This document is a Task Assignment Notification Form and supporting proposal from the Florida Department of Environmental Protection (FDEP) for engineering and environmental consulting services at Bahia Honda State Park in Big Pine Key, Monroe County, Florida. The consultant assigned to this task is Cummins Cederberg, Inc., a coastal and marine engineering firm based in South Miami, Florida. The contract is identified as CN330, Task Assignment No. 01, with Project No. 61316C. The FDEP Contract Manager is Alyssa Skehan, and the project involves road improvements to the staff housing access road at the state park.
The scope of work encompasses five primary subtasks: (1) Field Investigations including wetland delineation, asbestos and lead-based paint surveys, and topographic survey ($7,578.20); (2) Engineering at 60% completion level ($5,487.60); (3) Environmental Permitting for FDEP SWERP exemption and State 404 Program verification ($8,320.00 including $100.00 reimbursable); (4) 100% Design Documents including structural calculations and construction drawings ($8,107.60 including $100.00 reimbursable); and (5) Construction Support Services for submittals, RFIs, and site visits ($8,330.40). The total fixed price cost is $37,623.80 with an additional $200.00 in reimbursable costs for a total task amount of $37,823.80. The project start date is upon execution with a completion date of December 31, 2021. Payment will be made upon FDEP approval of deliverables for each subtask. The proposal includes detailed hour budgets by personnel classification and assumes no wetland impacts requiring mitigation, FDEP waiver of standard permit criteria, and successful exemption qualification for the roadway improvements project.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN330 01 FDEP 61316C
Bahia Honda State Park Road Improvements
Cummins Cederberg
Jason Cummins 305-741-6155 jcummins@cumminscederberg.com
Alyssa Skehan or successor 850-245-2781 Alyssa.Skehan@FloridaDEP.gov
Consultant shall provide topographic survey, asbestos & lead based paint survey, design, permitting, and construction administration services for the Road Improvements project at Bahia Honda State Park. See attached revised proposal dated March 5, 2021.
C Hewitt or successor
Upon execution $ 37,623.80 12/31/2021 $ 200.00
$ 37,823.80
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.03.09 09:11:59 -05'00'
C Hewitt C Hewitt Digitally signed by C Hewitt Date: 2021.03.09 09:12:55 -05'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.03.09 09:27:33 -05'00'
Jason Cummins
Digitally signed by Jason R Cummins Date: 2021-03-09 10:39:53
Michael W. Foster Jr. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2021.03.22 14:05:57 -04'00'
61316C 37505000005 080039/21 423001 U3200 131500 QK $ 37,823.80
$ 37,823.80
Cummins | Cederberg 7550 Red Road, Suite 217 ▪ South Miami, Florida 33143
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
CUMMINS | CEDERBERG
Coastal & Marine Engineering
March 5, 2021 89300-R5
Mr. C. Hewitt Project Manager
BUREAU OF DESIGN AND CONSTRUCTION
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
3900 Commonwealth Boulevard, MS 520 Tallahassee, Florida 32399
RE: CONTRACT NUMBER: CN330
PROPOSAL FOR MARINE ENGINEERING AND ENVIRONMENTAL CONSULTING SERVICES
AT THE BAHIA HONDA STATE PARK IN BIG PINE KEY, MONROE COUNTY, FLORIDA
Dear Mr. Hewitt;
Cummins Cederberg, Inc. (Cummins Cederberg) is pleased to present this proposal for engineering and environmental consulting services with respect to resilient road improvements at Bahia Honda
State Park located at 36850 Overseas Highway, Big Pine Key, Florida. It is our understanding
Bahia Honda State Park is interested in improving the existing 0.2-mile road to employee housing on the Gulf side of Big Pine Key by raising the elevation of the unpaved road to mitigate the impacts of sea level rise and reduce the frequency of flooding events. The road will remain unpaved and fill material may consist of crushed limerock compacted to FDOT specifications.
