This document is a Task Assignment Notification Form and associated proposal from the Florida Department of Environmental Protection (FDEP) to Cummins Cederberg, Inc., a coastal and marine engineering consulting firm. The contract is designated CN330, Task Assignment No. 20, with Project No. 61472C. The project location is Bill Baggs Cape Florida State Park in Key Biscayne, Miami-Dade County, Florida. The FDEP Contract Manager is Ralph Perkins, and the Project Manager is Jim McGuire. Cummins Cederberg's Consultant Representative is Jannek Cederberg, P.E.
The scope of work consists of three primary subtasks: (1) a topographic and limited hydrographic survey of approximately 5,550 linear feet of shoreline, eight fishing piers, and associated structures; (2) a marine engineering inspection with an engineering report documenting structural condition and repair recommendations; and (3) a marine resource survey to identify seagrasses, corals, and other sensitive resources. The total fixed price cost is $66,847.10, with no reimbursable costs, distributed across subtasks as follows: Subtask 1 ($36,452.72), Subtask 2 ($15,146.88), and Subtask 3 ($15,247.50). The work is scheduled to commence upon execution, with completion targeted for January 30, 2024. All deliverables include professional reports signed and sealed by Florida Registered Professional Engineers or Surveyors, as applicable.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.01.31 11:23:33 -05’00’
CCUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
January 17, 2023 132000-R1
Florida Department of Environmental Protection Bureau of Design and Construction Attn: Mr. Jim McGuire 3800 Commonwealth Blvd. MS 520 Tallahassee, Florida 32399
Sent via email: Jim.McGuire@FloridaDEP.gov
RE: Contract CN330, Task Assignment:
Proposals for Bulkhead and Shoreline Assessment at Bill Baggs Cape Florida State Park, Key Biscayne, Florida
Dear Mr. McGuire:
Cummins Cederberg, Inc. (Cummins Cederberg) is pleased to present this proposal for our marine engineering and environmental consulting services for the proposed Marine Engineering and Environmental Consulting Services at Bill Baggs Cape Florida State Park, located at 1200 Crandon Blvd. Key Biscayne, Miami-Dade County, Florida (Project). The proposed project consists of a topographic survey and marine engineering inspection of ~5,500 ft. of shoreline, eight (8) fishing piers, and associated structures. A marine resource survey along the same stretch of shoreline will be completed to document sensitive flora and fauna, such as corals and seagrass, within the general Project footprint.
For your review, Cummins Cederberg, Inc. (Cummins Cederberg) has provided the attached proposal summary and man-hour documentation for the service tasks identified below:
Subtask 1 – Topographic Survey Subtask 2 – Marine Engineering Inspection o Subtask 2A – Inspection o Subtask 2B – Engineering Report
Subtask 3 – Marine Resource Survey
We appreciate the opportunity to prepare a proposal for engineering and environmental consulting services and look forward to working together. Please review the attached Proposal Summary and deliverables; we will commence work upon receipt of Authorization to Proceed.
FDEP Bill Baggs Cape Florida State Park 132000-R1 January 17, 2023 Page 22 of 77
CUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Sincerely, CUMMINS CEDERBERG, INC.
Anne Shoffner (Laird) Sr. Project Manager/Marine Scientist
January 17, 2023 Page 33 of 77
CUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Bill Baggs Cape Florida Bulkhead and Shoreline Assessment 1200 Crandon Blvd., Key Biscayne, FL 33419
Contract: CN330 Task:
Subtask 1 - Topographic and Limited Hydrographic Survey Description:
Cummins Cederberg’s subconsultant will conduct a limited boundary, topographic, and hydrographic survey of the shoreline, approximately 5,550 LF from the lighthouse to north end of the western shoreline, and eight (8) fishing piers and upland up to 30 ft. The topographic survey will be completed for the Project site to serve as the basis for subsequent design and regulatory permitting. Specifically, the location and elevations of the seawall, rock revetment, and fishing piers (and associated elements) will be identified along with other general features of the site, both hardscape and landscape, pertinent to the Project. In addition, a limited hydrographic survey will be conducted of immediate water depths to collect every 10 ft. off the end of each fishing pier and every 20 ft. along the shoreline. A boundary survey will be prepared as required to secure permitting. Data will be geo-rectified in the State Plane Coordinate System; and elevation data collected in the field will be referenced in North American Vertical Datum of 1988 (NAVD88).
