CN-370000-CN230-T65.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CN230|5f4ec01f5eb38b1957861cb8292c2183
Contract number
CN230
Issued by
Florida

About this file

This is a Task Assignment Notification Form from the Florida Department of Environmental Protection (FDEP) for a design and construction management project at Koreshan State Park. The contract involves FDEP as the state agency, The Weiler Engineering Corporation as the consultant, and the project manager Del Cobb representing FDEP. The task assignment is designated as CN230 TA65 and covers comprehensive engineering services for campground redevelopment at 3800 Corkscrew Road, Estero, Florida.

The scope of work includes preparing plans and documentation to restore 60 campsites with ADA accessibility, utility work (water and electrical adjustments), and restoration of approximately 4,000 linear feet of internal roadway through mill and overlay. Services are organized into six main phases: (1) 30% design with surveys and geotechnical reports; (2) 60% design documents; (3) 100% design documents with specifications; (4) permitting and permit approvals; (5) pre-bid meeting attendance; and (6) construction phase services including pre-construction meeting, submittal review, RFI response, six monthly inspections, substantial completion walk-through, and final completion certification. The fixed price cost is $127,007.01, with reimbursable costs not to exceed $2,957.20, for a total task amount of $129,964.21. The project completion date is 5/10/2026, with execution commencing upon task assignment signing. Payment will be made upon FDEP approval of deliverables for each subtask in the amounts specified.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T21CO1.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
CN-370000-CN230-T34CO1.pdf PDF
CN-370000-CN230-T37.pdf PDF
CN-370000-CN230-T37CO1.pdf PDF
CN-370000-CN230-T42CO1.pdf PDF
CN-370000-CN230-T42CO3.pdf PDF
CN-370000-CN230-T43.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 TA65 FDEP-DRP 61510C

3800 Corkscrew Road, Estero, FL. 33928 Koreshan State Park - Campground Upgrades

The Weiler Engineering Corporation

Robin Palmer, P.E. (941) 505-1700 rpalmer@weilerengineering.org

Ralph Perkins, or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Prepare the plans & documentation necessary to restore the campsites & roadway areas, restore the existing utilities, at Koreshan State Park Campground per attached proposal dated 5/10/2023.

Del Cobb, or successor

Upon Execution $ 127,007.01 5/10/2026 $ 2,957.20

$ 129,964.21

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.01 11:10:23 -04'00'

Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2023.06.01 16:23:08 -04'00'

Michael Foster for Ralph Perkins Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.06.05 11:17:48 -04'00'

Robin Palmer, P.E. Robin C. Palmer Digitally signed by Robin C.

Palmer Date: 2023.06.05 11:55:26 -04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.06.22 15:43:39 -04'00'

61510C 37504000045 080039/23 423001 U3200 134000 QK $ 129,964.21

$ 129,964.21

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

• Replace 60 campsites

◦ ADA accessible campsites near bathhouse

◦ Campsite utilities to include water and electric. No sewer connections.

• Utility Work

◦ Adjust water and electrical services at the campsites for consistency (no main extensions or relocations)

• Roadway

◦ Restore roadway internal to campground (Approx 4,000 ft) mill and overlay) Our services will include:

D. Bidding and Construction Services

WEC will assist Client during bidding and construction to respond to questions and requests for additional information, provide periodic observation and project close out.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

Subtask 1: 30% Design

1) A - Design

a) WEC will conduct one site visit.

b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP and the Local Regulatory agency.

c) Consultant will prepare a site plan and typical sections and;

d) Consultant will prepare an opinion of probable cost

1) B – Surveys

a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey of the existing roadways and campsites.

1) C –Geotechnical Reports

a) Consultant will coordinate with Geotechnical Sub-Consultant to conduct core drilling at approximately 1 per 1/2 Mile and prepare a geotechnical Report identifying existing pavement section and LBR’s at every other core.

Deliverable:

1) A - Conceptual Design, Conceptual Site & Structural Plans – Consultant shall deliver 30% Plans to the client via digital PDF. Plans will include:

Cover sheet Survey Existing Conditions Site Plan Typical Sections Opinion of probable cost

1) B - Surveys

Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey via digital PDF, CAD and a Signed and Sealed copy.

1) C –Geotechnical Reports If Necessary

Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report identifying existing pavement, base and subbase at approximately 1 per 2600 feet of roadway & LBR’s each mile via digital PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1A - 30% Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 22 3190

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 18 2610

Weiler Engineering Registered Engineer Intern 115 29 3335

Weiler Engineering Senior Engineering Designer 100 70 7000

Weiler Engineering Engineering Technician 80 100 8000

Weiler Engineering Clerical 55 8 440

Total 24623.75

Subtask 1B - Survey

Firm Name Position Classification Unit Unit Rate Numbe r Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 8 1160

Reimbursable Cost: (if applicable)

CHW 3 Person Field Crew Hr 177.54 40 7101.6

CHW Project Surveyor Hr 74.75 24 1794

CHW Professional Surveyor & Mapper

Hr 163.93 12 1967.16

CHW Senior CAD/GIS Hr 103.13 40 4125.2

Total Survey 16147.96

Subtask 1C Geotech

Firm Name Position Classification Unit Unit Rate Numbe r Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Universal

Universal Senior Project Engineer Hr 165.84 16 2653.44

Universal Project Engineer Hr 94.50 16 1512

Universal Staff Engineer Hr 68.46 16 1095.36

Universal CAD Drafting Hr 54.00 8 432

Universal Total Geotech 6272.8

Description Number @ Total

Postage

Printing

Overnight Travel

(if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Subtask 2: 60% documents

Description: Plans completed to 60% incorporating comments from 30%.

Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost;

Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plans Site Details and General Notes

Reimbursable Total Cost 1A

Total Subtask 1 47044.51

Subtask 2 - 60% Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 22 3190

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 20 2900

Weiler Engineering Registered Engineer Intern 115 30 3450

Subtask 3: 100% documents

Description: Plans completed to 100%.

Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Opinion of Probable Cost;

Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site/Drainage Details and General Notes Specifications

Engineering Senior Engineering Designer 100 72 7200

Weiler Engineering Engineering Technician 80 100 8000

Weiler Engineering Clerical 55 8 440

Total 25228.75

Total for Subtask 2

25228.75

Subtask 3 - 100% Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Engineering Project Manager 145 14 2030

Reimbursable Cost:

Subtask 4: Permitting

Description:

4) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for exemption.

4) B – Permit Approvals, Weiler Engineering Principal in Charge 195 0.25 48.75

Weiler Engineering

Registered Professional Engineer 145 16 2320

Weiler Engineering Registered Engineer Intern 115 20 2300

Weiler Engineering Senior Engineering Designer 100 50 5000

Weiler Engineering Engineering Technician 80 64 5120

Weiler Engineering Clerical 55 6 330

Total 17148.75

Description Number @ Total

Postage 1 35 35

Printing 64 2.30 147.2

Overnight Travel

(if applicable)

Reimbursable Total Cost

182.2

Total for Subtask 3

17330.95

Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.

Deliverable:

4) A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five sets of permit applications with 100% plans.

4) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation

Subtask 4A Permit Applications

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 12 1740

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering Registered Professional Engineer 145 10 1450

Weiler Engineering Registered Engineer Intern 115 16 1840

Weiler Engineering Senior Engineering Designer 100 41 4100

Weiler Engineering Engineering Technician 80 57 4560

Engineering Clerical 55 5 275

Total 14160

Subtask 4B Permit Approvals

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 4 580

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering Registered Professional Engineer 145 3 435

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 8 640

Weiler Engineering Clerical 55 1 55

Total 3395

Description Number @ Total

Postage 1 35 35

Printing 200 2.3 460

Permit application fees estimate

1 2000 2000

Reimbursable Total Cost for 4A

Total for Subtask 4

20050

March 30, 2023, Rev 1 May 10, 2023 Mr. Del Cobb Koreshan State Park Campground

CN 230/TA65

Subtask 5: Attend a Pre-Bid meeting on-site

Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.

Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Reimbursable Cost:

Subtask 5 - Pre-bid

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Weiler Engineering Principal in Charge 195 0 $0.00

Weiler Engineering Registered Professional Engineer

145 0 $0.00

Weiler Engineering Registered Engineer Intern 115 8 $920.00

Weiler Engineering Senior Engineering Designer 100 8 $800.00

Weiler Engineering Engineering Technician 80 8 $640.00

Weiler Engineering Clerical 55 0 $0.00

Total $3520.00

Description Number @ Total Postage Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Subtask 6A - 6L: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)

Subtask 6A: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Reimbursable Total Cost $0.00

Total Subtask 5 $3520.00

Subtask 6A - Pre-Construction Mtg

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 0 0

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 2080

Mr. Del Cobb Koreshan State Park Campground

CN 230/TA65

Subtask 6B: Review Contractor submittals

Description:WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Description Number @ Total

Postage 0

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile) 0

Reimbursable Total Cost 0

Total subtask 6A 2080

Subtask 6B - Review Submittals

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 12 1200

Weiler Engineering Engineering Technician 80 2 160

Weiler Engineering Clerical 55 2 110

Total 2680

Mr. Del Cobb Koreshan State Park Campground

Subtask 6C: Respond to Contractor RFI's

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 6B 2715

Subtask 6C- Respond to RFI’s

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 2 290

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Subtask 6D: Provide Construction Inspections (Month 1)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 4 220

Total 2520

Description Number @ Total

Postage 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 6C 2520

Subtask 6D - Month 1 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Subtask 6E: Construction Inspection (Month 2)

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 6D 1007.5

Subtask 6F: Construction Inspection (Month 3)

Subtask 6E

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost

Total Subtask 6E 1042.5

Subtask 6G: Construction Inspection (Month 4)

Subtask 6F Month 3 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 35

Total Subtask 7F 1042.5

Mr. Del Cobb Koreshan State Park Campground

Descrip3on: WEC will provide a monthly inspec+on (NLT every 30 days) during construc+on.

Subtask 6G - Inspection Month 4

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Total Subtask 6G 1042.5

Mr. Del Cobb Koreshan State Park Campground

CN 230/TA65

Subtask 6H: Construc3on Inspec3on (Month 5)

Descrip3on: WEC will provide a monthly inspec+on (NLT every 30 days) during construc+on.

Subtask 6H Month 5 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Subtask 6I: Construction Inspection (Month 6)

Total Subtask 6H 1042.5

Subtask 6I Month 6 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Subtask 6J: Substantial Completion Walk-Through w/Punchlist

Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 35

Total Subtask 6I 1042.5

Subtask 6J Substantial

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Poject Manager 145 6 870

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 1 145

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1805

Subtask 6K: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.

Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager.

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 35

Total Subtask 6J 1840

Subtask 6K - Final

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Poject Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 1 145

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 2 200

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 1 55

Total 1380

Project Schedule:

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 35

Total Subtask 6K 1415

Activity Duration (Calendar Days) Days from Execution

Subtask 1A Preliminary 60 60

Subtask 1B Survey 60 60

Subtask 1C Geotech 60 60

Subtask 2: 60% plans 30 - includes 7 days for Client review

Subtask 3: 100% plans 30 – includes 7 days for Client review

Subtask 4A: Permit applications 30 – includes 7 days for Client review

Subtask 4B: Permit approvals 60 – includes response for additional information

Subtask 5: Prebid 30 210

Subtask 6A - Pre construction 30 240

Subtask 6B: Review Submittals 30 270

Subtask 6C: Respond to Contractor RFI's

180 (Est max overall calendar days;

RFI's will be responded to within 7 days of receipt from Contractor)

Subtask 6D: Provide Construction Inspections w/ (Month 1)

30 330

Subtask 6E: Provide Construction Inspections w/ Report (Month 2)

30 360

Summary of Fees:

Subtask 6F: Provide Construction Inspections w/ Report (Month 3)

30 390

Subtask 6G: Provide Construction Inspections w/ (Month 4)

30 420

Subtask 6H: Provide Construction Inspections w/ Report (Month 5)

30 450

Subtask 6I: Provide Construction Inspections w/ (Month 6)

30 480

Subtask 6J: Substantial Completion Walk-Through w/Punchlist

30 510

Subtask 6K: Final Completion w/ Certification

30 540

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1A Preliminary $24623.75 $0.00

Subtask 1B Survey $16147.96 $0.00

Subtask 1C Geotech $6272.80 $0.00

Subtask 2: 60% plans $25228.75 $0.00

Subtask 3: 100% plans $17148.75 $182.20

Subtask 4A Permit applications $14160.00 $2495.00

Subtask 4B Permit approvals $3395.00 $0.00

Subtask 5 Pre-Bid $3520.00 $0.00

Total Design & Permitting $110497.01 $2677.20

Subtask 6A - Pre-Construction Meeting

$2080.00 $0.00

Subtask 6B - Submittal Review $2680.00 $35.00

Subtask 6C Assistance during construction

$2520.00 $0.00

Subtask 6D Inspection 1 $1007.50 $0.00

Subtask 6E Inspection 2 $1007.50 $35.00

Subtask 6F Inspection 3 $1007.50 $35.00

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

Subtask 6G Inspection 4 $1007.50 $35.00

Subtask 6H Inspection 5 $1007.50 $35.00

Subtask 6I Inspection 6 $1007.50 $35.00

Subtask 6J Substantial Completion

$1805.00 $35.00

Subtask 6K Final Completion $1380.00 $35.00

Total during Construction $16510.00 $280.00

Total Fixed Price Cost: $127007.01

Total Fixed Price Cost: $2957.20

Overall Total Cost: $129964.21

Labor Rate Category Base Hourly Rate

(Direct) Audited OH &

Benefits % Direct Cost

FCCM % Operating

Allowance FCW Billing

Rates 100.00% 166.68% 7.89% 2.70% 15.00% 292.27%

2.92

Land Surveying Division Director/Professional Surveyor & Mapper $66.12 $110.21 $5.22 $1.79 $9.92 $193.07

Senior Project Manager $57.35 $95.59 $4.52 $1.55 $8.60 $167.46

Professional Surveyor & Mapper $56.14 $93.57 $4.43 $1.52 $8.42 $163.93

Chief of Surveyors/Project Surveyor $25.60 $42.67 $2.02 $0.69 $3.84 $74.75

2-Man Field Crew $43.91 $73.19 $3.46 $1.19 $6.59 $128.22

3-Man Field Crew $60.80 $101.34 $4.80 $1.64 $9.12 $177.54

GPS Field Operator/Robotics(1 man) $25.23 $42.05 $1.99 $0.68 $3.78 $73.67

Field Technician $21.73 $36.22 $1.71 $0.59 $3.26 $63.45

All Divisions Principals/Vice Presidents $89.96 $149.95 $7.10 $2.43 $13.49 $262.68

Senior CADD/GIS Designer $35.32 $58.87 $2.79 $0.95 $5.30 $103.13

CADD DesignerII/GIS Designer $28.35 $47.25 $2.24 $0.77 $4.25 $82.78

CADD DesignerI/GIS Technician $26.56 $44.27 $2.10 $0.72 $3.98 $77.56

Project Assistant/Administrative Assistant $24.13 $40.22 $1.90 $0.65 $3.62 $70.46

Certified True & Correct

John Howard Vice President of Finance + Operations 2/8/23

Causseaux, Hewett, & Walpole, Inc.

dba CHW Civil Engineering, Planning, Permitting, Surveying and Mapping, Construction Management and Inspection

Total Multiplier 2.92

Proposal Koreshan SP Campground_REV 1_5.10.2023.pdf
TA Form - Koreshan.pdf

File details come from the government source that posted it. Updated .