Impacts to wetlands are not anticipated, as the additional fill for the unpaved road improvements will be retained by a retaining element as applicable along the length of the road.
For your review, Cummins Cederberg, Inc. (Cummins Cederberg) has prepared the attached proposal summary and man-hour documentation for the service tasks identified below:
Subtask 1 – Field Investigations
Subtask 2 – Engineering – 60% Documents
Subtask 3 – Environmental Permitting – Roadway Improvements
Subtask 4 – Engineering – 100% Documents
Subtask 5 – Construction Support Services
We appreciate the opportunity to prepare a proposal for engineering and environmental consulting services and look forward to working together. Please review the attached Proposal Summary and deliverables; we will commence work upon receipt of Authorization to Proceed.
DEP Bahia Honda State Park 89300-R5 March 5, 2021
South Miami ▪ Fort Lauderdale ▪ Jupiter ▪ Tallahassee Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Sincerely, CUMMINS CEDERBERG, INC.
Jason Cummins, P.E.
Principal
Florida Professional Engineering No. 71538 Florida Certificate of Authorization No. 29062
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Bahia Honda State Park Staff Housing Access Road Improvement Project
Bahia Honda State Park, 36850 Overseas Highway, Big Pine Key, Florida 33043
Contract: CN330 Task: 1
SUBTASK 1 – FIELD INVESTIGATIONS
Description:
Subtask 1A: Wetland Delineation: A Cummins Cederberg biologist will perform a wetland delineation to identify the limits of wetlands on both sides of the road. The limits of wetlands will be surveyed in with a handheld GPS. This information will be utilized to ensure that impacts to wetlands are avoided and minimized to the maximum extent practicable in the design process and to support environmental permitting for the Project.
Subtask 1B: Asbestos and Lead-Based Paint Inspection: A sub-consultant from
Southern Earth Sciences (SESI) will perform Asbestos NESHAPS Renovation Surveys (40
CFR Part 61) of the identified roadway. SESI will perform bulk sampling of accessible suspect materials following the AHERA Sample Protocol and send the samples to a
NVLAP Laboratory for bulk PLM Analysis. SESI will sample painted surfaces associated with the infrastructure, as applicable, using a Heuresis Pb200i Lead Analyzer (XRF) for lead based paint.
Subtask 1C: Limited Boundary and Topographic Survey: A limited boundary survey will be completed for the proposed roadway area to serve as the basis for subsequent design and regulatory permitting. The location and elevation of the roadway will be surveyed along with other general features of the site pertinent to the Project. This survey is not intended as a full boundary survey but only specifically for the roadway improvement
Project. In addition, elevations along the perimeter and throughout the roadway will be collected. The survey data collected in the field will be reduced to the horizontal coordinate system and vertical datum established for the Project.
Deliverable:
Subtask 1A: Basemap depicting wetland limits superimposed on available recent aerial imagery in PDF.
Subtask 1B: One (1) report with the identified ACM present, approximate quantities, locations, and appropriate actions in PDF format.
Subtask 1C: One (1) property survey, signed/sealed by a Florida Registered Professional Surveyor, along with PDF and DWG files.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A: Wetland Delineation Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 1 $ 194.40 Cummins Cederberg Senior Scientist $135.00 8 $1,080.00 Cummins Cederberg Staff Scientist/Engineer $60.00 24 $1,440.00
Sub-total $2,714.40
Subtask 1B: Asbestos and Lead-Based Paint Inspection Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 1 $ 194.40 Cummins Cederberg Project Engineer $90.00 2 $ 180.00 Southern Earth Sciences Project Engineer $115.00 9 $1,035.00 Southern Earth Sciences PLM Analysis $25.00 8 $ 200.00
Sub-Total $1,609.40
Subtask 1C: Survey
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 1 $ 194.40 Cummins Cederberg Project Engineer $90.00 2 $ 180.00 Florida Keys Land Surveying
Field Crew $210.00 8 $1,680.00
Florida Keys Land Surveying
AutoCAD Drafting $150.00 4 $ 600.00
Florida Keys Land Surveying
Professional Surveyor and Mapper
$200.00 3 $ 600.00
Sub-Total $3,254.40
Reimbursable Cost:
Postage (est.)
