This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project at John Pennekamp State Park. The change order involves FDEP as the contracting agency and Cummins Cederberg as the consultant. Ralph Perkins serves as the FDEP Contract Manager, while Rasheed K. Muslimani represents Cummins Cederberg as the consultant representative.
The change order extends the task end date for the Dive Shop Dock Replacement project from August 11, 2022, to September 29, 2022, representing a 49-day extension at no cost to the project. The original task amount of $52,954.00 (consisting of $200.00 in reimbursement and $52,754.00 in fixed fees) remains unchanged, with the total task amount including all previous change orders remaining at $83,015.44. The task is funded through FDEP's budget using the 29-digit FLAIR code CN330 03 02 61315C. All required signatures were executed digitally between July 19 and July 27, 2022, with approval from the Budget Representative, Project Manager, Contract Manager, Consultant, and Contract Authority.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN330 03 02 61315C
John Pennekamp State Park Dive Shop Dock Replacement
Cummins Cederberg
Rasheed K. Muslimani 305-741-6155 rmuslimani@CumminsCederberg.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Extend Task End Date. No cost change order. Please see attached request dated 07/15/2022
$ 200.00 $ 52,754.00 $ 52,954.00 $ 200.00 $ 82,815.44 $ 83,015.44 $ 0.00 $ 0.00 $ 0.00
$ 200.00 $ 82,815.44 $ 83,015.44
Upon execution
06/31/2022
8/11/2022
9/29/2022
Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.07.19 15:53:14 -04'00'
Jim Post James Post Digitally signed by James Post Date: 2022.07.25 08:44:13 -04'00'
Ralph M Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.07.25 08:53:02 -04'00'
Jason Cummins
Digitally signed by Jason R Cummins Date: 2022-07-26 10:40:59
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.07.27 08:53:25 -04'00'
$ 0.00
Frawley, Rose
From: Rasheed Muslimani <rmuslimani@cumminscederberg.com> Sent: Friday, July 15, 2022 10:08 AM To: Post, James; Frawley, Rose Cc: Katie Britt Williams; Anne Laird Subject: FDEP Pennekamp - Dive Dock Project - Time Extension Request
Follow Up Flag: Follow up Flag Status: Flagged
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Good Morning Jim and Rose, As discussed earlier this week, we are kindly requesting a time extension for the dive dock Task Order, changing the deadline from 8/11/2022 to 9/29/2022.
Please review and let us know if this can be accommodated.
Let me know if we need to fill out any forms or if you need anything else.
Rasheed K. Muslimani, P.E., PMP, Senior Project Manager
CUMMINS │ CEDERBERG
Coastal & Marine Engineering
Miami │ Fort Lauderdale │ Jupiter │ St. Petersburg | Tallahassee 201 Alhambra Circle, Suite 601, Coral Gables, FL 33134 T: +1 305-741-6155 C: +1 239-293-3376 rmuslimani@CumminsCederberg.com
Please Note: Our Miami office has moved to 201 Alhambra Circle, Suite 601, Coral Gables, FL 33134
| CO #2 - Form.pdf |
| Email for extention.pdf |
File details come from the government source that posted it. Updated .