CN-370000-CN230-T24.pdf
PDF 320 KB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
Summary
This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for design and permitting services related to restoration work at Bahia Honda State Park. The contract involves FDEP as the state agency owner and Weiler Engineering Corporation as the consulting firm, with Jeff Weiler, P.E., serving as the consultant representative and Philip Stone designated as the FDEP Contract Manager.
The scope of work encompasses design and permitting services for bathhouse building code renovations at the Sandspur Beach Campground, including hurricane-resistant upgrades (roof ties, wind calculations, upgraded roof systems for 180 mph wind code compliance), material selections (hurricane-rated doors, louvers, and Hardie board siding), electrical and plumbing modifications, and shoreline stabilization plans using No. 57 stone. The contract is structured in three subtasks: Subtask 1 (60% design documents at $15,245.00), Subtask 2 (100% design documents at $6,195.00 plus $197.00 reimbursable costs), and Subtask 3 (permitting applications and approvals totaling $2,867.00). The total task amount is $24,504.00, with a fixed price cost of $24,110.00 and cost reimbursement of $394.00. Work commenced upon execution and was scheduled for completion by December 31, 2020. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 24 FDEP 6I504
Bahia Honda State Park Sandspur Beach Campground Restoration
Weiler Engineering Corporation
Jeff Weiler, P.E. 941-505-1700 weiler7@mac.com
Philip Stone or successor 850-245-2570 Philip.Stone@FloridaDEP.gov
Consultant shall provide design and permitting services for the Bahia Honda State Park Sandspur Beach Campground Bathhouse building code renovations. See attached proposal dated 6/26/2020.
C Hewitt or successor
Upon execution $ 24,110.00 12/31/2020 $ 394.00
$ 24,504.00
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2020.07.08 15:51:15 -04'00'
C Hewitt C Hewitt Digitally signed by C Hewitt Date: 2020.07.09 14:20:58 -04'00'
Philip Stone P.T. Stone Digitally signed by P.T. Stone Date: 2020.07.09 18:02:55 -04'00'
Jeff Weiler, P.E. R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2020.07.10 10:22:01 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2020.07.13 13:24:47 -04'00'
6I504 FD073 37505000005 088130-18 675002 U3200 131500 XR $ 24,504.00
$ 0.00
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 M A RATH O N O FF ICE : 6805 O VERSEAS H IG H W AY | M ARATH O N | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
June 26, 2020
Mr. C. B. Hewitt Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260A, MS 520 Tallahassee, FL 32399
RE: Bahia Honda – Sandspur Campground Restoration CN 230 TA 24 – Change to bath house
Dear Mr. Hewitt;
Included, find the summary of man hours and fees to make the requested changes to the bath house for the above referenced project and revise the design for stabilization of the banks/shoreline.
Initially, our scope was to make recommendations for repairs of damage caused by Hurricane Irma. The Department wishes to make additional changes and modifications that have caused the value of improvements to exceed 50% and, as a consequence, will require additional design and permitting.
The plans for the bathhouse will generally include:
Hurricane ties for roof system Hurricane ties in walls to strap wall system to floor Wind calculations for cladding and roof Upgrades to the roof system for the 180 mph wind code Section detail for walls and possible anti-microbial foam insulation Interior FRP finish (per client request, not code) Selection of hurricane rated doors, louvers, cladding, etc. (Hardie board siding recommended) Electrical (Per Contractor’s comments provided by the FDEP) Plumbing (Per Contractor’s comments provided by the FDEP)
The plans for the shoreline will include plans and details to stabilize the shoreline utilizing No 57 Stone or similar.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
Mr. CB Hewitt June 8, 2020 Revision 1 – June 27, 2020 Bahia Honda – Sandspur Campground Bathhouse & Shoreline Modifications
The Weiler Engineering Corporation
Restroom & Parking Restoration Bahia Honda State Park
Sand Spur Campground Area Contract Number 230, Task Assignment Number 24
Subtask 1: 60% documents
Description: Plans completed to 60%.
Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:
Hurricane ties for roof system Hurricane ties in walls to strap wall system to floor Wind calculations for cladding and roof Upgrades to the roof system for the 180 mph wind code Section detail for walls and possible anti-microbial foam insulation Interior FRP finish (per client request, not code) Selection of hurricane rated doors, louvers, cladding, etc. (Hardie board siding recommended) Electrical (Per Contractor’s comments provided by the Client) Plumbing (Per Contractor’s comments provided by the Client)
And;
Plans outlining the location of the required stabilization Sections and details
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 1 195
Registered Professional Engineer 145 12 1740
Registered Engineer Intern 115 16 1840
Senior Engineering Designer 100 30 3000
Engineering Technician 80 90 7200
Clerical 55 2 110
Total 15,245
Total for Subtask 1: $15,245.00
Subtask 2: 100% documents
Description: Plans completed to 100%.
Deliverable: Consultant shall address BDC comments and deliver five sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Hurricane ties for roof system Hurricane ties in walls to strap wall system to floor Wind calculations for cladding and roof Upgrades to the roof system for the 180 mph wind code Section detail for walls and possible anti-microbial foam insulation Interior FRP finish (per client request, not code) Selection of hurricane rated doors, louvers, cladding, etc. (Hardie board siding recommended) Electrical (Per Contractor’s comments provided by the FDEP) Plumbing (Per Contractor’s comments provided by the FDEP)
And;
Plans outlining the location of the required stabilization Sections and details
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 870
Principal in Charge 195 1 195
Registered Professional Engineer 145 8 1160
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 10 1000
Engineering Technician 80 30 2,400
Clerical 55 2 110
Total $6,195
Reimbursable Cost:
Postage 3 Fed-x at $35 = $105 Printing 40 sheets @ $2.30 per sheet $92.00 Overnight Travel(if applicable) Not anticipated
Reimbursable Total Cost $197
Total for Subtask 2: $6,392.00
Subtask 3: Permitting
Description: Plans completed to 100% for Permit applications for County Building approval.
Deliverable:
3 A – Permit Applications, 14 days after receipt of Client review comments from 60% plans consultant shall deliver digital PDF and five original Signed and Sealed sets of permit applications with 100% plans.
3 B – Permit Approvals, Depends on agencies but anticipate 30 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation. All permits, plans and documentation will be provided via digital PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask3A Permit Applications
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 1 195.00
Registered Professional Engineer 145 1 145
Registered Engineer Intern 115 2 230
Senior Engineering Designer 100 1 100
Engineering Technician 80 4 320
Clerical 55 1 55
Total $1335.00
Subtask 3B Permit Approvals
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 1 195
Registered Professional Engineer 145 1 145
Registered Engineer Intern 115 2 230
Senior Engineering Designer 100 1 100
Engineering Technician 80 4 320
Clerical 55 1 55
Total $1335.00
Reimbursable Cost 3A Only:
Postage 3 Fed-x at $35 = $105 Printing 40 sheets @ $2.30 per sheet $92.00
Overnight Travel (if applicable)
Not anticipated
Reimbursable Total Cost $197.00
Total for Subtask 3: $2,867
Bahia Honda – Sandspur Campground Bathhouse & Shoreline Modifications
Project Schedule:
Activity Duration (Calendar Days) Dates/ Days Subtask 1 30 15 Subtask 2 30 15 Subtask 3 30 30
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1 $15,245.00 0 Subtask 2 $6195.00 $197.00 Subtask 3A $1335.00 $197.00 Subtask 3B $1335.00 0 Total $24,110.00 $394.00 Change Order Total $24,504.00
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)