Printing Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) Reimbursable Total Cost
Total for Subtask 1: $7,578.20
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
SUBTASK 2 – ENGINEERING – 60% DOCUMENTS
Description:
Cummins Cederberg will layout and design an increase in elevation for the existing roadway based on survey data collected under Subtask 1C. The elevation increase may require vertical and/or sloping bank stabilization to retain the increased fill. The elevation increase will be optimized based on multiple variables, such as minimization of wetland impacts, cost of retainment required, and water levels.
Cummins Cederberg will prepare preliminary drawings, at approximately 60% completion level, inclusive of specifications, in sufficient detail for submittal to the regulatory agencies as
‘permit sketches’. The existing conditions and wetland delineation from Subtask 1C will be included. The plans will be prepared in CAD format.
Deliverable: 60% construction documents (11x17 or 22x34) in PDF format and construction cost estimate.
Fixed Price Cost:
Subtask 2: Engineering – 60% Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 4 $ 777.60 Cummins Cederberg Senior Engineer $135.00 6 $ 810.00 Cummins Cederberg Project Engineer $90.00 24 $2,160.00 Cummins Cederberg Staff Engineer $60.00 28 $1,680.00 Cummins Cederberg Secretary $60.00 1 $ 60.00
Sub-Total $5,487.60
Postage Printing
Total for Subtask 2: $5,487.60
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
SUBTASK 3 – ENVIRONMENTAL PERMITTING – ROADWAY IMPROVEMENTS
Description:
Subtask 3A: FDEP SWERP Application and Processing: Cummins Cederberg will prepare and process a Statewide Environmental Resource Permit (SWERP) Exemption Application through the Florida Department of Environmental Protection (FDEP), requesting an exemption for the proposed roadway improvements Project, pursuant to Chapter 62-330, F.A.C. Cummins
Cederberg will maintain contact with FDEP to review plans and provide additional information. The Client will provide Cummins Cederberg with a signed exemption verification request and a processing fee of $100.00.
Subtask 3B: State 404 Program Application and Processing: Cummins Cederberg will prepare and process a Notice of Intent to use a General Permit, pursuant to §62-330.402(1)
FAC and Section 4.3 of the 404 Handbook requesting Verification of the proposed roadway improvements Project pursuant to §62-331-016 General Permit for Bank Stabilization. The submittal will request the FDEP waive the 500 linear foot criterion, as the activity will result in no more than minimal adverse environmental effect to aquatic functions and values.
Cummins Cederberg will maintain contact with the FDEP staff to review plans and provide additional information. The Client will provide Cummins Cederberg with a signed application form.
Subtask 3A: FDEP SWERP Exemption Application form and FDEP Exemption in PDF.
Subtask 3B: Notice of Intent and General Permit for Bank Stabilization verification in
PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3A: FDEP SWERP Application and Processing Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Senior Scientist $135.00 14 $1,890.00 Cummins Cederberg Project Scientist $90.00 18 $1,620.00 Cummins Cederberg Secretary $60.00 4 $ 240.00
Sub-Total $3,750.00
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Subtask 3B: State 404 Program Notice of Intent Application and Processing Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Senior Scientist $135.00 14 $1,890.00 Cummins Cederberg Project Scientist $90.00 26 $2,340.00 Cummins Cederberg Secretary $60.00 4 $ 240.00
Sub-Total $4,470.00
Permit Application Fee $100.00 Postage Printing
Reimbursable Total Cost $100.00
Total for Subtask 3: $8,320.00
SUBTASK 4 – 100% DOCUMENTS
Subtask 4A: Design: Cummins Cederberg will finalize the layout and design for an increase in elevation for the existing access roadway. Specifications of FDOT sub-base fill and roadway standards will be implemented into the design of the roadway improvements and increased roadway elevation. Typical sections will be developed illustrating the design layout, retained elevations where applicable, and proposed materials. Specifications and details for material characteristics will be developed for various components as part of the design process, as applicable. Engineering calculations will be prepared as appropriate for the design.