Deliverables:
Subtask 1 - Survey, Signed/Sealed by a Florida Registered Professional Surveyor and Mapper (CAD/PDF)
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 - Topographic and Limited Boundary Survey
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Cummins Cederberg Principal $ 194.40 2 $ 388.80 Cummins Cederberg Senior Project Manager $ 144.24 8 $ 1,153.92 Cummins Cederberg Senior Engineer $ 135.00 16 $ 2,160.00 Cummins Cederberg Secretary $ 60.00 4 $ 240.00 ECS Land Surveyors, Inc. Professional Land
Surveyor $ 150.00 14 $ 2,100.00
ECS Land Surveyors, Inc. Survey CAD Technician $ 65.00 100 $ 6,500.00 ECS Land Surveyors, Inc. Survey Crew $ 130.00 182 $23,660.00
ECS Land Surveyors, Inc. Administrative $ 50.00 5 $ 250.00
Sub-Total $36,452.72
January 17, 2023 Page 44 of 77
CUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Reimbursable Cost:
Postage Printing Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) Reimbursable Total Cost $
Total for Subtask 1: $36,452.72
Subtask 2 – Marine Engineering Inspection Description:
2A Inspection: A team of engineer-divers, including a licensed Professional Engineer, will perform an above- and below-water inspection of the entire ~5,550 feet of seawall from the lighthouse to north end of the western shoreline and eight (8) fishing piers. The inspection will include visual assessment of the structural components (e.g., cap, panels, piles, rock slope, beams) to identify forms of deterioration (e.g. cracking, spalling, displacement, undermining, etc.)
and methods for repair or replacement, as needed. Field notes will be collected to document observed damage or deterioration, which will be referenced to stationing established along the shoreline. Above- and below-water photographs will also be obtained to document the assessment and will be included in the engineering report. The inspection will be conducted generally following methods provided in Standard Practice Manual for Underwater Investigations, ASCE Manual No. 101.
As a supportive effort to the marine engineering field inspection, Cummins Cederberg will conduct a desktop review relative to existing marine structures and shoreline protection systems within the inspection footprint. This review will include available design plans, structural inspection reports, or other engineering related documents. Documents will be pulled from publicly available databases. Findings from this desktop review could potentially supplement recommendations, if any, for repairs of existing structures.
2B Engineering Report: A report will be prepared to summarize the engineering observations and results of the inspection. The report will include an assessment of the existing marine structures and recommendations for repairs or replacement. In particular, the report will describe findings for each of the eight (8) fishing piers and provide recommendations on which, if any, fishing piers can be immediately reopened. If applicable, recommendations for minor repairs to expedite reopening select fishing piers will be provided. Based on Client communication, fishing piers #8, #7, and #5 were earmarked as the most popular fishing piers to reopen based on usage;
these piers, along with the all the piers, will be given recommendations on a course of action for reopening. Findings from the desktop review will be included as an appendix to this report and referenced along field findings as applicable. Color copies of photographs to reference
January 17, 2023 Page 55 of 77
CUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee observations will be included. The report will be signed and sealed by a Florida Registered Professional Engineer.
