This Task Assignment Notification Form (TA84) is issued by the Florida Department of Environmental Protection (FDEP) under Contract CN230 with Weiler Engineering Corporation to provide design and construction administration services for historic preservation work at Yulee Sugar Mill Ruins Historic State Park. The contract is managed by FDEP's Bureau of Design and Construction, with Ralph Perkins serving as the FDEP Contract Manager and Richard Marcil as the Project Manager. Robin Palmer, P.E., represents Weiler Engineering as the Consultant Representative.
The scope of work encompasses design services for the preservation of historic ruins at the Yulee Sugar Mill, including site inspection, structural restoration plans at 30%, 60%, and 100% design phases, and construction administration services (Subtasks 4A-4G). Design deliverables include plans, specifications, opinions of probable cost, and detail sheets addressing restoration of the Kettle Train, Boiler, Rolling Press, and Well. Construction phase services include assistance during bidding, pre-construction meeting attendance, contractor submittal review, RFI responses, interim site inspections, and substantial and final completion certifications. The fixed price for design services is $33,266.25, with construction administration services (Subtasks 4A-4G) totaling $13,182.50 but not activated upon execution. The overall total contract amount is $46,448.75 with no reimbursable costs. The project completion date is April 29, 2025, and payment is made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 TA84 FDEP 61543
Historic Ruins Preservation
Weiler Engineering
Robin Palmer, P.E. (941) 916-0291 rpalmer@weilerengineering.org
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Design services for the preservation of the historic ruins per the attached dated September 19, 2024. The fixed price for construction administration services is included (Subtasks 4A-4G), but NOT to be activated with this TA's execution.
Richard Marcil or successor
Upon Execution $ 33,266.25 April 29, 2025 $ 0.00
$ 33,266.25
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.10.02 15:43:21 -04'00'
Richard Marcil Richard Rene Marcil, III
Digitally signed by Richard Rene Marcil, III Date: 2024.10.02 15:51:39 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.10.03 14:44:27 -04'00'
R. Jeff Weiler, P.E. Jeff Weiler Digitally signed by Jeff Weiler Date: 2024.10.18 15:36:56 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2024.10.28 09:36:06 -04'00'
61543 37502000017 100718/00 675005 U1300 131500 X2 $ 33,266.25
$ 33,266.25
Yulee Sugar Mill Ruins Historic State Park
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
January 4, 2023- Revision 3: September 19, 2024
Mr. Richard Marcil
Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3900 Commonwealth Boulevard 260-L, MS 520
Tallahassee, FL 32399
RE: Yulee Mill Ruins State Park – Historic Preservation, CN - 230, TA - 84
Dear Mr. Marcil, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to provide reports, plans, and permits to perform Historic Preservation services on the
Sugar Mill.
1. Site Inspection to determine structural integrity of the structure.
2. 60% Structural Restoration Plans.
• Kettle Train (#5 on Exhibit Below)
• Remove sod and soil to expose grate + add a product/treatment to the grate to protect it.
• Flue is to remain as-is. No work is proposed on the flue.
• Boiler (#1 on Exhibit Below)
• Add structural support to the boiler to keep boiler, boiler run, stonework.
• Add a grate to prevent visitors from climbing into boiler run., and stack component intact.
• Replace any bricks with matching, local stonework.
• Rolling Press (#2 on Exhibit Below)
• Remove stone façade and add an access hole to allow inspections, maintenance, and air flow using a metal grate and lock. (Access hole should not be on the roadside face).
• Remove 1 face of façade and aging wooden structure. Replacement stabilization with cast-in-place foundation.
Yulee Sugar Mills Restoration
CN 230/TA84
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
• Well (#4 on Exhibit Below)
• Add a grate for protection using a heavy-duty metal grate similar to other locations.
3. 100% Structural Restoration Plans
CN 230/TA84
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Areas that do NOT require any attention at this time:
• Steam Well (#3)
• Cooling Vat (#6)
• Engine (#7)
• Stack (#8)
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
CN 230/TA84
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Yulee Ruins State Park
Sugar Mill Restoration
Contract Number 230, Task Assignment Number 84
Subtask 1: Preliminary 30% Design
Description: Plans completed to 30% incorporating comments from preliminary investigation and report.
1) A - Preliminary investigation,
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Local Building
Department.
c) Consultant will prepare a report identifying our findings and observations and a preliminary Opinion of Probable Cost.
Deliverable:
1) A - Preliminary investigation, Report and preliminary Opinion of Probable Cost electronically in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
Subtask 1: Preliminary 30% Design
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price
Cost
Weiler Engineering
Project Manager 145 8 1,160.00
Principal in Charge 195 .25 48.75
Registered Professional Engineer
145 8 1,160.00
Registered Engineer Intern 115 24 2,760.00
Senior Engineering Designer 100 16 1,600.00
Engineering Technician 80 16 1,280.00
Clerical 55 2 110.00
Total 8,118.75
Subtask 2: 60% Design
Description: Plans completed to 60% incorporating comments from preliminary investigation and report.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost
Cover sheet
Plan Sheet Identifying the General Location of the Mill and Facilities
Larger Scale Sheets Identifying Kettle Train, Boiler, Rolling Press, and Well with damaged areas and specific repairs
Details
General Notes
CN 230/TA84
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
Subtask 2: 60% Design
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 13 1,885.00
Principal in Charge 195 .25 48.75
Registered Professional Engineer
145 11 1,595.00
Registered Engineer Intern 115 18 2,070.00
Senior Engineering Designer 100 45 4,500.00
Engineering Technician 80 61 4,880.00
Clerical 55 2 110.00
Total 15,088.75
Subtask 3: 100% Design
Description: Plans completed to 100% incorporating comments from 60%.