Subtask 4B: Drawings: Cummins Cederberg will finalize drawings, inclusive of specifications, in sufficient detail for construction. Any revisions stemming from the environmental permitting process under Subtask 3. Cummins Cederberg will provide structural calculations for the design and subsequent building permit processing as appropriate. The drawings will be signed and sealed by a Florida registered Professional Engineer. The following drawing sheets are anticipated:
Cover Sheet – Location maps, titles
General Notes – Specifications, materials, list of abbreviations
Site Plan – Existing conditions, wetland limits, survey
Proposed Plan – Roadway layout, wetland limits, bank stabilization layout
Structural Sections – Cross sections, details
Subtask 4C: Bidding Assistance: Cummins Cederberg will provide support services as part of the bid solicitation process for the proposed works. The scope may include general review and response to Contractors’ questions, as requested by the Client. Attendance at one pre-bid meeting is included under this task. Additional meetings and construction support services following award will be performed under Subtask 5.
Subtask 4A: Four (4) sets of signed/sealed structural calculations, as applicable, and PDF file.
Subtask 4B: Four (4) sets of signed/sealed 100% construction plans (11x17 or 22x34), along with PDF and DWG files.
Subtask 4C: Responses to questions during bid process in PDF format. Attendance at pre-bid meeting.
Fixed Price Cost:
Subtask 4A: Design Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 2 $ 388.80 Cummins Cederberg Senior Engineer $135.00 4 $ 540.00 Cummins Cederberg Project Engineer $90.00 12 $1,080.00
Sub-Total $2,008.80
Subtask 4B: Construction Drawings
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 2 $ 388.80 Cummins Cederberg Senior Engineer $135.00 4 $ 540.00 Cummins Cederberg Project Engineer $90.00 12 $1,080.00 Cummins Cederberg Staff Engineer $60.00 32 $1,920.00 Cummins Cederberg Secretary $60.00 1 $ 60.00
Sub-Total $3,988.80
Subtask 4C: Bidding Assistance
Rate Hours Total Fixed
Price Cost Cummins Cederberg Senior Engineer $135.00 6 $ 810.00 Cummins Cederberg Project Engineer $90.00 12 $1,080.00 Cummins Cederberg Secretary $60.00 2 $ 120.00
Sub-Total $2,010.00
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Reimbursable Cost:
Postage $100.00 Printing
Reimbursable Total Cost $100.00
Total for Subtask 4: $8,107.60
SUBTASK 5 – CONSTRUCTION SUPPORT SERVICES
Subtask 5A: Submittals: Cummins Cederberg will provide construction support services for the Project as requested by the Client. The scope and associated budget is estimated to include six (6) review and responses to Submittals.
Subtask 5B: RFIs: Cummins Cederberg will provide construction support services for the Project as requested by the Client. The scope and associated budget is estimated to include five
(5) responses to Requests for Information (RFI’s).
Subtask 5C: Site Visits: Cummins Cederberg will provide construction support services for the Project as requested by the Client. The scope and associated budget is estimated to include two (2) Progress site visits, and (1) Final Inspection. Materials testing (if required) to be provided by the Contractor. This task includes up to three (3) site visits total.
Subtask 5A: Responses to Submittals in PDF format.
Subtask 5B: Responses to RFIs in PDF format.
Subtask 5C: Site inspection reports in PDF format.
