CN-370000-CN230-T81.pdf
PDF 439 KB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for a project at Bill Baggs Cape Florida State Park. The task assignment, numbered 81 under FDEP Contract CN230, engages Weiler Engineering Corporation as the consultant, with Jeff Weiler as the consultant representative and Ralph Perkins as the FDEP Contract Manager. The project is located at Bill Baggs State Park and is managed by the Bureau of Design and Construction within FDEP.
The scope of work encompasses improving beach access points 4 and 5 through repairing existing boardwalks and rails or replacing them with a natural walking trail. The project is structured in three main subtasks: Subtask 1 (Preliminary - 30%) includes site investigation, survey coordination, and lead and asbestos reporting at a cost of $13,378.59; Subtask 2 (100% Plans) involves completing final design documents for $8,719.75; and Subtask 3 (Permitting) addresses permit applications and approvals for $5,339.50. The total fixed price cost is $27,229.84 with reimbursable costs of $208.00, bringing the overall task amount to $27,437.84. The project execution date begins immediately upon approval, with a completion date of April 29, 2025. Payment is contingent upon FDEP approval of deliverables for each subtask. The project schedule extends 180 days from contract acceptance to permit approval completion.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 81 FDEP/DRP 61564C
Bill Baggs Cape Florida State Park Beach Access 4 & 5 Improvements
Weiler Engineering
Jeff Weiler 941-628-4732 weiler7@mac.com
Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov
Improving beach access points 4 and 5 by repairing the existing boardwalks/rails and/or replacing with a natural walking trail per the attached dated: November 17th, 2023.
Garland Sandel
Execution date $ 27,229.84 4/29/25 $ 208.00
$ 27,437.84
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.12.21 08:05:28 -05'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.12.21 08:59:03 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.12.21 13:06:33 -05'00'
Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2024.01.04 12:02:51 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2024.01.05 10:48:21 -05'00'
61564C 37505000011 080039/24 675002 U3200 131500 XR $ 27,437.84
$ 27,437.84
November 17, 2023
Mr. Garland Sandel Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Bill Baggs State Park - Beach Access 4 & 5 Improvements, CN - 230, TA - 81
Dear Mr. Sandel;
Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to repair the existing boardwalks/rails (Option 1) or replace with a natural walking trail (Option 2) at Beach access 4 & 5.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Mr. Garland Sandel Bill Baggs State Park Beach Access 4 & 5 Improvements
CN 230/TA81
Bill Baggs State Park
Contract Number 230, Task Assignment Number 81
Subtask 1: Preliminary - 30%
1) A - Preliminary investigation,
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP and the Local Building Department.
c) Consultant will prepare a preliminary site plan and opinion of probable cost for both options.
1) B – Survey
a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topo including the existing boardwalk and rails and ten feet each side.
1) C - Lead & Asbestos Report
a) Consultant will coordinate with Universal Engineering to complete one (1) lead and asbestos survey/report for all six structures.
Deliverable:
1) A - Preliminary investigation, Conceptual Site Plan – Consultant shall deliver 30% plans to the client via digital PDF. Plans will include:
Cover sheet Survey Existing Conditions 30% Site Plan for each option Opinion of probable cost for each option
1) B - Survey
Completed Survey - Consultant shall deliver a special Purpose Survey via digital PDF, CAD and a Signed and Sealed copy.
Mr. Garland Sandel Bill Baggs State Park
1) C - Lead & Asbestos Report
Written results of surveys will be delivered via email to the BDC via digital PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A - Preliminary Investigation
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 8 1160
Registered Engineer Intern 115 24 2760
Senior Engineering Designer 100 16 1600
Engineering Technician 80 16 1280
Clerical 55 2 110
Total
8118.75
Subtask 1B - Survey
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 4 580
Survey 3 Person Field Crew Hr 121.50 8 972
Survey Technician Hr 54.00 8 432
PSM Manager Hr 162 8 1296
Total Survey 3280
Mr. Garland Sandel Bill Baggs State Park
Subtask 1C - Lead & Asbestos
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Registered Professional Engineer
Hr 145 1
Registered Engineer Intern
Hr 115 1
Universal Engineering Senior Geotechnical Engineer, PE
Hr 165.84 8 1326.72
Sr. Engineering Technician Hr 49.14 8 393.12
Total 1979.84
Reimbursable Cost 1 Only: (if applicable)
Descrip(on Number @ Total
Postage
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
0.445 0 0
Total 0
Total Subtask 1 13378.59
Subtask 2: 100% documents
Description: Plans completed to 100% for one option incorporating comments from 30%.
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only) including:
Opinion of Probable Cost;
Cover sheet Existing Conditions
Mr. Garland Sandel Bill Baggs State Park
Site, Grading Plan (One Plan Sheet) Details General Notes
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Subtask 2 - 100% Plans
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 8 1160
Registered Engineer Intern 115 16 1840
Senior Engineering Designer 100 24 2400
Engineering Technician 80 24 1920
Total 8638.75
Total for Subtask 2 100% Plans
8638.75
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Reimbursable Cost:
Mr. Garland Sandel Bill Baggs State Park
Postage 1 35 35
Printing 20 2.30 46
Overnight Travel
(if applicable)
Reimbursable Total Cost
Subtask 2 - 100% Plans
8719.75
Subtask 3: Permitting
Description:
3) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.
3) B – Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
3) A – Permit Applications, Incorporate Client review comments from 30% plans and deliver five sets of permit applications with 100% plans.
3) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Mr. Garland Sandel Bill Baggs State Park
Consultant will provide Client with approvals and revised (if necessary) plans and documentation
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 3A Permit Applications
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 6 870
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 4 580
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 4 400
Engineering Technician 80 4 320
Total 3248.75
Subtask 3B Permit Approvals
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 2 200
Engineering Technician 80 2 160
Clerical 55 1 55
Mr. Garland Sandel Bill Baggs State Park
Total 1963.75
Reimbursable Cost:
Postage 1 35 35
Printing 40 2.3 92
Reimbursable Total Cost for3A
Subtask 3 - Permits
5339.5
Project Schedule:
Activity Duration (Calendar Days) Days from Contract Acceptance
Subtask 1A Preliminary 60 60
Subtask 1B Survey 60 60
Subtask 1C Lead & Asbestos 60 60
Subtask 2: 100% plans 30 - includes 7 days for Client review
Subtask 3A: Permit applications 30 – includes 7 days for Client review
Subtask 3B: Permit approvals 60 – includes response for additional information
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A Preliminary $8118.75 $0.00
Subtask 1B Survey $3280.00 $0.00
Subtask 1C Lead & Asbestos $1979.84 $0.00
Subtask 2: 100% plans $8638.75 $81.00
Mr. Garland Sandel Bill Baggs State Park Beach Access 4 & 5 Improvements
CN 230/TA81
Subtask 3A Permit applications $3248.75 $127.00
Subtask 3B Permit approvals $1963.75 $0.00
Total Fixed Price Cost: $27229.84
Total Fixed Price Cost: $208.00
Overall Total Cost: $27437.84
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)