This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a service contract with Weiler Engineering Corporation. The document, executed on December 22, 2020, involves the modification of an existing task assignment for the Lignumvitae Key State Park Service Dock Replacement project. The contract manager for FDEP is Philip Stone, and the consultant representative is Jeff Weiler. The change order was approved by Budget Representative Suzanne Lane, Project Manager C Hewitt, Contract Manager Philip Stone, Consultant Jeff Weiler, and Contract Authority Michael W. Foster Jr., P.E.

This change order extends the task completion timeline by 365 days, moving the original task end date from December 31, 2020, to December 31, 2021, to allow for completion of design and permitting activities. The change order is for time extension only with no adjustment to the task amount, which remains at $43,463.61 in total compensation ($2,361.45 in reimbursement and $41,102.16 in fixed fee). The original task execution date was February 17, 2020. The modification was requested via email dated December 21, 2020, by Robin Palmer, P.E., an Environmental Engineer at Weiler Engineering Corporation.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
CN-370000-CN230-T34CO1.pdf PDF
CN-370000-CN230-T37.pdf PDF
CN-370000-CN230-T37CO1.pdf PDF
CN-370000-CN230-T42CO1.pdf PDF
CN-370000-CN230-T42CO3.pdf PDF
CN-370000-CN230-T43.pdf PDF
CN-370000-CN230-T44.pdf PDF
CN-370000-CN230-T48.pdf PDF
CN-370000-CN230-T51CO2.pdf PDF
CN-370000-CN230-T54CO1.pdf PDF
CN-370000-CN230-T58.pdf PDF
CN-370000-CN230-T63.pdf PDF
CN-370000-CN230-T65.pdf PDF
CN-370000-CN230-T67.pdf PDF
CN-370000-CN230-T6CO1.pdf PDF
CN-370000-CN230-T72CO1.pdf PDF
CN-370000-CN230-T74.pdf PDF
CN-370000-CN230-T81.pdf PDF
CN-370000-CN230-T81CO1.pdf PDF
CN-370000-CN230-T82.pdf PDF
CN-370000-CN230-T83.pdf PDF
CN-370000-CN230-T84.pdf PDF
CN-370000-CN230-T85.pdf PDF
CN-370000-CN230-T88.pdf PDF
CN-370000-CN230-TA31.pdf PDF
CN-370000-CN230-TA5.pdf PDF
PC-370000-CN230.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN230 21 01 61268C

Lignumvitae Key State Park Service Dock Replacement

Weiler Engineering Corporation

Jeff Weiler 941-505-1700 weiler7@mac.com

Philip Stone Philip.Stone@FloridaDEP.gov

Change Order for time extension only to complete design and permitting. See attached email dated 12/21/20.

$ 2,361.45 $ 41,102.16 $ 43,463.61 $ 2,361.45 $ 41,102.16 $ 43,463.61

$ 0.00 $ 0.00 $ 0.00 $ 2,361.45 $ 41,102.16 $ 43,463.61

2/17/2020

12/31/2020

12/31/2020

12/31/2021

Suzanne Lane Suzanne Lane Digitally signed by Suzanne Lane Date: 2020.12.22 11:51:23 -05'00'

C Hewitt C Hewitt Digitally signed by C Hewitt Date: 2020.12.22 14:04:50 -05'00'

Philip Stone P.T. Stone Digitally signed by P.T. Stone Date: 2020.12.22 14:34:06 -05'00'

Jeff Weiler R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2020.12.29 11:23:03 -05'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr.

Digitally signed by Michael W.

Foster Jr.

Date: 2020.12.29 15:42:28 -05'00'

$ 0.00

From: rpalmer@weilerengineering.org To: Hewitt, C. B.

Cc: "Jeff Weiler" Subject: Lignumvitae Key Service Dock TA Extension Request Date: Monday, December 21, 2020 9:04:18 AM Attachments: image001.jpg

Good morning C, Can I please have a time extension on the Lignumvitae Key Service Dock Replacement project until 12/31/2021?

Thank you, Robin Palmer, P.E.

Environmental Engineer mailto:rpalmer@weilerengineering.org mailto:C.B.Hewitt@dep.state.fl.us mailto:weiler7@mac.com