This is a Task Assignment Notification Form and accompanying proposal from the Florida Department of Environmental Protection (FDEP) for construction phase engineering services at Bahia Honda State Park. The contract involves FDEP as the owner, Weiler Engineering Corporation as the consultant, and Jack Brady as the FDEP Contract Manager. The project is located at Bahia Honda State Park and concerns the replacement of bathhouse and restroom facilities. The task assignment is designated as TA23 under FDEP Contract Number CN230, with Project Number 61501.
The scope of work encompasses construction administration services including attending a pre-construction meeting, reviewing contractor submittals, responding to building department comments, processing contractor requests for information, providing eight monthly construction inspections with certified reports, and attending substantial completion and final completion walk-throughs with certification. The contract is structured as a fixed-price engagement with a total contract value of $13,904.25, comprised of $13,085.00 in fixed price costs and $819.25 in reimbursable expenses. The project start date is upon execution, with a completion date of September 1, 2020. Payment will be made upon FDEP approval of deliverables for each subtask. The proposal includes contingency subtasks for additional building department responses and contractor RFI processing, to be utilized only with prior approval from the FDEP Project Manager.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WEILER ENGINEERING CORPORATION EB-6656 - ENGINEERING SERVICES INCLUDE CIVIL I LANO DEVELOPMENT j WATERFRONl
\ ~ Jx ~lence in engineering
\ y I ....... I RESORTS I UTJLITlES I MUNICIPALGOVERNMENT I STRUCTURAL I MINING I GIS-GPS
_1 I I .'_/
May 3, 2018 (Revision 1-June 21, 2018)
Ms. Laura Ross Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260A, MS 520 Tallahassee, FL 32399
RE: Bahia Honda State Park Restrooms Replacement- CN 230, Task OS WEC Number 18045.006
Dear Ms. Ross;
Thank you for the opportunity to provide this proposal to provide Construction Phase Services necessary to construct the new restroom facilities in Bahia Honda State Park. WEC is currently working on the design and permitting for the new facilities, which included Subtasks 1 through 4. Our services during the construction phase will include the following:
I. Attend Pre-Construction meeting;
II. Review Contractor submittals;
Ill. Respond to RFl's;
IV. Provide monthly Construction Inspections and Reports per FDEP CCCL requirements V. Attend Substantial Completion and Final Completion in order to certify completion of construction as required by FDEP CCCL.
Enclosed is a proposal summary and man-hour documentation for these services and subtasks identified below. Please review the attached Proposal Summary and deliverables.
Sincerely, .,;-·7 -, /
~·'r'/1 '·"" <r·· >" u·.z,.,e,_
R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289-4161 I FAX 305-289-4162
WF INVITF YOU TO VISIT OUR WFB SITE AT WWW.WFILERENGINFFRING.ORG OR FMAIL US AT INFO@WFILFRFNGINFFRING.ORG
Construction Phase Services for New Elevated Restroom at Bahia Honda State Park
Contract Number CN230
Subtask SA - SP: Construction Phase Services
Description: WEC staff will assist Client with engineering representation at eleven (11) meetings and/or inspections during the course of construction. These include one (1) Pre Construction meeting, one (1) Substantial Completion walk-through/meeting, and one (1) Final Completion walk-through/meeting. Upon Contractor's submittal to Monroe County Building Department and receipt of comments, WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments. If additional revisions to plans are required based on Building Department comments, WEC will revise the plans accordingly and re-deliver five (S) sets of the revised 100% Plans along with digital version as PDF. WEC anticipates Building Department comments will be addressed within Subtask SC, Block 1 level of effort. However, in the event that Building Department comments require more extensive revisions Subtask SD Block 2 level of effort is included as contingency that can be utilized if determined to be necessary and with prior approval from the FDEP Project Manager. WEC will also provide up to eight (8) monthly inspections, with certified report during construction. WEC will also provide engineering review of Contractor's shop drawing submittals as well as assist Client with responses to Contactor's RFl's. Subtask SE Block 1 is intended to cover typical RFl's, with Subtask SF Block 2 intended as contingency level of effort to allow for processing of additional RFl's and/or those involving field engineering, plans deviations, unanticipated site conditions, and similar situations which can be utilized if determined to be necessary and with prior approval from the FDEP Project Manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Subtask SA: Attend Pre-Construction Meeting
Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Fixed Price Cost:
I subtask SA
PUNTA GORDA OFFICE: 201 WEST MARION AVENGE- SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 ·1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289-4161 I FAX 305 -289-4162