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only) including:
Opinion of Probable Cost
Cover sheet
Plan Sheet Identifying the General Location of the Mill and Facilities.
Larger Scale sheets identifying Kettle Train, Boiler, Rolling Press, and Well with damaged areas and specific repairs
Details
General Notes
Specifications
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
Subtask 3: 100% Design
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 8 1,160.00
Principal in Charge 195 .25 48.75
Registered Professional
Engineer
145 8 1,160.00
Registered Engineer Intern 115 12 1,380.00
Senior Engineering Designer 100 30 3,000.00
Engineering Technician 80 40 3,200.00
Clerical 55 2 110.00
Total 10,058.75
Subtask 4A – 4G: Construction Phase Services **(Note: Not activated until the construction is funded)**
Subtask 4A: Assistance During Bidding
Description: WEC will provide assistance during the bidding process. Responses to the FDEP on bidder RFIs will be responded to within 7 days.
Deliverable: Responses to bidder questions will be provided in PDF format to the FDEP Project
Manager within 7 days.
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
Subtask 4A: Assistance During Bidding
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 6 870.00
Weiler Engineering Senior Engineering Designer 100 4 400.00
Total 1,270.00
Subtask 4B: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project
Manager in Meeting Minutes.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4B: Attend Pre-Construction Meeting
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 8 1,160.00
Weiler Engineering Registered Engineer Intern 115 8 920.00
Total 2,080.00
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Subtask 4C: Review Contractor Submittals
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project
Manager within 7 days of final approvals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4C: Review Contractor Submittals
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290.00
Weiler Engineering Registered Engineer Intern 115 6 690.00
Weiler Engineering Senior Engineering Designer 100 8 800.00
Weiler Engineering Engineering Technician 80 2 160.00
Total 1,940.00
Subtask 4D: Respond to Contractor RFIs
Description: WEC will respond to RFIs from Contractor within 7 days throughout the course of the construction phase. If any plan changes are required, these changes will be completed within
14 days.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format within 7 days.
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
Subtask 4D: Respond to Contractor RFIs
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290.00
Weiler Engineering Registered Professional
Engineer
145 2 290.00
Weiler Engineering Registered Engineer Intern 115 6 690.00
Weiler Engineering Senior Engineering Designer 100 6 600.00
Weiler Engineering Clerical 55 1 55.00
Total 1,925.00
Subtask 4E: Interim Site Inspection
Description: WEC will provide an interim inspection during construction upon request from BDC.
Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format.
The inspection report will be submitted within 3 days of the site visit.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4E: Interim Site Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 1 145.00
Weiler Engineering Registered Professional
Engineer
145 .5 72.50
Weiler Engineering Registered Engineer Intern 115 10 1,150.00
Total 1,367.50
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Subtask 4F: Substantial Completion w/ Certification
Description: WEC will assist Client with the Substantial Completion inspection, with WEC representative attending the Substantial Completion inspection with punchlist. WEC will assist the FDEP with any permit closeout.
Deliverable: WEC will provide complete the substantial completion certification form required by FDEP Project Manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4F: Substantial Completion w/ Certification
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 3 435.00
Weiler Engineering Registered Professional
Engineer
145 1 145.00
Weiler Engineering Registered Engineer Intern 115 8 920.00
Weiler Engineering Senior Engineering Designer 100 8 800.00
Total 2,300.00
Subtask 4G: Final Completion
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will provide a final completion inspection report to the FDEP Project Manager.
CN 230/TA84
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
Subtask 4G: Final Completion
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 3 435.00
Weiler Engineering Registered Professional
Engineer
145 1 145.00
Weiler Engineering Registered Engineer Intern 115 8 920.00
Weiler Engineering Senior Engineering Designer 100 8 800.00
Total 2,300.00
Project Schedule:
Activity Duration (Calendar Days) Days from Execution
Subtask 1: Preliminary 30%
Design
90 90
Subtask 2: 60% Design 45 - includes 7 days for Client review
Subtask 3: 100% Plans 45 – includes 7 days for Client review
Subtask 4A: Assistance
During Bidding
TBD TBD
Subtask 4B: Attend A Pre-
Construction Meeting
TBD TBD
Subtask 4C: Review
Contractor Submittals
TBD TBD
Subtask 4D: Respond to
Contractor RFIs
TBD TBD
Subtask 4E: Interim Site
Inspection
TBD TBD
Subtask 4F: Substantial
Completion w/ Certification
TBD TBD
Subtask 4G: Final Completion TBD TBD
CN 230/TA84
January 4, 2023- Revision 3: September 19, 2024
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1: Preliminary 30%
Design
$8,118.75 $0.00
Subtask 2: 60% Design $15,088.75 $0.00
Subtask 3: 100% Plans $10,058.75 $0.00
Total Design Cost: $33,266.25 $0.00
Subtask 4A: Assistance During
Bidding
$1,270.00 $0.00
Subtask 4B: Attend A Pre-
Construction Meeting
$2,080.00 $0.00
Subtask 4C: Review Contractor
Submittals
$1,940.00 $0.00
Subtask 4D: Respond to
Contractor RFIs
$1,925.00 $0.00
Subtask 4E: Interim Site
Inspection
$1,367.50 $0.00
Subtask 4F: Substantial
Completion w/ Certification
$2,300.00 $0.00
Subtask 4G: Final Completion $2,300.00 $0.00
Total Construction Costs: $13,182.50 $0.00
Total Fixed Price Cost: $46,448.75
Total Fixed Price Cost: $0.00
Overall Total Cost: $46,448.75
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
**NOTE: Subtasks 4A - 4G are not yet activated**