Fixed Price Cost:
Subtask 5A: Submittals Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 2 $ 388.80 Cummins Cederberg Senior Engineer $135.00 4 $ 540.00 Cummins Cederberg Project Engineer $90.00 16 $1,440.00
Sub-Total $2,368.80
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Subtask 5B: RFIs Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 2 $ 388.80 Cummins Cederberg Senior Engineer $135.00 4 $ 540.00 Cummins Cederberg Project Engineer $90.00 14 $1,260.00
Sub-Total $2,188.80
Subtask 5C: Site Visits
Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal Engineer $194.40 12 $2,332.80 Cummins Cederberg Project Engineer $90.00 16 $1,440.00
Sub-Total $3,772.80
Postage Printing
Total for Subtask 5: $8,330.40
Project Schedule:
Activity Duration (Calendar Days)
1A: Wetland Delineation 14 Days
1B: Asbestos and Lead-Based Paint Inspection 14 Days
1C: Limited Boundary and Topographic Survey 21 Days
2: Engineering – 60% Documents 45 Days
3A: FDEP SWERP Applications & Processing 120 Days 3B: State 404 Program Application & Processing 180 Days
4A: 100% Design 45 Days
4B: 100% Drawings Concurrent with 4A
4C: Bid Assistance TBD
5A: Submittals TBD
5B: RFIs TBD
5C: Site Visits TBD
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable 1A: Wetland Delineation $2,714.40 1B: Asbestos and Lead-Based Paint Inspection
$1,609.40
1C: Limited Boundary and Topographic Survey
$3,254.40
2: Engineering – 60% Documents
$5,487.60
3A: FDEP SWERP Application & Processing
$3,750.00 $100.00
3B: State 404 Program Application & Processing
$4,470.00
4A: 100% Design $2,008.80 4B: 100% Drawings $3,988.80 $100.00 4C: Bid Assistance $2,010.00 5A: Submittals $2,368.80 5B: RFIs $2,188.80 5C: Site Visits $3,772.80
Total Fixed Price Cost: $37,623.80 Total Reimbursable Cost: $200.00
Overall Total Cost: $37,823.80
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
CONDITIONS/ASSUMPTIONS
Client shall notify Cummins Cederberg of any known conditions related to the Project that may affect the above-described scope of services.
Client shall provide safe access to the Project site as needed by Cummins Cederberg to complete the above-described scope of services.
Impacts to wetlands are not proposed and mitigation will not be required.
This scope assumes the FDEP will waive the criterion limiting 62-331.216 to activities no more than 500 feet in length along a bank and determine the discharge will result in no more than minimal adverse environmental effects. If the FDEP determines the scope of work does not qualify for the 62-331-216 General Permit Verification, an addendum scope will be provided for Client approval.
This scope assumes historical wetland impacts will not need to be addressed as part of the permitting process, the work will qualify for an FDEP exemption, and the work will qualify for a Letter of Consent for use of State owned Sovereign Submerged Lands. If the FDEP determines the work does not qualify for an exemption and/or requires proprietary authorization beyond a Letter of Consent, an addendum scope will be provided for Client approval.
Phone: +1 305 741 6155 ▪ Fax: +1 305 974 1969 info@CumminsCederberg.com ▪ www.CumminsCederberg.com
Fill required for project construction will not exceed one cubic yard per linear foot below
Mean/Ordinary High Water.
The road elevation and bulkhead will be designed to ensure no material will be eroded by normal or expected high water flows and will not impair surface water flow into or out of waters or wetlands.
This presumes there is no stormwater engineering required for the proposed improvements.
Construction drawings to be inclusive of specifications. If a separate specifications package is required, Cummins Cederberg can provide under an addendum scope of services.
Legal, agency, and permit fees not included.
Client or selected Marine Contractor to secure local Building Department Permit.
There will be no legal encumbrance issues, substantial objections from neighbors, no submerged land lease issues, and no historic or archaeological resource issues.
Budget for Subtask 1B is based on concurrent authorization and shared travel costs with similar scope item for proposed dock reconstruction at John Pennekamp Coral Reef State
Park under a separate task assignment.
File details come from the government source that posted it. Updated .