services. The change order was approved on September 21, 2023, and is part of a broader NRDA (Natural Resource Damage Assessment) Phase III restoration project.
Change Order No. 5 extends the task assignment end date from July 14, 2024, to December 2, 2024, and adds $16,253.76 in reimbursable costs (on a not-to-exceed basis) to cover additional site visits and bi-monthly coordination and progress meetings during the extended construction period through November 30, 2023. The extension was necessitated by construction delays caused by material shortages, labor constraints, and supply chain issues, which pushed the original substantial completion date from March 9, 2023, to November 30, 2023. The total contract amount with all change orders is now $390,704.59, consisting of $235,850.75 in fixed fees and $154,853.84 in reimbursable costs. The contract encompasses comprehensive services including design, permitting, bid administration, construction oversight, submittal reviews, and project closeout. Funding is available from the remaining project budget of $110,000.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN335 5 5 N2903
Earl Gilbert Park in City of Parker, Bay County, FL Oak Shore Drive Fishing Pier
Taylor Engineering, Inc.
Duncan Greer, P.E. 850-460-7040 DGreer@taylorengineering.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
This CO5 is updating the Task assignment end date to December 2, 2024 and to add budget to allow for additional site visits, progress meetings during the construction period.
$ 11,293.53 $ 11,293.53 $ 138,600.08 $ 235,850.75 $ 374,450.83 $ 16,253.76 $ 0.00 $ 16,253.76 $ 154,853.84 $ 235,850.75 $ 390,704.59
September 19, 2018
July 14, 2021
July 14, 2024
December 2, 2024
Jessica Madden Jessica Madden Digitally signed by Jessica Madden Date: 2023.09.14 13:44:53 -04'00'
Pearce Barrett, P.E. Pearce Barrett Digitally signed by Pearce Barrett Date: 2023.09.19 13:32:18 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.09.19 20:20:23 -04'00'
Jonathan Armbruster, P.E.
Angela Knecht
N2903 NRD03 37220500000 083654/12 099005 NRDR 131500 FJ $ 16,253.76
$ 16,253.7637202099005372201000008365412
Digitally signed by Jonathan Armbruster Date: 2023.09.20 21:12:54 -04'00'
Digitally signed by Angela Knecht Date: 2023.09.21 13:24:35 -04'00'
FLORIDA DEPARTMENT OF
Environmental Protection
Marjory Stoneman Douglas Building
3900 Commonwealth Boulevard Tallahassee, FL 32399
Ron DeSantis Governor
Jeanette NNuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Angela Knecht
Thru: Sarah Ketron
FROM: Pearce Barrett P.E.
SUBJECT: Oakshore Drive Pier, City of Parker, Bay County, CN335, Task Assignment No. 5, Change Order No. 5
DATE: August 29, 2023
Oakshore Drive Pier, a NRDA Phase III Project, located within Earl Gilbert City Park in the City of Parker, Bay County, Florida is comprised of the design, permitting and construction of a new fishing/pedestrian pier. This Task Assignment Change Order (TACO) is to extend construction administrative and observation services (Task 8.4) to cover the extended construction phase of the pier up through October, 2023. Extension of services described under Sub-Task 8.4 are deemed necessary for the successful completion of the project. This TACO will also extend the current Task Assignment from July 14, 2024 (CO No. 4) to December 02, 2024 to allow for sufficient time to construct the pier and provide coverage through the construction warrantee period. The reason for this extension and increase in fees is because the original sub-task 8.4 was to cover an anticipated construction period of ten (10) months. Due to unavoidable circumstances, such as material delays, labor shortages and supply train issues, the project’s original substantial completion date, which was set for March 9, 2023, was extended by construction Change Order No. 1, issued to H.G. Harders and Son, Inc (Construction Contractor) to July 9, 2023 then, through Construction Change Order No. 2 to October 1, 2023 and again by Construction Change Order No. 3 until November 30, 2023. Taylor Engineering has so far been able to maintain their costs and support the project through the first extension but will not be able to maintain within the existing budget for Task 8.4 with this latest extension of the construction period without additional fees.
