This is a Task Assignment Change Order Form (Change Order No. 02) issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN335, Task Assignment No. 17, involving the consultant firm Taylor Engineering, Inc. The project is located at Lake Talquin and concerns Dam Safety Inspections in Leon County, Florida. The FDEP Contract Manager is Ralph Perkins, and the Consultant Representative is Ken Craig, PE. The change order was approved on July 20, 2022, by authorized representatives from both FDEP and Taylor Engineering, including Budget Representative Diane Langston, Project Manager Theresa Carron, Contract Manager Ralph Perkins, and Contract Authority Bryan Bradner.
The change order authorizes an additive scope to the existing task for a Historic Structures Survey of the Jackson Bluff Dam at Lake Talquin, based on a proposal dated July 19, 2022. The net increase in task amount for this change order is $15,607.58, bringing the total task amount with all change orders to $181,177.55. The survey scope includes documentation of the National Register-eligible dam constructed in 1927, archival quality photographs, completion of the Florida Master Site File Historic Structures Form, and assessment of project impacts on the historic structure. Deliverables include a Historic Structures Survey Report with historic context and character-defining features analysis, and a Master Site File with archival photographs. The project duration is 60 days from Notice to Proceed, with the new task end date established as August 4, 2023. Labor costs are fixed price, involving Principal, Program Manager, Principal Investigator, GIS Specialist, and Clerical positions from Taylor Engineering and Gulf South Research Corporation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN335 17 02 61259
Lake Talquin Dam Safety Inspections
Taylor Engineering, Inc.
Ken Craig, PE 904.256.1334 kcraig@taylorengineering.com
Ralph Perkins 850.245.2460 ralph.perkins@FloridaDEP.gov
Additive scope to allow for a Historic Structures Survey per the attached proposal dated 7/19/2022.
$ 157,860.04 $ 157,860.04 $ 165,569.97 $ 165,569.97 $ 15,607.58 $ 15,607.58
$ 0.00 $ 181,177.55 $ 181,177.55
11/22/2021
6/5/2023
8/4/2023
8/4/2023
Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.07.20 12:09:00 -04'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2022.07.20 11:38:49 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.07.20 14:07:15 -04'00'
Ken Craig, PE Digitally signed by Kenneth Craig Date: 2022.07.20 15:02:04 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2022.07.29 13:39:48 -04'00'
61259 37501000115 080039/22 423001 U3200 131500 QK $ 15,607.58
$ 15,607.58