This is a Task Assignment Change Order Form submitted by Weiler Engineering Corporation to the Florida Department of Environmental Protection (FDEP) for the Dade Battlefield Historic State Park Lodge Roof Replacement project. The change order was executed in December 2023 and approved by all required signatories, including the FDEP Budget Representative, Project Manager, Contract Manager, and Contract Authority, along with the consultant representative.

The change order is a time-only extension with no additional cost to FDEP. The original task end date of December 31, 2022, was extended by 183 days to June 30, 2024, to allow sufficient time for construction completion and construction administration services. The task maintains its total cost of $15,661.76, comprised of $48.80 in reimbursement and $15,612.96 in fixed fees. The contract number is CN230, Task Assignment Number 42, Project Number 61357C, and the FDEP Contract Manager is Ralph Perkins. Weiler Engineering's Project Manager, Robin Palmer, P.E., requested this extension on December 7, 2023, to accommodate the ongoing construction schedule.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T21CO1.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
CN-370000-CN230-T34CO1.pdf PDF
CN-370000-CN230-T37.pdf PDF
CN-370000-CN230-T37CO1.pdf PDF
CN-370000-CN230-T42CO1.pdf PDF
CN-370000-CN230-T43.pdf PDF
CN-370000-CN230-T44.pdf PDF
CN-370000-CN230-T48.pdf PDF
CN-370000-CN230-T51CO2.pdf PDF
CN-370000-CN230-T54CO1.pdf PDF
CN-370000-CN230-T58.pdf PDF
CN-370000-CN230-T63.pdf PDF
CN-370000-CN230-T65.pdf PDF
CN-370000-CN230-T67.pdf PDF
CN-370000-CN230-T6CO1.pdf PDF
CN-370000-CN230-T72CO1.pdf PDF
CN-370000-CN230-T74.pdf PDF
CN-370000-CN230-T81.pdf PDF
CN-370000-CN230-T81CO1.pdf PDF
CN-370000-CN230-T82.pdf PDF
CN-370000-CN230-T83.pdf PDF
CN-370000-CN230-T84.pdf PDF
CN-370000-CN230-T85.pdf PDF
CN-370000-CN230-T88.pdf PDF
CN-370000-CN230-TA31.pdf PDF
CN-370000-CN230-TA5.pdf PDF
PC-370000-CN230.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN230 42 3 61357C

Dade Battlefield Historic State Park Lodge Roof Replacement

Weiler Engineering

Jeff Weiler 941-505-1700 weiler7@mac.com

Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov

183-day time-only extension request to utilize Construction Administration services.

$ 48.80 $ 15,612.96 $ 15,661.76 $ 48.80 $ 15,612.96 $ 15,661.76 $ 0.00 $ 0.00 $ 0.00 $ 48.80 $ 15,612.96 $ 15,661.76

03/04/2022

12/31/2022

12/31/2023

6/30/2024

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.12.13 15:40:56 -05'00'

Jasper Gebhardt Jasper Gebhardt Digitally signed by Jasper Gebhardt Date: 2023.12.14 10:27:26 -05'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.12.14 16:41:10 -05'00'

Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.12.15 08:33:22 -05'00'

Michael W. Foster, Jr. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.12.19 08:54:28 -05'00'

$ 0.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

December 7, 2023

Jasper Gebhardt Construction Project Manager

Bureau of Design and Construction Florida Department of Environmental Protection 407-752-0231

Re: Dade Battlefield Historic State Park Lodge Roof Replacement FDEP Contract No: CN230 Task Assignment No: 42, Project No: 61357C

Mr. Gebhardt, We are requesting a time extension for the Dade Battlefield Historic State Park Lodge Roof Replacement project. This extension would be at no additional cost to the FDEP. The current contract expires on 12/31/2023. We are requesting an extension until 06/30/2024 to allow enough time for the construction to be completed.

If you have any questions, or require additional information, please do not hesitate to contact me at (941) 505-1700 or electronically at rpalmer@weilerengineering.org.

Sincerely, Robin Palmer, P.E.

Project Manager Weiler Engineering Corporation