Summary: Task Assignment Notification Form - Curry Hammock State Park Beach Restoration
This is a Task Assignment Notification Form (Task Assignment No. 16) issued by the Florida Department of Environmental Protection (FDEP) under Contract CN330 to Cummins Cederberg, Inc., a coastal and marine engineering consulting firm. The task assignment pertains to engineering and environmental consulting services for beach restoration at Curry Hammock State Park in Monroe County, Florida. The contract manager is Ralph M. Perkins (FDEP), the project manager is Rose Frawley (FDEP), and the consultant representative is Jannek Cederberg. The task is authorized upon execution with a completion date of December 31, 2023.
The scope of work encompasses a phased analysis addressing approximately 1,305 linear feet of shoreline, comprising field investigations and data collection (topographic/bathymetric surveying, LiDAR review, aerial drone survey, preliminary benthic resource survey, and beach sand analysis), sea level rise and resilience evaluation, and feasibility assessment (regulatory due diligence and coastal engineering due diligence). The total fixed-price task amount is $66,836.87, with no cost reimbursement authorized. Payment is contingent upon FDEP approval of deliverables for each subtask. Deliverables include signed surveys, maps, orthographic imagery, field observation reports, technical memoranda, and feasibility studies. The project schedule allocates 60-day durations for most subtasks, with dependent tasks beginning 60 days after completion of Subtask 1.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: I Task Assignment No.: Owner's Name: I Project No.:CN330 16 FDEP 61407 Project Location: Project Name: Curry Hammock State Park Beach Re-Nourishment Consultant Name: Cummins Cederberg Consultant Representative: Phone: Email: Jannek Cederberg 305-741-6155 j cederberg@cumm i nscederberg.com FDEP Contract Manager: Phone: Email: Ralph M Perkins 850-245-2460 Ralph.Perkins@floridaDEP.gov Description of Task:
Task assignment to provide analysis of current conditions and erosion patterns of the beach at Curry Hammock State Park per attached proposal.
Project Manager: Rose Frawley
Start Date: I Upon ExecutionCompletion Date: I 12/31/23
Diane Langston Budget Representative, FDEP Rose Frawley Project Manager, FDEP Ralph M. Perkins Contract Manager, FDEP Jannek Cederberg Consultant Michael Foster Jr., P.E.
Contract Authority, FDEP
Project# Grant# Or2 Code
61407 37536060000
29 digit FLAIR Code:
Schedule Fixed Price Cost: $66,836.87Cost Reimbursement not to exceed: $ 0.00 Total Task Amount: $66,836.87 Approval Signatures:
Dl'ane Langston Digitally oigned by [l;ane Langston Date. 2022.051914:51:03-04'00'
Signature Rose Frawley Oog�ally signed by Rose Frawley
Dale 2022.06.20 15:06:14 --04W
Signature Ralph M Perkins �.:•��t:
d
2�"i��1��s��9:•
Signature
Date
Date
Date
Date
Cat/Year Fund Module Object Code EO
14126/22 423001 U3200 131500 QL
Total:
Amount
$66,836.87
$66,836.87
Page I of I
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.06.23 11:20:20 -04'00'
ClL\lMINS I Cl:DER.Bf:RG Coastal & \\arine l:ngitH'l-ring
February 11, 2022
Andrew Lippens, Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3900 Commonwealth Boulevard, MS 520
Sent via email: Andrew.Lippens@FloridaDEP.gov
RE: Contract CN330 TA16
Curry Hammock State Park Beach Restoration Project
Dear Mr. Lippens:
89391-R2
Cummins Cederberg respectfully submits the enclosed revised proposal for Coastal Engineering and Environmental Consulting Services in support of beach restoration at Bahia Honda State
Park. The proposal has been revised to delete the Subtask 4 - Grants Opportunities Research.
The scope of services provided for this preliminary phase now includes the following:
Subtask 1 - Field Investigations and Data Collection
Subtask 1A - Topographic/Bathymetric Survey
Subtask 1 B - LiDAR Review and Processing
Subtask 1 C - Aerial Drone Survey
Subtask 1 D - Preliminary Benthic Resource Survey
Subtask 1 E - Beach Sand Analysis Subtask 2 - Sea Level Rise/Resilience Evaluation
Subtask 3 - Feasibility Assessment
Subtask 3A - Regulatory Due Diligence
Subtask 38 - Coastal Engineering Due Diligence
We look forward to continuing to provide Coastal Engineering and Environmental Permitting
Consulting Services to the Florida Department of Environmental Protection in support of Curry
Hammock State Park beach restoration.
Sincerely, CUMMINS CEDERBERG, INC.
Jannek Cederberg
Principal
CUMMINS CEDERBERG, INC. I South Miami I Fort Lauderdale I Jupiter I St Petersburg I Tallahassee
Curry Hammock State Park Beach Restoration
February 11, 2022
89391-R2
Beach Restoration
Curry Hammock State Park
Contract Number: CN330, Task Assignment Number: 16
Cummins Cederberg, Inc. (Cummins Cederberg) is pleased to present this Scope of Work to the
Florida Department of Environmental Protection (FDEP) for engineering and environmental consulting services in support of Curry Hammock State Park Beach Restoration along approximately 1,305 linear ft of shoreline, as depicted in Figure 1 below (Project). The red lines in the Figure represent a total of 755 linear ft of shoreline identified by Park staff as high priority and the blue line represents 550 linear ft of shoreline identified as a secondary priority. This proposal includes work for the entire 1,305 linear ft of shoreline.
CUMMINS CEDERBERG, INC. I South Miami I Fort Lauderdale I Jupiter I St. Petersburg I Tallahassee