This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under Contract CN230, Task Assignment No. 90. The contract engages The Weiler Engineering Corporation, a consulting firm based in Punta Gorda, Florida, to provide structural investigation services for hurricane damage assessment at Gasparilla Island State Park. The project is managed by FDEP's Bureau of Design and Construction, with Ralph Perkins serving as the FDEP Contract Manager and Garland Sandel as the Project Manager.
The scope of work consists of two subtasks: an initial structural investigation to determine damage to the office, Armory Memorial Chapel, lighthouse, and boardwalk, with deliverables due within seven calendar days of task order execution; and a final inspection and amended determination following sand removal, due within fourteen calendar days thereafter. Subtask 1 is priced at $2,412.50 and Subtask 2 at $1,572.50, for a total fixed-price contract amount of $3,985.00 with no reimbursable costs. Payment is contingent upon FDEP approval of deliverables for each subtask. The project is scheduled to begin upon execution and conclude by April 29, 2025, with funding charged to FDEP's 29-digit FLAIR code 6M407C FD097 37504003191 080039/25 408001 U3200 131500 PF.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 90 FDEP 6M407C
Keeper House/Office
The Weiler Engineering Corporation
Jeff Weiler, P.E. (941) 505-1700 weiler7@mac.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov Description of Task:
This project consists of damage & providing a written . Per attached proposal dated 11/1/2024
Garland Sandel or successor
Upon Execution $ 3,985.00 4/29/2025 $ 0.00
$ 3,985.00
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.12.03 10:25:12 -05'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2024.12.03 11:22:16 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2025.01.13 14:38:31 -05'00'
Jeff Weiler, P.E. Jeff Weiler Digitally signed by Jeff Weiler Date: 2025.01.14 10:35:57 -05'00'
Michael W. Foster Jr., P.E.
6M407C FD097 37504003191 080039/25 408001 U3200 131500 PF $ 3,985.00
$ 3,985.00
Gasparilla Island State Park
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2025.01.27 15:32:42 -05'00'
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
November 1, 202
Mr. Garland Sandel Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Gasparilla State Park Hurricane Milton Damage - Office C 230 - TA
Dear Mr. Sandel;
We understand that you would like for us to provide preliminary structural inspections of the office within Gasparilla Island State Park post Hurricane Milton. Once the sand is removed from the site, a secondary structural inspection will be needed to further any damage.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
11/1/24 Mr Garland Sandel GISP Office
Gasparilla Island State Park - Office Contract Number 230, Task
Assignment Number
Subtask 1: Site Visit and Description: WEC will attend an initial site visit to Armory Memorial Chapel, lighthouse, boardwalk, and office and prepare a with findings and recommendations..
Deliverable: Consultant shall deliver a outline findings (digital PDF only) including:
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2: Final Inspection & Description: After the sand is removed Consultant will make one more site visit to additional damage and amend the initial report accordingly.
Deliverable: Final report amended to include any discovery after the sand is removed Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 - Site Visit and Initial
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 6 690
Senior Engineering Designer 100 6 600
Engineering Technician 80 6 480
Clerical 55 .25 13.75
Total for Subtask 1
2412.5
Mr Garland Sandel GISP Office Assessment
Reimbursable Cost:
Schedule
Subtask 2 - Final
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 0 0
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 3 345
Senior Engineering Designer 100 3 300
Engineering Technician 80 4 320
Clerical 55 .5 27.5
Total FInal 1572.5
Postage 0 35 0
Printing 0 2.30 0
Overnight Travel
(if applicable)
Reimbursable Total Cost
Total for Subtask 2
1572.5
Mr Garland Sandel GISP Office
Summary of Fees:
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Activity Duration (Calendar Days) Dates to be based on date of execution of task order
Subtask 1 - Initial 7
Subtask 2 - Final 14 after sand is removed
Subtask Additional Services Fee Additional Reimbursement Estimate
Subtask 1 - Initial 2412.5 0.00
Subtask 2 - Final 1572.5 0.00
Totals $3985.00 $0.00