CN-370000-CN230-T67.pdf
PDF 1 MB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
Contract Summary
This is a Task Assignment Notification Form and associated proposal from the Florida Department of Environmental Protection (FDEP) for the Accessible Launch project at Lovers Key State Park. The task assignment (CN230, Task Assignment 67) engages Weiler Engineering Corporation as the consultant, with project management oversight provided by FDEP staff including Ralph Perkins (Contract Manager) and Garland Sandel (Project Manager). The consultant representative is Jeff Weiler, P.E.
The scope of work comprises ten subtasks spanning design, permitting, and construction-phase engineering services for an accessible kayak launch facility. Design and permitting services include updated survey ($4,286.00), updated 100% plans ($2,353.75), permit applications ($1,453.75), and permit approvals ($807.50) for a subtotal of $9,051.00. Construction-phase services include assistance during bidding ($1,580.00), pre-bid meeting attendance ($1,404.50), pre-construction meeting attendance ($1,344.50), submittal review ($2,280.00), construction phase assistance for three months ($3,045.00), substantial completion walk-through and punchlist ($2,164.50), and final completion with certifications ($2,149.50), totaling $13,968.00 for construction services. The total fixed price cost is $22,691.00 with reimbursable costs not to exceed $328.00, for a total task amount of $23,019.00. The completion date is December 31, 2024. Payment is made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 67 FDEP 61306C
Lovers Key State Park Accessible Launch
Weiler Engineering Corporation
Jeff Weiler (941)628-4732 Cell weiler7@mac.com
Ralph Perkins or successor 850-245-2560 ralph.perkins@floridadep.gov
Consultant to provide updated design and permits for the construction of an accessible kayak launch for one side of the existing launch area, provide erosion control measures for the other existing launch area to make it safer to use and add at least 1 ADA parking spot near ADA kayak launch.... per the attached proposal dated 3.23.23.
Garland Sandel or successsor
Execution date $ 22,691.00
12.31.24 $ 328.00
$ 23,019.00
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.05.31 14:26:27 -04'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.05.31 14:31:19 -04'00'
David Matson for Ralph Perkins or Successor David Matson Digitally signed by David Matson Date: 2023.06.01 09:32:41 -04'00'
Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.06.01 10:10:30 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.06.02 15:29:25 -04'00'
61306C 37504000193 080039/23 423001 U3100 131500 QK $ 23,019.00
$ 23,019.00
March 23, 2023
Mr. Garland Sandel Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Lovers Key Kayak Launch - Update Plans and CEI - Contract 230, TA67
Dear Mr. Sandel;
We are pleased to offer this proposal to update the plans and documents previously completed by Weiler Engineering and renew the Army Corps of Engineers (ACOE) permit and provide services during construction.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.
Please feel free to contact me if you have any questions or wish to discuss matters further.
Sincerely, R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
Lovers Key Kayak Launch
CN 230 TN68
Lovers Key Kayak Launch
Update Plans and CEI Contract Number 230, Task Assignment Number 68
Subtask 1: Survey Description: The Weiler Engineering Corporation (Consultant) will coordinate with a Florida Registered Engineer to update the existing special purpose survey including the upland and bathymetric in the area of the new dock adequate for design and permitting.
Deliverable: Consultant will provide a Signed and Sealed Special Purpose survey (Not a Boundary Survey) in PDF format via email to the Bureau of Design and Construction (BDC).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 - Survey
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 2 290
3 Person Field Crew Hr 121.50 16 1944
Survey Technician Hr 54.00 20 1080
PSM Manager Hr 162 6 972
Total Survey 4286
Postage
Printing
Overnight Travel (if applicable) Mileage (@ $0.445 per mile)
Reimbursable Total Cost $0.00
Total Subtask 1 Survey
$4286.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS Text Box
Robinson_MS Text Box
Subtask 2 - Plans Update
Description: Consultant will update the plans to accommodate minor changes in topography based on updated survey and for submittal to the ACOE.
Deliverable: Consultant will provide 100% plans via PDF/ email.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Reimbursable Cost: (if applicable)
Subtask 2 – 100% Plans
Firm Name Position Classification Hour ly Rate
Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 $290.00
Principal in Charge 195 0.25 $48.75 Registered Professional Engineer 145 2 $290.00
Registered Engineer Intern 115 2 $230.00
Senior Engineering Designer 100 8 $800.00
Engineering Technician 80 8 $640.00
Clerical 55 1 $55.00
Total $2353.75
Postage
Printing
Overnight Travel (if applicable)
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 3: Permitting
A – Permit Applications, Description: Consultant will assist Client to submit permit applications to renew the ACOE Permit.
Deliverable: Consultant shall deliver five sets of permit applications with 100% plans.
B – Permit Approvals, Description: Documents with Permit applications for renewal of the ACOE permit.
Deliverable: Consultant will provide via email to the BDC the approved permits for ACOE.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Mileage (@ $0.445 per mile) Reimbursable Total Cost $0.00
Total Subtask 2 $2353.75
Subtask 3A Permit Applications
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 $290.00
Principal in Charge 195 0.25 $48.75 Registered Professional Engineer 145 1.50 $217.50
Registered Engineer Intern 115 6 $690.00
Senior Engineering Designer 100 1 $100.00
Engineering Technician 80 1 $80.00
Clerical 55 0.50 $27.50
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Reimbursable Cost:
Subtask 4: Assistance during bidding
Description: Consultant will respond to bidders’ questions and provide clarifications during bidding.
Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.
Total $1453.75
Subtask 3B Permit Approvals
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 $0.00 Registered Professional Engineer 145 1 $145.00
Registered Engineer Intern 115 2 $230.00
Senior Engineering Designer 100 1 $100.00
Engineering Technician 80 2 $160.00
Clerical 55 0.50 $27.50
Total $807.50
Postage 1 Fed-x at $35 $35.00
Printing 50 sheets @ $2.30/sheet
$115.00
Reimbursable Total Cost $150.00
Total for Subtask 3 $2411.25
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Reimbursable Cost:
Subtask 4 Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 $290.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 1 $145.00
Registered Engineer Intern 115 6 $690.00
Senior Engineering Designer 100 4 $400.00
Engineering Technician 80 0 $0.00
Clerical 55 1 $55.00
Total $1580.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage ($0.445 per mile)
Not anticipated
Reimbursable Total Cost
$0.00
Total for Subtask 4 $1580.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 5: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Reimbursable Cost:
Subtask 5 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern 115 4 $460.00
Senior Engineering Designer 100 0 $0.00
Engineering Technician 80 4 $320.00
Clerical 55 0 $0.00
Total $1360.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.50
Reimbursable Total Cost
$44.50
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 6: Attend Pre-Construction Meeting Description: WEC staff will attend one pre-construction meeting on site, respond to questions and prepare minutes.
Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Reimbursable Cost:
Total Subtask 5
$1404.50
Subtask 6 - Pre-construction Mtg
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern
115 0 $0.00
Senior Engineering Designer
100 4 $400.00
Engineering Technician 80 4 $320.00
Clerical 55 0 $0.00
Total $1300.00
Postage Not anticipated
Printing Not anticipated
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 7: Review Contractor submittals
Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.
Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.5
Reimbursable Total Cost
$44.50
Total Subtask 6 $1344.50
Subtask 7 - Submittal Review
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 $290.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern
115 8 $920.00
Senior Engineering Designer
100 8 $800.00
Engineering Technician
80 2 $160.00
Clerical 55 2 $110.00
Total $2280.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 10: Assistance during construction (3 Months)
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Deliverable: Correspondence with Contractor and regulatory agencies provide via PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Postage Not anticipated (all deliverables in digital form only)
Printing Not anticipated (all deliverables in digital form only)
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
$0.00
Total Subtask 7 - Submittals
$2280.00
Subtask 8
Firm Name Position Classification Hourly Rate
Ho urs
Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 $870.00
Principal in Charge 195 1 $195.00
Registered Professional Engineer
145 4 $580.00
Registered Engineer Intern
115 6 $690.00
Senior Engineering Designer
100 6 $600.00
Engineering Technician 80 0 $0.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 9: Substantial Completion Walk-Through w/Punchlist Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.
Deliverable: WEC will provide comments and input on punch list within one (1) day of Substantial Completion inspection.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Clerical 55 2 $110.00
Total $3045.00
Postage Not anticipated
Printing Not anticipated (all deliverables in digital form only)
Overnight Travel (if applicable) Not anticipated
Mileage (@ $0.445 per mile) Not anticipated
Reimbursable Total Cost $0.00
Total Subtask 8 $3045.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Subtask 10: Final Completion w/ Certification
Description: WEC will assist Client with the Final Completion inspection of the site with WEC representative attending the Final Completion inspection.
Deliverable: WEC will prepare final certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 9
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 1 $195.00
Registered Professional Engineer
145 1 $145.00
Registered Engineer Intern
115 4 $460.00
Senior Engineering Designer
100 1 $100.00
Engineering Technician 80 8 $640.00
Clerical 55 0 $0.00
Total $2120.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.50
Reimbursable Total Cost
$44.50
Total Subtask 9 $2164.50
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Project Schedule:
Subtask 10 - Final
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Prroject Manager 145 4 $580.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 2 $290.00
Registered Engineer Intern 115 4 $460.00
Senior Engineering Designer
100 4 $400.00
Engineering Technician 80 4 $320.00
Clerical 55 1 $55.00
Total $2105.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.50
Reimbursable Total Cost
$44.50
Total Subtask 10 $2149.50
Activity Duration (Calendar Days) Dates to be based on date of execution of task order
Subtask 1 Survey 30
Subtask 2: 100% plans 30 – includes 7 days for Client review
Subtask 3A: Permit applications 15 – includes 7 days for Client review
Subtask 3B: Permit approvals 60 – includes response for additional information
Subtask’s 4-10 240
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
Summary of Fees:
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 1 - Survey $4286.00 $0.00
Subtask 2: 100% plans $2353.75 $0.00
Subtask 3A Permit applications $1453.75 $150.00
Subtask 3B Permit approvals $807.50 $0.00
Subtotal Design & Permitting $8901.00 $150.00
Total Design & Permitting $9051.00
Subtask 4: Assistance during bidding
$1580.00 $0.00
Subtask 5: Pre-bid meeting $1360.00 $44.50 Subtask 6: Attend Pre-Con Mtg $1300.00 $44.50
Subtask 7: Review Submittals $2280.00 $0.00
Subtask 8: Assistance during Construction - 3 Months
$3045.00 $0.00
Subtask 9: Substantial Completion Walk-Through w/Punchlist - Site
$2120.00 $44.50
Subtask 10: Final Completion w/ Certification
$2105.00 $44.50
Subtotal Construction Services $13790.00 $178.00
Total Fixed Price $22691.00
Total Reimbursable Cost $328.00
Total Overall Cost $23019.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Robinson_MS
| BLANK TA Form.pdf |
| CN230 TA67 Lovers Key-Kayak Launch.pdf |
File details come from the government source that posted it. Updated .