This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) under Contract CN330 for the Quayside Island Shoreline Stabilization project located in Biscayne Bay, Miami, Florida. The contract is held by Cummins Cederberg, Inc., with FDEP Contract Manager Ralph Perkins and Consultant Representative Penny Cutt overseeing the work. Change Order No. 05 was issued on January 13, 2025, for Project No. RM2204.

This change order authorizes Subtask 11 – Geotechnical Investigations to be added to the scope of work at a cost of $20,469.02, comprised entirely of fixed fees with no reimbursable costs. The work includes two Standard Penetration Tests (SPTs) to a depth of approximately 35 feet below seawater level using a barge-mounted drill rig, performed by subcontractor ECS Florida, LLC. Engineering fees total $4,938.77 and driller's fees total $15,530.25, covering personnel time, equipment displacement, barge rental, and drilling operations. The investigation is required to secure structural approvals from the Miami-Dade County Building Department per Florida Building Code §1810.1.1 and to obtain necessary permits. The deliverable is a Geotechnical Investigation Report signed and sealed by a Florida Registered Professional Engineer in PDF format. The new task end date is December 30, 2025, and the total contract amount with all change orders is $116,997.20.

View the file

Other files

File Type Posted
CN-370000-CN330-R1.pdf PDF
CN-370000-CN330-T11.pdf PDF
CN-370000-CN330-T12CO1.pdf PDF
CN-370000-CN330-T14.pdf PDF
CN-370000-CN330-T15.pdf PDF
CN-370000-CN330-T15CO1.pdf PDF
CN-370000-CN330-T19.pdf PDF
CN-370000-CN330-T1CO1.pdf PDF
CN-370000-CN330-T20CO2.pdf PDF
CN-370000-CN330-T21.pdf PDF
CN-370000-CN330-T22CO1.pdf PDF
CN-370000-CN330-T23CO1.pdf PDF
CN-370000-CN330-T28.pdf PDF
CN-370000-CN330-T29.pdf PDF
CN-370000-CN330-T30 CO1.pdf PDF
CN-370000-CN330-T30.pdf PDF
CN-370000-CN330-T31.pdf PDF
CN-370000-CN330-T34.pdf PDF
CN-370000-CN330-T4.pdf PDF
CN-370000-CN330-T7.pdf PDF
CN-370000-CN330-T8CO2.pdf PDF
CN-370000-CN330-CMC3.pdf PDF
CN-370000-CN330-CMC5.pdf PDF
CN-370000-CN330-T13.pdf PDF
CN-370000-CN330-T16CO2.pdf PDF
CN-370000-CN330-T20CO1.pdf PDF
CN-370000-CN330-T22.pdf PDF
CN-370000-CN330-T22CO2.pdf PDF
CN-370000-CN330-T3.pdf PDF
CN-370000-CN330-T33.pdf PDF
CN-370000-CN330-T8.pdf PDF
CN-370000-CN330-T8CO1.pdf PDF
CN-370000-CN330-T8CO6.pdf PDF
PC-370000-CN330.pdf PDF
CN-370000-CN330-CMC1.pdf PDF
CN-370000-CN330-CMC2.pdf PDF
CN-370000-CN330-CMC4.pdf PDF
CN-370000-CN330-T1.pdf PDF
CN-370000-CN330-T12.pdf PDF
CN-370000-CN330-T16CO1.pdf PDF
CN-370000-CN330-T19CO1.pdf PDF
CN-370000-CN330-T2.pdf PDF
CN-370000-CN330-T21CO1.pdf PDF
CN-370000-CN330-T23.pdf PDF
CN-370000-CN330-T25CO1.pdf PDF
CN-370000-CN330-T26.pdf PDF
CN-370000-CN330-T8CO4.pdf PDF
CN-370000-CN330-T10.pdf PDF
CN-370000-CN330-T16.pdf PDF
CN-370000-CN330-T17.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bryan Bradner Digitally signed by Bryan Bradner Date: 2025.02.05 14:35:24 -05'00'

CCUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee

89370-CO5

Quayside Island Shoreline Stabilization Biscayne Bay, Miami, Florida Contract: CN330 TA8-CO5

Subtask 11 – Geotechnical Investigations Description:

Subtask 11A – Geotechnical Investigations: Structural and zoning approvals are required to secure the DERM Class I permit, to complete Subtasks 4C and 7C of the Scope of Work.

