CN-370000-CN230-T25CO2.pdf
PDF 987 KB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN230. The change order involves Weiler Engineering Corporation, Inc., a consulting firm based in Punta Gorda, Florida, and pertains to the Myakka River State Park Concession Project. The change order was executed in December 2021 and required approval from multiple FDEP representatives, including the Budget Representative, Project Manager, Contract Manager, and Contract Authority.
The change order is additive in nature and addresses time extension only, with no change to the task amount. The original task amount was $13,862.20, which includes $434.70 in reimbursement and $13,427.50 in fixed fees. The total task amount remains $37,099.50 with all change orders. The primary modification extends the project duration by 365 days due to unknown conditions that delayed both consultant design work and FDEP funding of required new work. The original task end date of July 1, 2021, was extended to December 31, 2021, and subsequently extended further to December 31, 2022, by this change order. The project is funded under FLAIR Code 61231C with the project number 61231C and is categorized as CA Services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 TA25 CO2 61231C
Myakka River State Park Concession Project CA Services
Weiler Engineering Corporation, Inc.
Jeff Weiler (941)505-1700 weiler7@mac.com
Alyssa Skehan (850)245-2781 Alyssa.Skehan@FloridaDEP.gov
Additive change order for time. Unknown conditions have extended the time required for consultant to design and for FDEP to fund the required new work. As per attached proposal dated 12/16/2021.
$ 434.70 $ 13,427.50 $ 13,862.20 $ 569.60 $ 36,529.90 $ 37,099.50 $ 0.00 $ 0.00 $ 0.00
$ 569.60 $ 36,529.90 $ 37,099.50
08/19/2020
7/1/2021
12/31/2021
12/31/2022
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.12.16 15:36:53 -05'00'
John Goss John Goss Digitally signed by John Goss Date: 2021.12.16 08:27:46 -05'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2021.12.21 10:24:53 -05'00'
Jeff Weiler, PE R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2021.12.21 12:08:01 -05'00'
Michael Foster Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2021.12.22 08:52:51 -05'00'
61231C
$ 0.00
From: Brian Corso To: Goss, John Cc: rpalmer@weilerengineering.org Subject: RE: Expiring TA - Myakka Concession Date: Thursday, December 16, 2021 4:16:11 PM Attachments: FE CN230 TA25_revised.pdf
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Good afternoon John, Regarding the Myakka Concession Building remodel, in light of the project delays, we kindly request a Change Order for time on TA25, as to add 365 days to the project duration.
Let me know if there is a form or anything else I can do to facilitate this.
Regards, Brian Corso Structural Department Manager The Weiler Engineering Corporation 201 W. Marion Ave. Suite 1306 Punta Gorda, FL 33950
(941) 505-1700 ext.210 mailto:bcorso@weilerengineering.org mailto:John.Goss@FloridaDEP.gov mailto:rpalmer@weilerengineering.org
| CN230 TA25 CO2 Myakka River Concession - signed (003).pdf |
| Expiring TA - Myakka Concession.pdf |
File details come from the government source that posted it. Updated .