Deliverables:
Report Signed/Sealed by a Florida Registered Professional Engineer in PDF
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2 – Marine Engineering Inspection
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Cummins Cederberg Principal $ 194.40 3 $ 583.20 Cummins Cederberg Senior Project Manager $ 144.24 6 $ 865.44 Cummins Cederberg Senior Engineer $ 135.00 40 $ 5,400.00 Cummins Cederberg Associate Engineer II $ 98.07 64 $ 6,276.48 Cummins Cederberg Senior Designer $ 103.86 16 $ 1,661.76 Cummins Cederberg Secretary $ 60.00 6 $ 360.00
Sub-Total $15,146.88
Reimbursable Cost:
Postage Printing Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost $
Total for Subtask 2: $15,146.88
Subtask 3 – Marine Resource Survey Description:
3A Survey: As part of the initial design phase, Cummins Cederberg will conduct a marine resource survey to identify potential seagrasses, corals, and other marine resources relative to avoidance and minimization of potential impacts that may occur as a result of the seawall or fishing pier reconfiguration within the proposed Project boundaries. Note, however, the federally (USACE) recognized seagrass growing season is from June 1 – September 30, and if this initial survey is performed before June 1 for the purposes of design planning, an additional “in-season” seagrass survey will likely be required during the permitting process. A second survey is not included in this scope.
January 17, 2023 Page 66 of 77
CUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Due to the large area of shoreline, a reconnaissance survey will be performed along the entire ~5,550 ft. with extensive areas of seagrass mapped directly, out to 50 ft. perpendicular (waterward) to and paralleling the shoreline. In areas extending >50 ft. parallel to the shoreline, perpendicular transects will be established every 30 ft. to document the extent of the resource within certain segments of the Project area to adequately characterize the area for the purpose of avoidance and impact minimization. Data (e.g., species, percent coverage, and location of marine resources observed) will be collected via SCUBA (or snorkel, depending on depth) on prepared underwater paper and representative photographs will be taken. Coordinates will be collected at specific locations throughout the survey to document edges of habitats, or individual coral colonies observed.
3B Report: The data will be processed and illustrated on a basemap. The basemap will include location and coverage of documented marine resources. A brief observation report, including representative photographs, will be prepared summarizing the investigations.
Deliverables: Environmental Survey Report in PDF-format
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Subtask 3 – Marine Resource Survey
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Cummins Cederberg Project Director $ 187.50 1 $ 187.50 Cummins Cederberg Senior Project Manager $ 144.24 12 $1,730.88 Cummins Cederberg Senior Scientist $ 135.00 40 $ 5,400.00 Cummins Cederberg Associate Scientist $ 79.32 64 $ 5,076.48 Cummins Cederberg Senior Designer $ 103.86 24 $2,492.64 Cummins Cederberg Secretary $ 60.00 6 $ 360.00
Sub-Total $15,247.50
Reimbursable Cost:
Postage Printing Overnight Travel (if applicable) Mileage (@ $0.445 per mile)
Reimbursable Total Cost $
Total for Subtask 3: $15,247.50
January 17, 2023 Page 77 of 77
CUMMINS CEDERBERG, INC. | Miami | Fort Lauderdale | Jupiter | St. Petersburg | Tallahassee
Project Schedule Activity Duration (Calendar Days) Subtask 1 – Topographic Survey 60 days from authorization to proceed Subtask 2A – Engineering Inspection 60 days from authorization to proceed Subtask 2B – Engineering Report 60 days from the completion of Subtask 2A Subtask 3A – Marine Resource Survey 60 days from authorization to proceed Subtask 3B – Marine Resource Report 60 days from the completion of Subtask 3A
Summary of Fees
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A – Topographic Survey $36,452.72 Subtask 2A – Engineering Inspection
$15,146.88 Subtask 2B – Engineering Report Subtask 3A – Marine Resource Survey
$15,247.50 Subtask 3B – Marine Resource Report
Total Fixed Price Cost: $ 66,847.10 Total Reimbursable Cost: $ 0.00
Overall Total Cost: $ 66,847.10
Conditions/Assumptions Client shall notify Cummins Cederberg of any known conditions related to the Project that may affect the above-described scope of services.
Client shall provide safe access to the Project site as needed by Cummins Cederberg to complete the above-described scope of services.
A second in season (June 1 – September 30) marine resource survey will likely be required for this Project if the initial survey is done outside of seagrass growing season. If a marine resource survey is required, Cummins Cederberg can provide one under an addendum scope of work.
Client will provide any available background information, such as as-built drawings, historical photographs, or other available documentation.
There will be no legal encumbrance issues, substantial objections from neighbors, no submerged land lease issues, and no historic or archaeological resource issues.