The additional fees allocated to the Consultant by this Change Order are to be on a not to exceed reimbursable basis of $16,253.76 and will provide for additional site visits, and bi-monthly (2xs/mo.) coordination/progress meetings during the extended construction period thru November 30, 2023.
I approve the Consultant’s request for additional fees and find them to be reasonable. The funds for this TACO are available in the remaining project budget of $110,000.
The current and proposed project allocation for consulting fees through construction and close out for this Task Assignment are listed below:
Original Task Amount: $ 11,293.53 Task amount including all previous Change Orders: $363,157.30 Net increase in task amount for this Change Order: $ 16,253.76
Total Amount with all Change Orders: $390,704.59
DEP Agreement No. CN335, TA5, CO5, Page 1 of 7
OAK SHORE DRIVE FISHING PIER
DEP Agreement No. CN335
Task Assignment No. 5 Revised Scope of Services
Change Order No. 5
CONSTRUCTION PHASE ADMINISTRATION SERVICES CONSULTANT (ADDED PER CHANGE ORDER NO. 4)
The Consultant shall provide selected construction engineering, inspection, and administrative services during construction of the project. These services shall begin upon the award of the construction contract and receipt of notice to proceed (NTP) from the Department’s Project Manager and extend through project completion and final certification.
Pre-Construction Meeting and Regulatory Noticing
The Consultant will coordinate with the Department’s Project Manager to prepare for and conduct pre-construction meeting with the selected Construction Contractor after award and execution of the construction contract. The pre-construction meeting will occur at least 21 days prior to commencement of construction activities. The pre-construction meeting will occur in two parts, held in sequence on the same day. The first part of the meeting will include general construction information regarding schedule, access, permit requirements, Contract General and Special Conditions, and be attended by representatives of the Contractor, Department, City of Parker, FDEP and USACE regulatory and compliance staff. The second part of the pre-construction meeting will occur at the project site and focus on technical issues and clarification of the construction documents.
The pre-construction meeting will focus on describing the project and scope of work, reviewing the construction methodology, drawings and technical specifications, project schedule, general and specific conditions, environmental permits, and verifying construction access and work areas. In addition to responding to the Construction Contractor’s questions concerning the technical aspects of the work, the Consultant, together with the Department’s Project Manager, will discuss contract general and special conditions (i.e., requirements not provided in the construction drawings and technical specifications), lines of communication, specific roles and authority of the various parties involved with the project (e.g.: Department, Consultant, City, and Construction Contractor), mobilization/demobilization activities, areas proposed for laydown or storage of equipment, materials and supplies, project access, contract administration, review and processing of monthly progress payment(s), correspondence procedures, project schedule, progress meetings, submittal register, and labor requirements. Consultant shall take detailed minutes of the pre-construction meeting discussions and of the visit to the site with the Construction Contractor(s) and/or regulatory agencies. The pre-construction meeting will be held at a date, time, and place agreeable to the Consultant and Department’s Project Manager. The site visit with the Construction Contractor and participating agencies will further review site conditions as they pertain to construction activities, specifications, and project details.
The Consultant will prepare the technical submittals including digital copies of the regulatory plans and specifications if required by the regulatory permits and NTP(s). The Consultant will coordinate with the Department’s Project Manager, regulatory staff, and the Construction Contractor as necessary in support of the regulatory NTP submittals and requests to the regulatory agency(s). The Consultant will also submit a notice of commencement (NOC) to the regulatory agencies prior to construction start-up as required by regulatory permits.
Deliverables: Consultant shall provide to the Department’s Project Manager copies of the pre-construction meeting agenda, sign-in sheet, and minutes from the meeting. Consultant shall also provide any technical submittals for the regulatory NTP and NOC.
Schedule: The Pre-Construction Meeting shall occur at least twenty-one (21) days prior to commencement of construction. The Consultant shall provide a draft of the meeting agenda to the Department Project Manager at least ten
(10) days prior to the meeting for review and comment. Consultant will prepare and submit meeting minutes to all attendees at the meeting within one (1) week following the meeting.