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer Cross-Out Completed
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160.00 Principal in Charge 195 o 0.00
Registered Professional Engineer 145 0 0.00
Registered Engineer Intern 115 8 920.00
Senior Engineering Designer 100 0 0.00
Engineering Technician 80 0 0.00
Clerical 55 0 0.00
Total 2,080.00
Reimbursable Cost:
Postage Not anticipated
Printing 120 sheets @ $2.30 per sheet= $276 (additional plans sets if requested)
Overnight Travel (if applicable} Not anticipated
Mileage(@ $OA45 per mile} $266.11
Reimbursable Total Cost $542.11
Subtask SA Subtotal: $2622.11
Subtask SB: Review Contractor submittals
Deliverable: WEC will review and comment on Contractor submittal package within 14 days of receipt, and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Fixed Price Cost:
Subtask SB
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 o 0.00
Registered Engineer Intern 115 8 920.00
Senior Engineering Designer 100 12 1,200.00
Engineering Technician 80 2 160.00
Clerical 55 2 110.00
Total 2,680.00
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHO N I FL 33050 I TEL 305 -289-4161 I FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer Cross-Out Completed rpalmer
Reimbursable Cost:
Postage 3 Fed-x at $35 = $105
Printing Not anticipated (all deliverables in digital form only)
Overnight Travel (if applicable) Not anticipated Mileage(@ $0.445 per mile) Not anticipated
Reimbursable Total Cost $105.00
Subtask SB Subtotal: $2,785.00
Subtask SC: Respond to Building Department comments - Block 1
Deliverable: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Fixed Price Cost:
Subtask SC
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager ' 145 2 290.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 ' 1 I 145.00
Registered Engineer Intern 115 6 ! 690.00
Senior Engineering Designer 100 8 ' 800.00
Engineering Technician 80 0 I 0.00
Clerical 55 1 55.00
Total i 1,980.00
Reimbursable Cost:
Postage 3 Fed-x at $35 = $105
Printing 120 sheets @ $2.30 per sheet $276
Overnight Travel Not anticipated
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE-SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY i MARATHON I FL 33050 I TEL 305 -289-4161 [ FAX 305 -289-416 2
WE INVITE YOU TO V!SIT OUR WEB SITE AT www.wmERENGINEERING.ORG OR EMAIL us AT !NFO@WEILERENGINEERING.ORG rpalmer
(if applicable)
Mileage(@ $0.445 per mile) 58 miles Monroe County Building Dept $25.81
Reimbursable Total Cost $406.81
Subtask SC Subtotal: $2386.81
Subtask SD: Respond to Building Department comments - Block 2 (if required)
Deliverable: If work on this Subtask is required, WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments. Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Fixed Price Cost:
Subtask 8D Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Weiler Engineering Project Manager 145 2 290.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 .5 72.50
Registered Engineer Intern 115 4 460.00
Senior Engineering Designer 100 8 800.00
Engineering Technician 80 0 0.00 Clerical 55 1 55.00 Total 1,677.50
Reimbursable Cost:
Postage 3 Fed-x at $35 = $105 (if required)
Printing 120 sheets @ $2.30 per sheet $276 (if required) Overnight Travel Not anticipated
(if applicable) Mileage(@ $0.445 per mile) 58 miles R/T (Bldg Dept) @ 0.445 = $25.81 (if required)
Reimbursable Total Cost $406.81
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE -SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289-4161 I FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer Cross-Out Completed rpalmer Cross-Out Completed rpalmer i
Subtask SD Subtotal: $2084.31
Subtask SE: Respond to Contractor RFl's - Block 1
Deliverable: WEC will respond to RFl's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Fixed Price Cost:
Subtask SE
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 I 290.00
Principal in Charge 195 0 1 0.00
Registered Professional Engineer 145 2 290.00
Registered Engineer Intern 115 8 ! 920.00
Senior Engineering Designer 100 J8 800.00
Engineering Technician 80 0 0.00
Clerical 55 4 220.00
Total i 2,520.00
Reimbursable Cost:
Postage Not anticipated
Printing Not anticipated (all deliverables in digital form only)
Overnight Travel (if applicable} Not anticipated
Mileage(@ $0445 per mile) Not anticipated
Reimbursable Total Cost $0.00
Subtask 8E Subtotal: $2520.00
Subtask SF: Respond to Contractor RFl's - Block 2 (if required)
Deliverable: If work on this Subtask is required, WEC will respond to RFl's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE· SUITE :306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFF,CE: 6805 OVERSEAS HIGHWAV ! MARATHON I FL 33050 I TEL 305 -289-4161 ! FAX 305 -289-4162
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT iNFO@WEILERENGI NEERING.ORG rpalmer
Fixed Price Cost:
Subtask SF
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Weiler Engineering Project Manager 145 2 290.00
Principal in Charge 195 0 0.00 Registered Professional Engineer 145 .5 72.50 Registered Engineer Intern 115 4 460.00
Senior Engineering Designer 100 8 800.00 Engineering Technician 80 0 0.00 Clerical 55 1 55.00 Total 1,677.50
Reimbursable Cost:
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable) Not anticipated