To secure structural approvals from the Miami-Dade County Building Department, geotechnical investigations are required per Florida Building Code §1810.1.1. As the Miami- Dade County Building Department will not accept a test piling, supplemental budget and scope are required to perform a geotechnical investigation.

Two (2) Standard Penetration Tests (SPTs) to a depth of approximately 35 feet will be performed below sea water level, from a barge-mounted drill rig. Water depths will be confirmed by probing. Sunshine One Call will be contacted for advice regarding the location of underground utilities prior to commencement of field work. Cummins Cederberg or its subconsultants cannot be held responsible for damage to below ground structures or utilities which are not identified to us. We specifically request any available information about the location of underground utilities for this Project.

If the subsurface conditions encountered in the field are different from the typical conditions previously observed near the area, the geotechnical engineer will contact the Cummins Cederberg design engineer to discuss. Given the presence of existing timber piles in the area, the geotechnical engineer does not anticipate any changes in the subsurface conditions. All efforts will be made to collect required geotechnical data with one mobilization and two SPTs as scoped herein.

Deliverables:

Subtask 11A: Geotechnical Investigation Report, Signed/Sealed by a Florida Registered Professional Engineer, in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Quayside Island 89370-CO5 December 3, 2024 Page 2 of 3

CCUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee

Fixed Price Cost:

Subtask 11: Geotechnical Investigations ECS Engineering Fees & Cummins Cederberg Review Fees

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Cummins Cederberg Senior Engineer $ 135.00 2 $ 270.00

Cummins Cederberg Project Manager $ 99.51 2 $ 199.02

ECS Florida, LLC Principal-In-Charge /Program Manager

$ 210.00 2 $ 420.00

ECS Florida, LLC Project Manager $ 174.73 4 $ 698.92 ECS Florida, LLC Administrative Assistant $ 65.50 4 $ 262.00

ECS Florida, LLC Geotechnical Engineer - Senior

$ 167.50 10 $ 1,675.00

ECS Florida, LLC Geotechnical Engineer - Mid

$ 128.53 11 $ 1,413.83

Sub-Total $ 4,938.77 Driller’s Fees

Firm Name Discipline Rate Quantity/Unit Total Fixed Price Cost

ECS Florida, LLC Equipment Displacement (Small Barge)

$ 5,175.00 1/each $ 5,175.00

ECS Florida, LLC Mob & Demob Barge (Crane)

$ 2,530.00 1/each $ 2,530.00

ECS Florida, LLC Daily Rental Small Barge $ 2,875.00 2/day $ 5,750.00

ECS Florida, LLC Equipment Displacement (Small Rig)

$ 517.00 1/each $ 517.00

ECS Florida, LLC Drill & Wash Casing 0’ – 50’

$ 23.00 10/ft $ 230.00

ECS Florida, LLC Drill & Wash Casing 0’ – 50’

$ 26.45 35/ft $ 925.75

ECS Florida, LLC Set-Up per Boring $ 402.50 1/boring $ 402.50 Sub-Total $ 15,530.25

Reimbursable Cost:

Postage (est.)

Printing Overnight Travel (if applicable)

Mileage (@ $0.445 per mile) Reimbursable Total Cost

Quayside Island 89370-CO5 December 3, 2024 Page 3 of 3

CCUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee

Total for Subtask 11: $20,469.02

SSummary of Fees

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

6A: Additional Engineering Design – 60% Documents – Fixed Pier and Floating Dock

$ 6,602.64

7A: Additional Support for USACE Permit Application and Processing

$ 3,332.40

7B: Additional Support for SFWMD Permit Application and Processing

$ 2,035.44

7C: Additional Support for Miami-Dade County Permit Application & Processing

$ 4,107.84 $ 5,993.77

8A: Additional Engineering Design – 100% Documents – Fixed Pier and Floating Dock

$ 8,668.08

9: Bidding Assistance $ 3,304.56 10A: Construction Support Services – Submittals

$ 3,304.56

10B: Construction Support Services – RFIs $ 2,674.56 10C: Construction Support Services – Site Visit and Project Closeout

$ 9,200.52

11A: Geotechnical Investigations $ 20,469.02 Total Fixed Price Cost: $ 63,699.62

Total Reimbursable Cost: $ 5,993.77 Overall Total Cost: $ 69,693.39

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

CONDITIONS/ASSUMPTIONS

Client shall notify Cummins Cederberg of any known conditions related to the Project that may affect the above-described scope of services.

Client or selected Marine Contractor to secure local Building Department Permit as required prior to commencement of construction.