DEP Agreement No. CN335, TA5, CO5, Page 2 of 7
Total Fixed Price for Subtask 8.1: $6,097.56
Pre-Construction Seagrass Verification
If required by regulators or determined necessary by the Department, Consultant will visit the project site and complete a limited survey to verify seagrass habitat conditions within the vicinity of proposed structure footprints, Construction Contractor’s proposed construction corridor(s), and a surrounding 30-foot buffer. The survey will employ qualitative and quantitative methods accepted by state and federal regulatory and resource agencies. The Consultant will collect detailed mapping information within the survey area using global positioning system equipment providing sub-foot horizontal accuracy. The Consultant will present findings in a brief memorandum including a figure of the observed area. This subtask excludes revisions or regulatory coordination that may be required should seagrasses be observed within the structure footprint.
Deliverables: Consultant shall provide a brief memorandum in electronic format (.pdf) summarizing the survey.
Schedule: Consultant will initiate this Subtask upon request from the Department’s Project Manager and complete the deliverables within 21 days.
Total Fixed Price for Subtask 8.2: $6,947.04
Construction Submittal Reviews
Description: The Consultant will review the Construction Contractor’s required submittals to assess compliance with contract documents. The Consultant shall, upon conclusion of a submittal review, provide the Department’s Project Manager with a summation of the submittals from the Construction Contractor and whether each submittal was approved, recommended for changes, or was rejected. All submittals received and status will be reviewed with the Department’s Project Manager and Contractor during bi-weekly construction progress meetings. The Consultant shall coordinate with the Department’s Project Manager and Construction Contractor to resolve issues of concern, discuss project plans and specifications, and discuss schedule and documentation. The Consultant shall coordinate with the Construction Contractor to address inconsistencies or missing submittals.
Deliverables: The Consultant shall provide to the Department’s Project Manager digital copies of the Contractors’ submittals and submittal register (summarizing the submittal dates and approvals) and the submittal reviews prepared by the Consultant. The Consultant shall also provide any revised submittals and reviews submitted during the construction phase.
Schedule: The Consultant shall review the submittals and provide final deliverables to the Department’s Project Manager within 15 days of receiving submittals from the Construction Contractor.
Total Cost Reimbursement (Not to Exceed) for Subtask 8.3: $15,233.34
The Consultant, upon submission and written acceptance by the Department’s Project Manager of available deliverables described under this Subtask, may request reimbursement for this subtask on a monthly basis.
Construction Observation and Administration (REVISED PER CHANGE ORDER NO. 5)
Description: Consultant shall perform periodic construction observation and administrative (COA) services as described herein to support the construction phase of the project and remain available throughout the project, with a planned maximum duration of 14 months, to assist the Construction Contractor’s interpretation of the design intent and
DEP Agreement No. CN335, TA5, CO5, Page 3 of 7 requirements. COA activities will include those services identified herein as needed to verify construction is proceeding in general accordance with the drawings, specifications, and permits. These activities will include the following:
1. a. Once the Construction Contractor has mobilized to the project site and throughout the construction phase, the Consultant will provide qualified personnel to provide onsite construction observation during critical periods of construction but no less than one visit every two weeks during active construction activities. Each site visit will include but not be limited to onsite observation and review of the Construction Contractor’s activities related to the following project features:
i. Protection of existing work and environmental resources;
ii. Protection of new work from damage;
iii. Protection of private property;
iv. Maintenance of current construction schedule;
v. Protection of land resources (e.g.: fuel and oil spill preventions, work areas, etc.);
vi. Protection of water resources (e.g.: stormwater pollution prevention, erosion and turbidity control, etc.) and other regulatory permit requirements;
vii. Protection of species identified in the environmental permits;
viii. Control of noise pollution;
ix. Project quality control procedures (to produce an end product that meets contract requirements);
x. Adherence to designation of employee parking, equipment and material storage areas;
xi. Maintenance of onsite bulletin board and project sign;
xii. Maintenance of project site security;
xiii. Cleanup of waste and debris;
xiv. Limitation of and maintenance of pedestrian access in areas of construction.
b. The Consultant shall maintain a construction observation log, in a format approved by the Department’s Project Manager, to document the observations made on the day of the site visit and any construction related conversations with Construction Contractor’s site representative(s). The log shall be reviewed with the Construction Contractor site representative and signed by both the observer and the Construction Contractor’s representative; the log will provide a daily log of construction progress, delays, and/or issues. The construction observation reports will document the date, weather conditions, personnel/visitors on site, the Construction Contractor’s general manpower (e.g., superintendent, field Consultant, laborers, etc.) and equipment (backhoe, bulldozer, cranes, pile driving equipment, etc.), and a daily summary of events. The Consultant will also keep a record of all phone conversations and copies of emails between the Consultant and Construction Contractor.
