About this file

This is a Task Assignment Change Order Form submitted to the Florida Department of Environmental Protection (FDEP) by Taylor Engineering, Inc. The change order documents a time extension for the Sea Level Impact Projection (SLIP) Study project, with FDEP Contract Number CN335, Task Assignment Number TA10, and Project Number R2144. The change order was processed and approved by FDEP personnel including Budget Representative Lisa Yarborough, Project Manager Whitney Gray, Contract Manager Jeffrey Whitfield, and Contract Authority Alex Reed on July 30, 2021.

The change order extends the task execution timeline by 31 days to complete critical licensing and copyright components for Subtask 7 of the SLIP Study project. The original task end date of July 30, 2021 was extended to August 30, 2021. This is a time-only extension with no change to the task amount; the total task amount remains $198,285.81, consisting of $3,000.00 in reimbursement and $195,285.81 in fixed fees. The extension was requested by Taylor Engineering's consultant representative Angela Schedel to allow completion of technical system documentation and licensing agreement deliverables that could not be finalized by the original deadline. The change order was funded through FDEP's FLAIR code allocation for the project.

View the file

Other files

File Type Posted
CN-370000-CN335-CMC2.pdf PDF
CN-370000-CN335-T12.pdf PDF
CN-370000-CN335-T13.pdf PDF
CN-370000-CN335-T16.pdf PDF
CN-370000-CN335-T17.pdf PDF
CN-370000-CN335-T17CO1.pdf PDF
CN-370000-CN335-T1CO1.pdf PDF
CN-370000-CN335-T2.pdf PDF
CN-370000-CN335-T22.pdf PDF
CN-370000-CN335-T23.pdf PDF
CN-370000-CN335-T24.pdf PDF
CN-370000-CN335-T5CO5.pdf PDF
CN-370000-CN335-T6CO2.pdf PDF
CN-370000-CN335-T8CO6.pdf PDF
CN-370000-CN335-CMC1.pdf PDF
CN-370000-CN335-T14.pdf PDF
CN-370000-CN335-T14CO1.pdf PDF
CN-370000-CN335-T14CO3.pdf PDF
CN-370000-CN335-T15.pdf PDF
CN-370000-CN335-T17CO4.pdf PDF
CN-370000-CN335-T18.pdf PDF
CN-370000-CN335-T20.pdf PDF
CN-370000-CN335-T20CO1.pdf PDF
CN-370000-CN335-T21.pdf PDF
CN-370000-CN335-T21CO3.pdf PDF
CN-370000-CN335-T25.pdf PDF
CN-370000-CN335-T5.pdf PDF
CN-370000-CN335-T5CO1.pdf PDF
CN-370000-CN335-T5CO3.pdf PDF
CN-370000-CN335-T6.pdf PDF
CN-370000-CN335-T6CO4.pdf PDF
CN-370000-CN335-T8.pdf PDF
CN-370000-CN335-TA4.pdf PDF
CN-370000-CN335-TA5 CO4.pdf PDF
CN-370000-CN335-CMC3.pdf PDF
CN-370000-CN335-CMC4.pdf PDF
CN-370000-CN335-T10.pdf PDF
CN-370000-CN335-T11.pdf PDF
CN-370000-CN335-T11CO4.pdf PDF
CN-370000-CN335-T14CO2.pdf PDF
CN-370000-CN335-T16CO1.pdf PDF
CN-370000-CN335-T19.pdf PDF
CN-370000-CN335-T1CO3.pdf PDF
CN-370000-CN335-T5CO2.pdf PDF
CN-370000-CN335-T6CO3.pdf PDF
CN-370000-CN335-T9.pdf PDF
CN-370000-CN335-TA3.pdf PDF
PC-370000-CN335.pdf PDF
CN-370000-CN335-A1.pdf PDF
CN-370000-CN335-CMC5.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN335 TA10 2 R2144

FDEP Sea Level Impact Projection (SLIP) Study

Taylor Engineering, Inc.

Angela Schedel 904-256-1305 aschedel@taylorengineering.com

Jeffrey Whitfield 850-245-2630 Jeffrey.Whitfield@FloridaDEP.gov

Add 31 days to work out critical licensing and copyright components. This is a time only extension to complete subtask 7 as per the attached e-mail from the consultant dated 7/30/2021.

$ 10,188.00 $ 290,267.00 $ 300,455.00 $ 3,000.00 $ 195,285.81 $ 198,285.81

$ 0.00 $ 0.00 $ 0.00 $ 3,000.00 $ 195,285.81 $ 198,285.81

10/26/2020

7/30/2021

7/30/2021

8/30/2021

Lisa Yarborough Lisa Yarborough Digitally signed by Lisa Yarborough Date: 2021.07.30 09:39:00 -04'00'

Whitney Gray

Jeffrey Whitfield

Angela Schedel

Alex Reed

R2144 37538010005 100593/00 000286 U1620 241000 AT $ 198,285.81

$ 198,285.8137101000286375004000010059300

Whitney Gray Digitally signed by Whitney Gray Date: 2021.07.30 10:47:53 -04'00'

Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2021.07.30 11:34:57 -04'00'

Angela Schedel Digitally signed by Angela Schedel Date: 2021.07.30 12:45:40 -04'00'

Date: 2021.07.30 15:57:12 -04'00'

Mahan, Sarah

From: Mahan, Sarah Sent: Friday, July 30, 2021 9:04 AM To: Mahan, Sarah Subject: FW: FDEP SLIP Tool Final Invoice Question

From: Angela Schedel <aschedel@taylorengineering.com> Sent: Friday, July 30, 2021 8:52 AM To:Mahan, Sarah <Sarah.Mahan@FloridaDEP.gov>; Gray, Whitney <Whitney.Gray@FloridaDEP.gov> Cc: Bonnie Woolard <bwoolard@taylorengineering.com>; John N. Messer <jmesser@taylorengineering.com>; Laura Rosenbaum <lrosenbaum@taylorengineering.com> Subject: RE: FDEP SLIP Tool Final Invoice Question

Sarah, As requested by DEP, we are asking for a time extension for subtask 7 of the SLIP Study project, TA #10, Project #R2144, Contract #CN335. Our current TA is set to expire on 7/30/21, and we believe an extension of 31 days is sufficient time to finish this subtask.

Best, Angela

Angela Schedel, Ph.D., P.E. | Vice President, Community Resilience Main: 904 731 7040 | Direct: 904 256 1305

From: Angela Schedel <aschedel@taylorengineering.com> Sent: Thursday, July 29, 2021 9:42 AM To: Gray, Whitney <Whitney.Gray@FloridaDEP.gov> Cc: Bonnie Woolard <bwoolard@taylorengineering.com>; John N. Messer <jmesser@taylorengineering.com>; Mahan, Sarah <Sarah.Mahan@FloridaDEP.gov> Subject: FDEP SLIP Tool Final Invoice Question

Whitney, Since you are out of the office tomorrow, I wanted to check in with you and see if your team has accepted the deliverables which are due tomorrow. Our billing specialist, Bonnie, is out of the office tomorrow, and we would prefer to send the invoice today. However, last month our invoice arrived before the deliverables were complete and that caused a few headaches. Alternately, we can send the final invoice on Monday when Bonnie is back in the office.

The deliverables due tomorrow, July 30th, are:

Task 5 (re tasked) deliverables SLIP web application User Acceptance Test (UAT) test scenarios and discrepancy corrections Requirements Traceability Matrix (RTM)

Task 7 deliverables Technical system documentation Licensing agreement

Thank you.

Angela

Angela Schedel, Ph.D., P.E. |Vice President, Community Resilience Taylor Engineering, Inc.

10199 Southside Blvd., Suite 310, Jacksonville, FL 32256 Main: 904 731 7040 | Direct: 904 256 1305 www.taylorengineering.com Destin | Jacksonville | Sarasota | Tampa