CN-370000-CN330-T12CO1.pdf
PDF 420 KB Posted
- Contract number
- CN330
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project involving Cummins Cederberg, Inc., a coastal and marine engineering firm. The change order applies to Task Assignment No. TA 12 under FDEP Contract No. CN330, with the project located at Bahia Honda State Park. The change order was executed on December 6, 2022, and required approval signatures from FDEP budget, project management, and contract authority personnel, as well as the consultant representative.
This change order constitutes a time-only extension with no modification to task costs. The original task end date of December 31, 2022, has been extended by 360 days to December 25, 2023, due to permitting delays that were escalated to the FDEP Section Chief. The total task amount remains $12,052.60, consisting of $100.00 in reimbursement and $11,952.60 in fixed fees. The project involves road improvements at Bahia Honda State Park, and the extension was requested by the consultant to accommodate the extended permitting timeline while maintaining the existing financial commitment with no additional cost to the state.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN330 TA 12 01 61316C
Bahia Honda State Park Road Improvements
Cummins Cederberg, Inc.
Jason Cummins. P.E. 305-741-6155 jcummins@cumminscederberg.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov Description and Justification of Change:
This is a time-only extention; see attached dated 12/06/22.
$ 100.00 $ 11,952.60 $ 12,052.60 $ 100.00 $ 11,952.60 $ 12,052.60 $ 0.00 $ 0.00 $ 0.00
$ 100.00 $ 11,952.60 $ 12,052.60
04/26/22
12/31/22
12/31/22
12/25/23
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2022.12.01 15:07:47 -05'00'
Terry McCullum Jr. Terry McCullum, Jr.
Digitally signed by Terry McCullum, Jr.
Date: 2022.12.01 15:22:33 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.12.05 11:20:54 -05'00'
Jason Cummings, P.E.
Digitally signed by Jason R Cummins Date: 2022-12-02 14:12:38
Michael W. Foster Jr., P.E.
61316C
$ 0.00
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.12.06 16:54:10 -05'00'
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Hello, I have clarified my request with the following language.
I followed up with our permitting processor for this project and although they have elevated the permitting delay issue to the Section Chief, we feel it would be best to get an extension of 360 days to the completion date for this Task Assignment – No. TA12 for the Bahia Honda road improvement project.
Thank you for your assistance.
Kind regards, Anne Laird, M. Sc., Senior Project Manager/ Marine Scientist
CUMMINS │ CEDERBERG
Coastal & Marine Engineering
T: +1 561-658-1297 C: +1 772-486-8530 alaird@CumminsCederberg.com
Please Note: Our offices will be closed from December 24th, 2022 through January 1st, 2023 in observance of the holidays.
mailto:alaird@CumminsCederberg.com
| CN330 TA12 CO1 Bahia Honda - Road Improvements |
| CN330 TA12 CO1 - Bahia Honda - Road Improvements - Backup |
File details come from the government source that posted it. Updated .