Copies of the observation logs, and record of phone conversations and emails between Consultant and Construction Contractor shall be submitted with monthly invoices.
c. The Consultant will notify the Department’s Project Manager of any observed permit violations, work stoppages, or conflicts and provide recommendations to the Department’s Project Manager as to how to proceed with the project. However, the Consultant shall not be responsible for jobsite safety or direct the Construction Contractor’s means and methods of construction.
2. Bi-monthly (twice a month) Coordination/Progress meetings will be held via a videoconferencing format agreed to between the Department’s Project Manager and the Consultant; or if necessary, Department Project Manager and Consultant may agree to hold these meetings on site. These meetings will include, at a minimum, the Department’s Project Manager, Consultant, Consultant’s on-site representative, and the Construction Contractor’s Project Manager. Other invitees may include, when needed, sub-consultants and sub-contractors, and representatives of the City. The project coordination meetings will be held during normal working hours at a time mutually agreed upon by the Department’s Project Manager, Consultant, and Construction Contractor during the Pre-construction Meeting. The Consultant will review the Contractor’s agenda and meeting minutes, coordinate revisions and clarifications, and distribute them to all attendees afterward. The progress meeting agenda shall generally include reviewing minutes of the previous meeting, work progress since the previous meeting and compared to the construction schedule, current definable features of work, submittal register, off-site activities, construction operations (e.g.: mobilization, site work, structures, environmental monitoring), testing results (e.g.: pile driving), changes to construction schedule, problem prevention, contract quality for
DEP Agreement No. CN335, TA5, CO5, Page 4 of 7 materials and workmanship, pending modifications, changes and substitutions, contractor’s monthly pay application, and other business, as appropriate. Consultant shall coordinate with Department’s Project Manager on setting the schedule for the coordination meetings and approval of the agenda.
3. Consultant will review of up to ten (10) (not including the final pay application) monthly Construction Contractor’s Pay Applications and provide the Department’s Project Manager with certification that the pay application is accurate and reflects construction activity completed during the period covered by the pay application;
4. Consultant will prepare of up to three (3) change order directives, to address unforeseen conditions arising during construction activities (e.g., not caused by issues arising from the drawings or specifications prepared by the Consultant);
5. Consultant will provide consultation to the Department’s Project Manager and/or Construction Contractor to resolve issues that may result from construction activities, interpretation of the drawings and specifications, construction schedule, or environmental monitoring;
6. Review and respond to up to five (5) requests for information (RFI) from Construction Contractor which includes one (1) plan revisions as part of the RFI process.
7. For observations of electrical utilities to confirm general conformance with the Contract Documents, the Consultant shall provide a qualified Professional who is under the supervision of the Engineer of Record (or Consultant Project Manager) to coordinate with the Department’s Project Manager and conduct up to two (2) site visits during key intervals of the construction (e.g., pay applications, building permit compliance, etc.) documents
8. The Consultant will administer the construction contract from their Destin office and from the project site and will remain available throughout construction to provide advice and consultation to Department through site visits and videoconferences. The role of the Consultant under this Subtask will be to address questions pertaining to engineering, design, permitting issues, scheduling, and any proposed changes to the project design.
9. The Consultant shall provide, through senior management, review and quality control/quality assurance oversight during the performance of this Subtask.
If deemed necessary to perform additional onsite construction observation visits to solve unanticipated problems or if the construction extends beyond the original construction period outside of the control of the Consultant, then any additional costs to the Consultant because of these events will be addressed through a Task Assignment Change Order.
Deliverables: The Consultant shall identify in their monthly requests for payment each of the observation and/or administrative activities performed, identity of site personnel performing the site visits, and the dates and hours expended on which the site visits were provided. All COA activities performed during the month shall be supported by sufficient documentation. The Consultant shall provide to the Department’s Project Manager copies of all daily observation reports, photographs where necessary, notes and minutes from progress meetings, notes from phone calls, copies of emails, and change orders.