Mileage(@ $0.445 per mile) Not anticipated
Reimbursable Total Cost $0.00
Subtask SF Subtotal: $1677.5
Subtask SG: Provide Construction Inspections (Month 1)
Deliverable: WEC will provide a monthly inspection (NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 5G
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00
Principal in Charge 195 0 0.00 Registered Professional Engineer 145 .5 72.50
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY J MARATHON I FL 33050 I TEL 305 -289-4161 J FAX 305 -289-4162
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer
I
Registered Engineer Intern 115 6 ! 690.00
Senior Engineering Designer 100 1 I 100.00
Engineering Technician 80 0 ! 0.00
Clerical 55 0 1 0.00 Total j 1,007.50
I
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35
Printing Not anticipated Overnight Travel (ff applicable) Not anticipated Mileage(@ $0.445 per mile) 58 miles R/T@ 0.445 = $25.81 Reimbursable Total Cost $60.81
Subtask SG Subtotal: $1068.31
Subtask SH: Construction Inspection (Month 2)
Deliverable: WEC will provide a monthly inspection (NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask SH
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00 Principal in Charge 195 0 0.00
Registered Professional Engineer 145 .5 72.50
Registered Engineer Intern 115 6 690.00 Senior Engineering Designer 100 1 100.00
Engineering Technician 80 0 0.00
Clerical 55 0 0.00
Total 1,007.50
Reimbursable Cost:
PUNTA GORDA OFFICE: 201 WEST ~ARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I EL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFF:CE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 j TEL 305 -289-4161 I FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB S!TE AT WWW.WEILEl'{ENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer Cross-Out Completed rpalmer
Postage 1 Fed-x at $35 = $35
Printing Not anticipated
Overnight Travel (if applicable) Not anticipated
Mileage(@ $0.445 per mile) $25.81
Reimbursable Total Cost $60.81
Subtask SH Subtotal: $1068.31
Subtask 51: Construction Inspection (Month 3)
Deliverable: WEC will provide a monthly inspection (NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask SI
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 .5 72.50
Registered Engineer Intern 115 6 690.00
Senior Engineering Designer 100 1 100.00
Engineering Technician 80 0 0.00
Clerical 55 0 0.00
Total 1,007.50
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35
Printing Not anticipated
Overnight Travel (if applicable) Not anticipated
Mileage(@ $0.445 per mile) 58 miles $25.81
Reimbursable Total Cost $60.81
Subtask 51 Subtotal: $1068.31
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289-4161 I FAX 305 -289-4162
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer
I i
Subtask SJ: Construction Inspection (Month 4)
Deliverable: WEC will provide a monthly inspection (NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask SJ
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00 Principal in Charge 195 0 0.00 Registered Professional Engineer 145 .s 72.50 Registered Engineer Intern 115 6 690.00 Senior Engineering Designer 100 1 100.00 Engineering Technician 80 iO 0.00 Clerical 55 ·o 0.00 Total 1,007.50
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35 Printing Not anticipated Overnight Travel (if applicable) Not anticipated Mileage(@ $0.445 per mile) 58 miles $25.81 Reimbursable Total Cost $60.81 ;
Subtask SJ Subtotal: $1068.31
Subtask SK: Construction Inspection (Month 5)
Deliverable: WEC will provide a monthly inspection (NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
PUNTA GORDA OF:'ICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY j MARATHON I FL 33050 ; TEL 305 -289-4161 I FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERiNG.ORG rpalmer
Subtask SK Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Weiler Engineering Project Manager 145 1 145.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 .5 72.50
Registered Engineer Intern 115 6 690.00
Senior Engineering Designer 100 1 100.00
Engineering Technician 80 0 0.00
Clerical 55 0 0.00
Total 1,007.50
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35 Printing Not anticipated Overnight Travel ( if applicable) Not anticipated Mileage(@ $0.445 per mile) 58 miles $25.81 Reimbursable Total Cost $60.81
Subtask SK Subtotal: $1068.31
Subtask SL: Construction Inspection (Month 6)
Deliverable: WEC will provide a monthly inspection {NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask SL
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 .5 72.50 Registered Engineer Intern 115 6 690.00 Senior Engineering Designer 100 1 100.00 Engineering Technician 80 0 0.00 Clerical 55 0 0.00
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE· SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289 - 4161 I FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer
I Total 1,007.50
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35
Printing Not anticipated Overnight Travel (if applicable) Not anticipated Mileage(@ $0.445 per mile) 58 miles $25.81
Reimbursable Total Cost $60.81
Subtask SL Subtotal: $1068.31
Subtask SM: Construction Inspection (Month 7}
Deliverable: WEC will provide a monthly inspection (NLT every 30 days} during construction.
WEC will provide two (2} original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask SM
Firm Name Position Classification 1 Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 l 145.00 Principal in Charge 195 0 0.00 Registered Professional Engineer 145 .5 j 72.50 Registered Engineer Intern 115 6 I 690.00 I
Senior Engineering Designer 100 1 100.00 Engineering Technician 80 0 0.00
Clerical 55 0 0.00
Total ' 1,007.50
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35
Printing Not anticipated OvernightTravel (if applicable) Not anticipated Mileage(@ $0.445 per mile) 58 miles $25.81
PU :'-JTA GORDA OFFICE: 201 WEST MARION AVE1\UE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289-4161 I FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
I Reimbursable Total Cost 1 $60.81
Subtask SM Subtotal: $1068.31
Subtask SN: Construction Inspection {Month 8)
Deliverable: WEC will provide a monthly inspection (NLT every 30 days) during construction.
WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask SN Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 1 145.00 Principal in Charge 195 0 0.00
Registered Professional Engineer 145 .5 72.50 Registered Engineer Intern 115 6 690.00
Senior Engineering Designer 100 1 100.00 Engineering Technician 80 0 0.00
Clerical 55 0 0.00
Total 1,007.50
Reimbursable Cost:
Postage 1 Fed-x at $35 = $35
Printing Not anticipated OvernightTravel (if applicable) Not anticipated
Mileage(@ $0.445 per mile) 58 miles $25.81
Reimbursable Total Cost $60.81
Subtask SN Subtotal: $1068.31
Subtask 80: Substantial Completion Walk-Through w/Punchlist
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 -289-4161 I FAX 305 -289-4162
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Deliverable: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist. WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.
Fixed Price Cost:
Subtask 50 Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Weiler Engineering Poject Manager 145 6 870.00
Principal in Charge 195 0 0.00 Registered Professional Engineer 145 1 145.00
Registered Engineer Intern 115 6 690.00
Senior Engineering Designer 100 1 100.00
Engineering Technician 80 0 0.00 Clerical 55 0 I 0.00 I
Total 1,805.00
Reimbursable Cost:
Postage 2 Fed-x at $35 = $70
Printing Not anticipated Overnight Travel (if applicable) Not anticipated Mileage(@ $0.445 per mile) 58 miles $25.81
Reimbursable Total Cost $95.81
Subtask 50 Subtotal: $1900.81
Subtask SP: Final Completion w/ Certification
Deliverable: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection. WEC will also provide complete the final completion certification form required by FDEP Project Manager.
Fixed Price Cost:
Subtask SP Firm Name I Position Classification
I Hourly Rate I Hours I Total Fixed Price
Cost
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE-SUITE 1306 I PUNTA GORDA I FL 33950 ! TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6 8 05 OVERSEAS HIGHWAY I MARATHON I FL 33050 I TEL 305 - 289-4161 I FAX 305 -289-4162
WE iNVITE YOU TO ViSIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Weiler Engineering Poject Manager 145 2 290.00
Principal in Charge 195 0 0.00
Registered Professional Engineer 145 1 145.00
Registered Engineer Intern 115 6 690.00
Senior Engineering Designer 100 2 200.00
Engineering Technician 80 0 0.00
Clerical 55 1 55.00
Total 1,380.00
Reimbursable Cost:
Postage 3 Fed-x at $35 = $105
Printing Not anticipated
Overnight Travel (if applicable) Not anticipated
Mileage(@ $0.445 per mile) 58 miles $25.81 Reimbursable Total Cost $130.81
Subtask SP Subtotal: $1510.81
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY I MARATHON [ FL 33050 [ TEL 305 -289-4161 I FAX 305 -289-4162
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Project Schedule:
Activity Duration (Calendar Days) Dates
Subtask SA-SP: Construction Phase Services Subtask SA: Attend Pre-Con Mtg NTP for Subtask 5 + 1 day
Subtask SB: Review Submittals 240 (Est max overall calendar days;
submittals will be reviewed within 7 days of receipt from Contractor)
Subtask SC: Respond to Bldg Dept 60 (concurrent with SB) RAl's - Block 1 Subtask SD: Respond to Bldg Dept 0 (concurrent w/ SC if required) RAl's - Block 2 (if required)
Subtask SE: Respond to Contractor 240 (Est max overall calendar days;
RFl's - Block 1 RFl's will be responded to within 7 days of receipt from Contractor)
Subtask SF: Respond to Contractor 0 (concurrent w/ SE if required) RFl's - Block 2 (if required)
Subtask SG: Provide Construction 30 Inspections w/ (Month 1) Subtask SH: Provide Construction 60 Inspections w/ Report (Month 2) i Subtask 51: Provide Construction I inspections w/ Report (Month 3)
! Subtask SJ: Provide Construction 120 ' Inspections w/ (Month 4)
Subtask SK: Provide Construction 150 Inspections w/ Report (Month 5) Subtask SL: Provide Construction 180 Inspections w/ (Month 6) Subtask SM: Provide Construction 210 !
Inspections w/ (Month 7) Subtask SN: Provide Construction 240 Inspections w/ (Month 8) Subtask 50: Substantial 242
1 Completion Walk-Through w/Punchlist
Subtask SP: Final Completion w/ 270 Certification
Summary of Fees:
PUNTA GORDA OFrlCE: 201 WEST MARION AVENUE - SUITE 1306 I PUNTA GORDA J FL 33950 I TEL 941-505 -1700 I FAX 941-505 -1702
MARATHON OFFiCE: 6805 OVERSEAS HIGHWAY I MARATHON I FL 33050 ! TEL 305 -289-4161 i FAX 305 -289-4162
WE INVITE YOU TO V!SIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
I
I rpalmer Cross-Out Completed rpalmer Cross-Out Completed rpalmer Cross-Out Completed rpalmer
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask SA-SP: Construction Phase
Services
Subtask SA: Attend Pre-Con Mtg 2080.00 542.22
Subtask SB: Review Submittals 2,680.00 105.00
Subtask SC: Respond to Bldg Dept RAl's - 1,980.00 402.54
Block 1
Subtask SD: Respond to Bldg Dept RAl's 1,677.50 402.54
- Block 2 (if required)
Subtask SE: Respond to Contractor RFl's 2,S20.00 0.00
- Block 1
Subtask SF: Respond to Contractor RFl's 1,677.50 305.10
- Block 2 (if required)
Subtask SG: Provide Construction 1,007.50 60.81
Inspections w/ {Month 1)
Subtask SH: Provide Construction 1,007.50 60.81
Inspections w/ Report (Month 2)
Subtask 51: Provide Construction 1,007.50 60.81 Inspections w/ Report (Month 3)
Subtask SJ: Provide Construction 1,007.50 60.81
Inspections w/ (Month 4)
Subtask SK: Provide Construction 1,007.50 60.81 Inspections w/ Report (Month 5)
Subtask SL: Provide Construction 1,007.S0 60.81
Inspections w/ (Month 6)
Subtask SM: Provide Construction 1,007.50 60.81
Inspections w/ (Month 7)
Subtask SN: Provide Construction 1,007.50 60.81
Inspections w/ (Month 8)
Subtask 50: Substantial Completion 1,805.00 95.81
Walk-Through w/Punchlist
Subtask SP: Final Completion w/ 1,380.00 130.81
Certification
Total Cost: 13,085.00 819.25
Overall Total Cost: $13,904.25
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE· SUITE 1306 I PUNTA GORDA I FL 33950 I TEL 941-505 -1700 I FAX 941·505-1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY / MARATHON / FL 33050 / TEL 305 -289-4161 / FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG rpalmer Cross-Out Completed rpalmer Cross-Out Completed rpalmer