Task Assignment Notification and Scope of Work Summary
This document is a Task Assignment Notification Form and detailed Scope of Work proposal between the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, and Cummins Cederberg, Inc., a consulting engineering firm. The project, designated as Contract CN330, Task Assignment TA23, involves road improvement design and engineering services at Avalon State Park located along A1A in Fort Pierce, Florida. The project is owned and managed by FDEP, with Ralph Perkins serving as the FDEP Contract Manager and Del Cobb as the FDEP Project Manager. Cummins Cederberg, Inc. is represented by Jordon Cheifet, PE, CFM.
The contract encompasses comprehensive engineering services for resilient road improvements at the park entrance and roadway, with a fixed price cost of $95,918.23. Services are structured across six major subtasks: (1) Field Investigations including topographic survey, geotechnical investigation, and site assessment ($34,461.68); (2) 60% Engineering Design ($25,035.83); (3) 100% Engineering Design ($13,819.83); (4) Environmental Permitting for South Florida Water Management District 10-2 Certification ($5,580.82); (5) Bidding Assistance ($2,449.84); and (6) Construction Administration including pre-construction, three construction observation phases, and certification and closeout ($14,570.23). The project schedule spans from authorization to proceed through project closeout, with individual subtask durations ranging from 40 to 120 calendar days. Payment will be made upon FDEP approval of deliverables for each subtask. The contract commenced upon execution on May 3, 2023, with an anticipated completion date of May 3, 2026.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN 330 TA 23 FDEP-DRP 61514C
Avalon State Park Road Improvement Design&Engineering @ Avalon St. Park
Cummins Cederberg, Inc.
Jordon Cheifet, PE, CFM (561) 658-1296 jcheifet@cumminscederberg.com
Ralph Perkins, or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Road Improvement Design and Engineering at Avalon St. Park per attached proposal dated 5/3/23.
Del Cobb, or successor
Upon Execution $ 95,918.23 5/3/26
$ 95,918.23
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.05.03 13:53:59 -04'00'
Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2023.05.03 16:20:04 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.05.04 08:47:02 -04'00'
Jordon Cheifet, P.E.,C.F.M.
Digitally signed by Jordon Cheifet Date: 2023-05-08 10:23:01
Jordon Cheifet Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.05.10 08:52:49 -04'00'
61514C 37505000202 080039/23 423001 U3200 131500 QK $ 95,918.23
$ 95,918.23
CUMMINS CEDERBERG, INC. | South Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
May 3, 2023 132100
Del Cobb, Project Manager
Florida Department of Environmental Protection
Division of Recreation and Parks
Bureau of Design and Construction
3900 Commonwealth Boulevard, MS 520
Tallahassee, FL 32399
Via: Del.L.Cobb@FloridaDEP.gov
RE: Contract CN330, Task Assignment: TA23 Proposal for Road Improvement Design and Engineering at Avalon St. Park
Dear Mr. Cobb:
Cummins Cederberg, Inc. (Cummins Cederberg) is pleased to present this proposal for engineering services with respect to resilient road improvements at Avalon St. Park, located along
A1A in Ft. Pierce. It is our understanding that the Florida Department of Environmental Protection
(FDEP) is interested in improving the existing park entrance and roadway to stabilize the entrance road, create some parking spots, and replace the entrance gate.
For your review, Cummins Cederberg, Inc. (Cummins Cederberg) has prepared the attached proposal summary and man-hour documentation for the service tasks identified below:
▪ Subtask 1 – Field Investigations o Subtask 1A – Topographic Survey o Subtask 1B – Geotechnical Investigation o Subtask 1C – Site Assessment
▪ Subtask 2 – 60% Engineering Design
▪ Subtask 3 – 100% Engineering Design
▪ Subtask 4 – Environmental Permitting
▪ Subtask 5 – Bidding Assistance
▪ Subtask 6 – Construction Administration o Subtask 6A – Pre-Construction o Subtask 6B – Construction Observation 1 o Subtask 6C – Construction Observation 2 o Subtask 6D – Construction Observation 3 o Subtask 6E – Certification and Closeout http://www.cumminscederberg.com/ mailto:Andrew.Lippens@FloridaDEP.gov
Avalon St. Park Road Improvements 132100
May 3, 2023 Page 2 of 14
Please review that attached Proposal Summary and Deliverables.
Sincerely, CUMMINS CEDERBERG, INC.
Jordon Cheifet, PE, CFM
Senior Engineer
May 3, 2023 Page 3 of 14
CUMMINS CEDERBERG, INC. | South Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Avalon St. Park Roadway Improvements
A1A, Ft. Pierce, Florida
Contract: CN330 Task: TA23
Cummins Cederberg, Inc. (Cummins Cederberg) is pleased to present this Scope of Work to the
Florida Department of Environmental Protection (FDEP) for engineering and environmental consulting services in support of the resilient road improvements at Avalon State Park. The area of concern extends from A1A to the Avalon West Day Use Area, was outlined during a site visit with Park staff on November 21, 2022, and is summarized in the figure below.
Figure 1: Project Location
Subtask 1: Field Investigations
Description:
1A Topographic Survey: Cummins Cederberg will complete topographic surveying for the
Project area to serve as the basis for subsequent analysis, planning, design, and regulatory permitting. The survey will encompass the area shown in Figure 1. Along A1A, cross sections will be taken to 100 feet each way of the entry road at approximate fifty (50) foot intervals, and cross sections will be taken at approximate fifty (50) foot intervals from edge of vegetation to edge of vegetation, approximately 2,500 feet westward into the park along the existing dirt entry road. The diagonal wooden fence on each side will also be located for reference. Utilities within the specific Project area will also be located using Ground Penetrating Radar (GPR), marked, and included in the survey map for use in design. The survey will be referenced horizontally to the Florida State Plane Coordinate System (NAD83/11) and vertically to the
North American Vertical Datum of 1988 (NAVD88).
1B Geotechnical Investigation: Cummins Cederberg will complete a geotechnical investigation for the Project area to serve as the basis for subsequent analysis, planning, design, and regulatory permitting. The investigation will include two (2) Standard Penetration
Test (SPT) borings (ASTM D1586) to depths of 10 feet below the existing grade to characterize the soil. Eight (8) hand auger borings to depths of 5-7 feet below existing grade will also be performed to characterize the soils under the entry road. A report will be prepared with engineering analysis of all data obtained to evaluate general subsurface conditions and to develop engineering recommendations to guide site preparation procedures, pavement design, and any other pertinent geotechnical engineering aspects of the project.
May 3, 2023 Page 4 of 14
1C Site Assessment: Cummins Cederberg will perform a site visit to observe existing conditions relative to roadway design and collect relevant design criteria. Utilities located under Task 1A will be reviewed and verified. A desktop assessment of trees surveyed under
Task 1A will be reviewed to evaluate potential impacts to vegetation.
Deliverable:
• Subtask 1A - Topographic Survey, Signed and Sealed by a Professional Surveyor and
Mapper (CAD/PDF)
• Subtask 1B – Geotechnical Investigation Report, Signed and Sealed by a Professional
Engineer (PDF)
• Subtask 1C – Field Observation Summary (PDF)
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1A
Firm Name Position Classification Hourly
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 8 $1,153.92
Cummins Cederberg Senior Engineer $135.00 16 $2,160.00
Cummins Cederberg Associate Engineer II $98.07 8 $784.56
Cummins Cederberg Senior Designer $103.86 8 $830.88
Craig A. Smith &
Associates
Professional Surveyor and
Mapper/VP
$171.63 12 $2,059.56
Craig A. Smith &
Associates
Surveyor Crew $124.50 60 $7,470.00
Craig A. Smith &
Associates
Surveyor Field Crew
Coordinator
$99.00 20 $1,980.00
Craig A. Smith &
Associates
Survey CAD Technician $63.00 46 $2,898.00
Craig A. Smith &
Associates
Utility Locates $126.45 20 $2,529.00
Sub-Total $21,865.92
Subtask 1B
Firm Name Position Classification Hourly
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 4 $576.96
Cummins Cederberg Senior Engineer $135.00 4 $540.00
Cummins Cederberg Associate Engineer II $98.07 4 $392.28
May 3, 2023 Page 5 of 14
Andersen Andre
Consulting Engineers, Inc.
Principal Engineer (P.E.) $175.00 3 $525.00
Andersen Andre
Consulting Engineers, Inc.
Staff Geotechnical Engineer $80.00 66.75 $5,340.00
Sub-Total $7,374.24
Subtask 1C
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 2 $288.48
Cummins Cederberg Senior Engineer $135.00 8 $1,080.00
Cummins Cederberg Associate Engineer II $98.07 4 $392.28
Chen Moore and
Associates
Senior Project Manager $154.46 6 $926.76
Chen Moore and
Associates
Project Engineer $106.38 16 $1,702.08
Chen Moore and
Associates
Senior Designer $103.99 8 $831.92
Sub-Total $5,221.52
Reimbursable Cost:
Postage
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost $
Total for Subtask 1: $34,461.68
Subtask 2: Engineering - 60% Engineering Design
Description: Cummins Cederberg will prepare 60% construction documents pertaining to civil engineering for the purpose of Owner review and interdisciplinary coordination. Hydraulic calculations for drainage improvements will be developed and a design narrative will be prepared.
An Opinion of Probable Cost (OPC) for the proposed work will be developed. Cummins
Cederberg will attend up to one (1) virtual meeting with the Client for project coordination to refine the scope or discuss project details. Plans are anticipated to include:
• Existing Conditions
• Demolition
• Paving, Grading, and Drainage
May 3, 2023 Page 6 of 14
• Stormwater Pollution Prevention
• Maintenance of Traffic
• Associated Details, General Notes, and Specifications
Deliverable: 60% Construction Plans (PDF), 60% OPC (PDF) complete, accurate, and timely.
Subtask 2
Firm Name Position Classification Hourly
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 4 $576.96
Cummins Cederberg Senior Engineer $135.00 6 $810.00
Cummins Cederberg Associate Engineer II $98.07 12 $1,176.84
Cummins Cederberg Senior Designer $103.86 24 $2,492.64
Chen Moore and
Associates
Principal $279.39 1 $279.39
Chen Moore and
Associates
Senior Project Manager $154.46 12 $1,853.52
Chen Moore and
Associates
Project Engineer $106.38 50 $5,319.00
Chen Moore and
Associates
Senior Designer $103.99 120 $12,478.80
Chen Moore and
Associates
Clerical $48.68 1 $48.68
Sub-Total $25,035.83
Printing
Total for Subtask 2: $25,035.83
Subtask 3: 100% Engineering Design
Description: Cummins Cederberg will prepare 100% construction documents pertaining to civil engineering by incorporating final comments provided under Subtask 2. Hydraulic calculations for
May 3, 2023 Page 7 of 14 drainage improvements will be finalized and the design narrative will be finalized. The Opinion of
Probable Cost (OPC) for the proposed work will be finalized. Cummins Cederberg will attend up to one (1) virtual meeting with the Client for project coordination prior to finalizing the plans.
Technical specifications will be included in the plans and will accompany the FDEP front-end contract documents.
Deliverable: 100% Construction Plans (PDF), 100% OPC (PDF)
Subtask 3
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 2 $288.48
Cummins Cederberg Senior Engineer $135.00 2 $270.00
Cummins Cederberg Associate Engineer II $98.07 4 $392.28
Cummins Cederberg Senior Designer $103.86 16 $1,661.76
Chen Moore and
Associates
Principal $279.39 1 $279.39
Chen Moore and
Associates
Senior Project Manager $154.46 8 $1,235.68
Chen Moore and
Associates
Project Engineer $106.38 32 $3,404.16
Chen Moore and
Associates
Senior Designer $103.99 60 $6,239.40
Chen Moore and
Associates
Sub-Total $13,819.83
Printing
Total for Subtask 3: $13,819.83
Subtask 4: Environmental Permitting
May 3, 2023 Page 8 of 14
Description: Cummins Cederberg will prepare and submit environmental permit applications, as required to the South Florida Water Management District (SFWMD) for a 10-2 Certification.
Deliverable: Environmental Permit Application (PDF)
Subtask 4
Firm Name Position Classification Hourly
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 2 $288.48
Cummins Cederberg Project Manager $99.51 2 $199.02
Cummins Cederberg Project Scientist $90.00 12 $1,080.00
Chen Moore and
Associates
Senior Project Manager $154.46 4 $617.84
Chen Moore and
Associates
Project Engineer $106.38 8 $851.04
Chen Moore and
Associates
Senior Designer $103.99 24 $2,495.76
Chen Moore and
Associates
Sub-Total $5,580.82
Printing
Total for Subtask 4: $5,580.82
Subtask 5: Bidding Assistance
Description: Cummins Cederberg will attend up to one (1) pre-bid meeting and review and respond to questions from potential bidders pertaining to the Project. Cummins Cederberg will review submitted bids and provide a written evaluation relative to the lowest and qualified bidder.
Deliverable: Bidder Recommendation Letter (PDF)
May 3, 2023 Page 9 of 14
Subtask 5
Firm Name Position Classification Hourly
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Engineer $135.00 4 $540.00
Cummins Cederberg Associate Engineer II $98.07 4 $392.28
Chen Moore and
Associates
Senior Project Manager $154.46 4 $617.84
Chen Moore and
Associates
Associate Engineer $106.38 8 $851.04
Chen Moore and
Associates
Sub-Total $2,449.84
Printing
Total for Subtask 5: $2,449.84
Subtask 6: Construction Administration
Description: Cummins Cederberg will provide the following construction administration services:
6A Pre-Construction:
• Attend up to one (1) pre-construction conference
• Review shop drawing submittals relevant to the Project
6B Construction Observation 1:
• Review and respond to Contractor RFIs relevant to the Project
• Perform one (1) field visit to observe the Contractor’s progress
6C Construction Observation 2:
May 3, 2023 Page 10 of 14
6D Construction Observation 3:
6E Certification and Closeout:
• Attend up to one (1) substantial completion walkthrough to generate punch list
• Review Contractor provided as-built survey
• Attend up to one (1) final walkthrough to confirm punch list items were addressed
• Permit closeout including preparation of statement of substantial conformance with the environmental permits.
Deliverable: Project Certification Letter (PDF)
Subtask 6A
Firm Name Position Classification Hourly
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 1 $144.24
Cummins Cederberg Senior Engineer $135.00 2 $270.00
Cummins Cederberg Associate Engineer II $98.07 2 $196.14
Chen Moore and
Associates
Senior Project Manager $154.46 1 $154.46
Chen Moore and
Associates
Project Engineer $106.38 6 $638.28
Chen Moore and
Associates
Sr. Construction Specialist $120.68 4 $482.72
Sub-Total $1,885.84
Subtask 6B
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Engineer $135.00 2 $270.00
Cummins Cederberg Associate Engineer II $98.07 3 $294.21
Chen Moore and
Associates
Principal $279.39 1 $279.39
Chen Moore and
Associates
Senior Project Manager $154.46 1 $154.46
Chen Moore and
Associates
Project Engineer $106.38 7 $744.66
May 3, 2023 Page 11 of 14
Chen Moore and
Associates
Sr. Construction Specialist $120.68 18 $2,172.24
Sub-Total $3,914.96
Subtask 6C
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Engineer $135.00 1 $135.00
Cummins Cederberg Associate Engineer II $98.07 3 $294.21
Chen Moore and
Associates
Senior Project Manager $154.46 1 $154.46
Chen Moore and
Associates
Project Engineer $106.38 7 $744.66
Chen Moore and
Associates
Sub-Total $3,500.57
Subtask 6D
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Engineer $135.00 1 $135.00
Cummins Cederberg Associate Engineer II $98.07 2 $196.14
Chen Moore and
Associates
Project Engineer $106.38 6 $638.28
Chen Moore and
Associates
Sub-Total $3,141.66
Subtask 6E
Rate
Hours Total Fixed
Price Cost
Cummins Cederberg Senior Project Manager $144.24 1 $144.24
Cummins Cederberg Senior Engineer $135.00 2 $270.00
Cummins Cederberg Associate Engineer II $98.07 2 $196.14
Chen Moore and
Associates
Senior Project Manager $154.46 1 $154.46
Chen Moore and
Associates
Project Engineer $106.38 6 $638.28
Chen Moore and
Associates
Sr. Construction Specialist $120.68 6 $724.08
Sub-Total $2,127.20
May 3, 2023 Page 12 of 14
Printing
Total for Subtask 6: $14,570.23
Project Schedule
Activity Duration (Calendar Days)
Subtask 1A – Topographic
Survey
60 days from authorization to proceed
Subtask 1B – Geotechnical
Investigation
60 days from authorization to proceed
Subtask 1C – Site
Assessment
60 days from authorization to proceed
Subtask 2 – 60%
Engineering Design
60 days from the completion of Subtask 1A, 1B, 1C
Subtask 3 – 100%
Engineering Design
60 days from the completion of Subtask 4 (subject to FDEP providing review comments)
Subtask 4 – Environmental
Permitting
60 days from the completion of Subtask 2
Subtask 5 – Bidding
Assistance
60 days from the completion of Subtask 3 (subject to FDEP solicitation schedule)
Subtask 6A – Pre-
Construction
90 days from the completion of Subtask 5 (subject to FDEP notice to proceed issuance to Contractor)
Subtask 6B – Construction
Observation 1
40 days from the completion of Subtask 6A (subject to
Contractor progress)
Subtask 6C – Construction
Observation 2
80 days from the completion of Subtask 6B (subject to
Contractor progress)
Subtask 6D – Construction
Observation 3
120 days from the completion of Subtask 6C (subject to
Contractor progress)
Subtask 6E – Certification and Closeout
60 days from the completion of Subtask 6D (subject to
Contractor providing required documentation)
Summary of Fees
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A – Topographic
Survey
$21,865.92
Subtask 1B – Geotechnical
Investigation
$7,374.24
May 3, 2023 Page 13 of 14
CUMMINS CEDERBERG, INC. | South Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Subtask 1C – Site
Assessment
$5,221.52
Subtask 2 – 60% Engineering
Design
$25,035.83
Subtask 3 – 100%
Engineering Design
$13,819.83
Subtask 4 – Environmental
Permitting
$5,580.82
Subtask 5 – Bidding
Assistance
$2,449.84
Subtask 6A – Pre-
Construction
$1,885.84
Subtask 6B – Construction
Observation
$3,914.96
Subtask 6C – Construction
Observation
$3,500.57
Subtask 6D – Construction
Observation
$3,141.66
Subtask 6E – Certification and Closeout
$2,127.20
Total Fixed Price Cost: $95,918.23
Total Reimbursable Cost:
Overall Total Cost: $95,918.23
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Conditions/Assumptions
• Client will notify Cummins Cederberg of any known conditions related to the Project that may affect the above-described scope of services.
• Client will provide safe access to the Project site as needed by Cummins Cederberg to complete the above-described scope of services.
• It is assumed there will be no legal encumbrance issues and no historical or archaeological resource issues.
• Client will provide any available background information, such as as-built drawings, historical photographs, or other available documentation.
• The project shall be designed, permitted, and constructed within a single phase.
• If any off-site utilities (potable water, sanitary sewer, stormwater) or off-site roadway improvements are required, they shall be rendered as an additional service.
• No work within A1A will be performed, and therefore permits from the Florida Department of Transportation are not included.
May 3, 2023 Page 14 of 14
• Utility relocation, including, but not limited to water main, sanitary sewer, and stormwater, is not anticipated. Should such utility relocation be required, it may be rendered as an additional service.
• Franchise utilities design, such as power, telecommunications, and natural gas, are not included.
• No known environmental concerns, wetlands, or sensitive species are in the Project area.
• No tree removal permitting will be required.
• Tree replacement design is not included.
• Client shall provide submittal fees for government agencies.
• There is no known contamination within the Project site.
• Work shall comply with all regulating agency requirements.
• Construction staging plans are not included in this scope.
• Contractor to obtain any necessary NPDES NOI permits.
• Contractor to prepare any dewatering plans and obtain dewatering permit(s).
• Client shall require site contractor to prepare final as-builts (prepared by a licensed surveyor) for project certification.
• The scope of topographic survey and geotechnical investigations in based on a conceptual estimate of the length of entry road that could be paved given the project budget provided by FDEP.