Schedule: The Construction Observation and Administration services shall commence upon the issuance of the Notice- To-Proceed to the Construction Contractor and continue throughout the construction period. The Subtask will terminate immediately prior to the substantial completion inspection (Subtask 9.1). The final deliverables shall be provided within 30 days following construction completion. Monthly deliverables shall be provided within ten (10) working days of end of the preceding month to support monthly billings.
Total Cost Reimbursement (Not to Exceed) for Subtask 8.4: $139,620.50
The Consultant, upon submission and written acceptance by the Department’s Project Manager of available deliverables described under this subtask, may request reimbursement for this subtask on a monthly basis (over a duration of thirteen [13] months).
DEP Agreement No. CN335, TA5, CO5, Page 5 of 7
Performance Measures for Task 8: The Department’s Project Manager shall review the submittals and submittal register.
The Department’s Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Total Cost for Task 8: $167,898.44
Fee Summary
Fee Summary
Task Fixed Price Cost
Reimbursement (Not to Exceed)
Subtask 1 - Natural Resource Survey and Coordination Meeting $11,293.53
Subtask 2 - Post-Storm Site Assessment $7,340.02
Subtask 3 - Data Collection $33,923.16
Subtask 4.1 - Kick-Off Meeting $3,154.48
Subtask 4.2 - Coastal Conditions Analyses (CCA) $9,267.10
Subtask 4.3 - Preliminary Engineering Design $21,596.58
Subtask 5.1 - Permit Application and Supporting Documentation Preparation $12,543.84
Subtask 5.2 - Sovereign Submerged Land Lease Modification and Recording $0.00
Subtask 5.3 - RAI Response and Regulatory Coordination $6,578.82
Subtask 5.4 - Seagrass Survey Verification $3,468.15
Subtask 6.1 - Structural Engineering Design (90%-Complete) $62,669.84 Subtask 6.2 - Final Construction Drawings and Technical Specifications (100%- Complete) $15,143.88
Subtask 7 - Bid Administration Assistance $9,531.78
Subtask 8.1 – Pre-Construction Meeting and Regulatory Noticing $6,097.56
Subtask 8.2 – Pre-Construction Seagrass Verification $6,947.04
Subtask 8.3 – Construction Submittal Reviews $15,233.34
Subtask 8.4 – Construction Observation and Administration $139,620.50
Subtask 9.1 – Substantial Completion Inspection and Certification $7,220.10
Subtask 9.2 – Final Completion Inspection and Certification $5,719.89
Subtask 9.3 – Regulatory Certifications and Certificate of Occupancy $8,043.66
Subtask 9.4 – Project Documentation $5,311.32
Total Fixed Price: $235,850.75
Total Cost Reimbursement: $154,853.84
Grand Total: $390,704.59
DEP Agreement No. CN335, TA5, CO5, Page 6 of 7
Project Schedule
Subtask 1 - Natural Resource Survey and Coordination Meeting
Assuming the Task Assignment is authorized by September 17, 2018, the natural resource survey shall occur prior to September 30, 2018 in accordance with NMFS guidelines. If schedule requirements necessitate, the Consultant may request and secure written approval from regulatory agencies to conduct surveys into early October; however, such approval is not guaranteed. The draft natural resource survey report will be provided to the DEP Project Manager within four (4) weeks from the date of the survey(s) (Subtasks 1.1.1-1.1.2). The Consultant shall schedule the coordination meeting within two (2) weeks of completion of the natural resource survey and provide draft meeting agenda before the meeting and attendance log and meeting minutes within one (1) week of the meeting date. Final task deliverables will be provided to the DEP Project Manager within one (1) week following receipt of DEP comments.
Subtask 2 - Post-Storm Site Assessment
The subconsultant will conduct the site assessment within three weeks of authorization (excluding the period between December 24, 2018 – January 1, 2019).
Subtask 3 - Data Collection The draft Post-Storm Assessment Memorandum will be provided to the DEP Project Manager within three (3) weeks from the date of the field observations (Subtask 2.1).
Subtask 4.1 - Kick-Off Meeting Final task deliverables will be provided to the DEP Project Manager within one (1) week following culmination of the coordination meeting and receipt of DEP comments.
Subtask 4.2 - Coastal Conditions Analyses (CCA)
The boundary and field survey shall be completed within six weeks following the Notification to Proceed from the DEP Project Manager following completion of Task
2. Final deliverables shall be provided within 30 days of survey data collection.
Subtask 4.3 - Preliminary Engineering Design
The geotechnical field investigations shall be completed within six weeks following the completion of Task 2 and upon written authorization from the DEP Project Manager. Notably, wind, wave, and current conditions may affect the proposed schedule for offshore geotechnical data collection. Final deliverables shall be provided within approximately 30 days of geotechnical data collection.
Subtask 5.1 - Permit Application and Supporting Documentation Preparation
The Consultant shall coordinate with the DEP project manager and schedule the Kick-Off Meeting within approximately three (3) weeks of authorization. The Consultant shall provide the deliverable(s) within one (1) week of the meeting.
Subtask 5.2 - Sovereign Submerged Land Lease Modification and Recording
The Consultant shall provide the deliverable within four (4) weeks of authorization.
Subtask 5.3 - RAI Response and Regulatory Coordination
The Consultant shall provide the deliverable within six (6) weeks of completion of Subtask 4.2 including receipt of written DEP recommendation for design storm condition (e.g., 50-yr storm event).
Subtask 5.4 - Seagrass Survey Verification
The Consultant shall provide completed DEP and USACE permit applications within four (4) weeks of acceptance of the preliminary design (i.e., 60%-complete, permit) drawings (Subtask 4.3).
Subtask 6.1 - Structural Engineering Design (90%- Complete)
The Consultant shall provide the deliverable within four (4) weeks of DEP acceptance of the proposed SSLL.
Subtask 6.2 - Final Construction Drawings and Technical Specifications (100%-Complete)
The Consultant shall provide the deliverable within six (6) weeks of completion of Subtask 4.2 including receipt of written DEP recommendation for design condition (e.g., 50-yr storm event).
DEP Agreement No. CN335, TA5, CO5, Page 7 of 7
Subtask 7 - Bid Administration Assistance
The Consultant shall provide the deliverable within three (3) weeks of authorization of Change Order 3.
Subtask 8.1 – Pre- Construction Meeting and Regulatory Noticing
The Pre-Construction Meeting shall occur at least twenty-one (21) days prior to commencement of construction. The Consultant shall provide a draft of the meeting agenda to the Department Project Manager at least ten (10) days prior to the meeting for review and comment. Consultant will prepare and submit meeting minutes to all attendees at the meeting within one (1) week following the meeting.
Subtask 8.2 – Pre- Construction Seagrass Verification
Consultant will initiate this Subtask upon request from the Department’s Project Manager and complete the deliverables within 21 days.
Subtask 8.3 – Construction Submittal Reviews
The Consultant shall review the submittals and provide final deliverables to the Department’s Project Manager within 15 days of receiving submittals from the Construction Contractor.
Subtask 8.4 – Construction Observation and Administration
The Construction Observation and Administration services shall commence upon the issuance of the Notice-To-Proceed to the Construction Contractor and continue throughout the construction period. The Subtask will terminate immediately prior to the substantial completion inspection (Subtask 9.1). The final deliverables shall be provided within 30 days following construction completion. Monthly deliverables shall be provided within ten (10) working days of end of the preceding month to support monthly billings.
Subtask 9.1 – Substantial Completion Inspection and Certification
Project closeout services shall commence once the Construction Contractor submits a request to certify the project substantially complete and be conducted in accordance with schedule in the construction contract documents.
Subtask 9.2 – Final Completion Inspection and Certification
Final Completion Inspection and Certification shall commence once the Construction Contractor submits a request to certify the project complete and be conducted in accordance with the schedule in the construction contract documents.
Subtask 9.3 – Regulatory Certifications and Certificate of Occupancy
Consultant shall provide copies of deliverables within 21 days following the Final Completion Inspection (Subtask 9.2)
Subtask 9.4 – Project Documentation
Consultant will provide the digital library and final progress report within 30 days of the Final Completion Inspection.
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK