Don Pedro Island State Park Visitor Dock Repairs - Task Assignment Summary

This is a Task Assignment Notification Form and detailed scope of work for design and permitting services issued by the Florida Department of Environmental Protection (FDEP). The document establishes Contract CN230, Task Assignment 37, between FDEP and Weiler Engineering Corporation to provide comprehensive engineering services for the repair and replacement of visitor docks at Don Pedro Island State Park. The project is managed by Wayne Thomas (FDEP Project Manager) and Robin Palmer (Consultant Representative), with Alyssa Skehan serving as the FDEP Contract Manager. The scope involves two docks: the main dock, which will be repaired/replaced in the same footprint, and the secondary dock, which will be replaced with a modified footprint involving removal of two fingers and doubling the length of the middle dock finger.

The contract encompasses 13 subtasks spanning design, permitting, bidding assistance, and construction phase support services. Design and permitting subtasks (1-7) include surveying, benthic and asbestos assessments, preliminary 30% plans, 60% plans, permit applications and approvals, and final 100% signed and sealed plans. Construction-related subtasks (8-13) cover bidding assistance, pre-construction meetings, submittal reviews, construction phase support (estimated at three months), substantial completion inspections, and final completion certification. The total task amount is $42,159.88, comprising a fixed price cost of $40,978.88 upon execution and cost reimbursement not to exceed $1,181.00 (due by completion date of 6/30/2023). Payment will be made upon FDEP approval of deliverables for each subtask. The project schedule includes design and permitting activities spanning approximately 480 calendar days, with the detailed cost breakdown distributed across individual subtasks for planning, surveys, environmental assessments, and design phases.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-A1.pdf PDF
CN-370000-CN230-CMC1.pdf PDF
CN-370000-CN230-T11.pdf PDF
CN-370000-CN230-T13CO1.pdf PDF
CN-370000-CN230-T2.pdf PDF
CN-370000-CN230-T27.pdf PDF
CN-370000-CN230-T28.pdf PDF
CN-370000-CN230-T34.pdf PDF
CN-370000-CN230-T36.pdf PDF
CN-370000-CN230-T37CO3.pdf PDF
CN-370000-CN230-T3CO2.pdf PDF
CN-370000-CN230-T4.pdf PDF
CN-370000-CN230-T42.pdf PDF
CN-370000-CN230-T42CO2.pdf PDF
CN-370000-CN230-T45CO3.pdf PDF
CN-370000-CN230-T46.pdf PDF
CN-370000-CN230-T4CO2.pdf PDF
CN-370000-CN230-T51CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 37 FDEP 61366C

Don Pedro Island State Park Visitor Dock Repairs

Weiler Engineering Corporation

Robin Palmer 941-505-1700 rpalmer@weilerengineering.org

Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov

Consultant to provide design and permitting documents to repair/replace visitor dock and the secondary dock at Don Pedro Island State Park as per proposal dated 11/1/21.

Wayne Thomas

Upon Execution $ 40,978.88 6/30/2023 $ 1,181.00

$ 42,159.88

Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.11.08 17:09:00 -05'00'

Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2021.11.09 10:05:04 -05'00'

Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.11.09 10:11:58 -05'00'

Jeff Weiler, P.E.

Michael W Foster Jr P.E.

61366C 37504003201 080039/22 423001 U3200 131500 QK $ 42,159.88

$ 42,159.88

R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2021.11.16 10:13:26 -05'00'

Michael W. Foster Jr.

Digitally signed by Michael W.

Foster Jr.

Date: 2021.12.01 15:01:55 -05'00'

September 28, 2021 - Revision 3 - November 1, 2021

Mr. Wayne Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: Don Pedro Island State Park - Dock Repair and/or Replacement - Contract 230, TA 37

Dear Mr. Thomas;

We are pleased to submit this proposal for design and permitting to repair/replace the main and secondary docks at Don Pedro Island State Park. Our general understanding is as follows:

Scope #1 Main Dock: Repair/replace existing main dock at Don Pedro State Park.� The existing dock at Don Pedro State Park is to be repaired/replaced in the same footprint.

Scope #2 Secondary Dock: Replace existing secondary dock at Don Pedro State Park.� The existing dock at Don Pedro State Park is to be replaced and the footprint modified.� The existing dock has 3 fingers of equal length: the northern and southern finger will be removed in their entirety and the middle dock finger will be replaced and the length will be doubled.

It is our understanding that CEI services will not be included in this Task Assignment so I have stricken them for now.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

September 28, 2021 - Rev 3 - 11/01/21 Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Main/Primary Dock

Secondary Dock

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Don Pedro Island State Park Main Dock Repair &

Secondary Dock Replacement Contract Number 230, Task Assignment Number 37

Subtask 1: Survey

Description: The Weiler Engineering Corporation (Consultant) will coordinate with a Florida Registered Engineer to prepare a special purpose survey adequate for design and permitting.

Deliverable: Consultant will provide a Signed and Sealed Special Purpose topographic and bathymetric survey of each dock (Not a Boundary Survey) in PDF format via email to the Bureau of Design and Construction (BDC).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1 - Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Dagostino 3 Person Field Crew Hr 121.50 8 972

Dagostino Survey Technician Hr 54.00 8 432

Dagostino PSM Manager Hr 162 6 972

Dagostino Total Survey 2956

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 1

Survey

$2956.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 2: Benthic Survey

Description: The Consultant will coordinate with environmental sub consultant, Terramar Environmental Services, Inc, to conduct a benthic assessment in the location of the proposed docks.

Deliverable: (These are the payment triggers – what items will consultant provide to FDEP, including format, size, number, minimum content, due date, etc)

Benthic Survey - Completed benthic assessment meeting SFWMD, USACOE and FKNMS requirements in PDF and Cad formats.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost: (if applicable)

Subtask 2 - Benthic Resource Assessment

Firm Name Position Classification Rate Hours Total Fixed Price Cost

Weiler Engineering Registered Professional Engineer 145 1 $145.00

Registered Engineer Intern 115 1 $115.00

Terramar Environmental Services Senior Environmental Scientist 167.40 27 $4519.80

Total Benthic Survey $4779.80

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total for Subtask 2 - Benthic Survey

$4779.80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 3: Asbestos Report

Description: Consultant will coordinate with Universal Engineering to complete an asbestos survey/report for the remaining concrete pads.

Deliverable: (These are the payment triggers – what items will consultant provide to FDEP, including format, size, number, minimum content, due date, etc)

Written results of asbestos survey will be delivered via email to the BDC via digital PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost: (if applicable)

Subtask 3 - Asbestos Report

Firm Name Position Classification Rate Hours Total Fixed Price Cost

Weiler Engineering Registered Professional Engineer 145 1 $145.00

Registered Engineer Intern 115 1 $115.00

Universal Engineering Senior Geotechnical Engineer, PE

165.84 2 $331.68

Sr. Engineering Technician 49.14 10 $491.40

Total Asbestos report $1083.08

Postage

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 4: Preliminary Design - 30% Plans

Description: The Weiler Engineering Corporation (Consultant) shall conduct one site visit with staff to inspect the docks and to discuss proposed ideas, research existing/available data and permits, conduct a pre-application meeting with the ACOE, the County and Water Management District. Consultant will evaluate whether or not the existing piles can be re-used and prepare plans to 30%.

Deliverable: Consultant will provide a summary of meetings with local and State regulatory agencies outlining permit requirements, plans prepared to 30% and a preliminary opinion of probable cost in PDF format via email to the Bureau of Design and Construction (BDC).

Cover Sheet Topographic and Bathymetric Survey Benthic Survey Existing Conditions Best Management Plan Demolition Plan Dock Plans - each dock Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total for Subtask 3 - Asbestos Report

$1083.08

Subtask 4 - Preliminary Design

Firm Name Position Classification Hourly Rate

Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Weiler Engineering Principal in Charge 195 2 $390.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Reimbursable Cost: (if applicable)

Subtask 5: 60% documents

Description: Plans completed to 60% incorporating comments from 30%.

Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:

Cover Sheet Survey Existing Conditions Best Management Plan Demolition Plan Dock Plans - each dock Structural Notes Framing Plan & Details - each dock Profiles Specifications

Weiler Engineering Registered Professional Engineer

145 6 $870.00

Weiler Engineering Registered Engineer Intern

115 10 $1150.00

Weiler Engineering Senior Engineering Designer

100 28 $2800.00

Weiler Engineering Engineering Technician 80 40 $3200.00

Weiler Engineering Clerical 55 2 $110.00

Total $9390.00

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 4

Preliminary Design

$9390.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 5 – 60% Plans

Firm Name Position Classification

Hour ly

Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 8 $1160.00

Registered Engineer Intern

115 11 $1265.00

Senior Engineering Designer

100 27 $2700.00

Engineering Technician

$2400.00

Clerical 55 2 $110.00

Total $8990.00

Postage No prints/provided digitally via email

Printing Not anticipated

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

$0.00

Total Subtask 5 $8990.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 6: Permitting

A – Permit Applications, Description: Consultant will assist Client to submit permit applications for the State Fire Marshal, the ACOE and State - Southwest Florida Water Management District permits.

Deliverable: Consultant shall deliver five sets of permit applications with 100% plans.

B – Permit Approvals, Description Consultant will coordinate with Client to respond to regulatory requests for additional information through approval.

Deliverable: Consultant will provide via email to the BDC the completed permits for the County, City and SWFWMD for site approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 6A Permit Applications

Firm Name Position Classification Hourly Rate

Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 5 $725.00

Registered Engineer Intern

115 16 $1840.00

Senior Engineering Designer

100 16 $1600.00

Engineering Technician 80 8 $640.00

Clerical 55 3 $165.00

Total $6325.00

Subtask 6B Permit Approvals

Firm Name Position Classification Hourly Rate

Hours

Total Fixed Price Cost

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Reimbursable Cost:

Subtask 7: 100% documents

Description: Plans completed to 100%.

Deliverable: Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Cover Sheet Survey Existing Conditions Best Management Plan Demolition Plan Dock Plans - each dock Structural Notes

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 2 $230.00

Senior Engineering Designer

100 5 $500.00

Engineering Technician 80 4 $320.00

Clerical 55 1 $55.00

Total $1540.00

Postage

Printing

County Permits Estimate $1000.00

SFWMD Exemption $100.00

Reimbursable Total Cost $1100.00

Total for Subtask 6 $8965.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Framing Plan & Details - each dock Profiles Specifications

Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 8: Assistance during bidding

Description: Consultant will respond to bidders’ questions and provide clarifications during bidding.

Subtask 7 - 100 % Plans

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 4 $580.00

Registered Engineer Intern

115 6 $690.00

Senior Engineering Designer

100 20 $2000.00

Engineering Technician

80 22 $1760.00

Clerical 55 2 $110.00

Total $5915.00

Postage 1 Fed-x at $35 = $105 35 Printing 20 sheets @ $2.30 per sheet

Overnight Travel

(if applicable)

Not anticipated

Reimbursable Total Cost

$81.00

Total for Subtask 7 $5996.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Reimbursable Cost:

Subtask 8 - Bidding assistance Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1580.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel

(if applicable)

Not anticipated

Mileage ($0.445 per mile)

Not anticipated

Reimbursable Total Cost

$0.00

Total for Subtask 8 $1580.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 9: Attend Pre-Construction Meeting

Description: WEC staff will attend one pre-construction meeting on site with one contractor for both docks, respond to questions and prepare minutes.

Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 9 - Pre-construction Mtg

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 0 $0.00

Senior Engineering Designer

100 4 $400.00

Engineering Technician 80 4 $320.00

Clerical 55 0 $0.00

Total $1300.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0

Reimbursable Total Cost

$0.00

Total Subtask 9 $1300.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 10: Review Contractor submittals

Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.

Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 10 - Submittal Review

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 8 $920.00

Senior Engineering Designer

100 2 $200.00

Engineering Technician

80 2 $160.00

Clerical 55 1 $55.00

Total $1625.00

Postage Not anticipated (all deliverables in digital form only)

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 11: Assistance during construction (3 Months)

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Deliverable: Correspondence with Contractor and regulatory agencies provided via

PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Reimbursable Total Cost

$0.00

Total Subtask 10 - Submittals

$1625.00

Subtask 11

Firm Name Position Classification Hourly Rate

Ho urs

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $2125.00

Postage Not anticipated

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 12: Substantial Completion Walk-Through w/Punchlist

Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.

Deliverable: WEC will provide comments and input on punch list within one (1) day of Substantial Completion inspection.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost $0.00

Total Subtask 11 $2125.00

Subtask 12 - Substantial

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 1 $100.00

Engineering Technician 80 4 $320.00

Clerical 55 0 $0.00

Total $1800.00

Postage Not anticipated

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Subtask 13: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion inspection of the site with WEC representative attending the Final Completion inspection.

Deliverable: WEC will prepare final certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost

$0.00

Total Subtask 12 $1800.00

Subtask 13 - Final

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Prroject Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer

100 4 $400.00

Engineering Technician 80 8 $640.00

Clerical 55 1 $55.00

Total $2885.00

Postage Not anticipated

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Project Schedule:

Summary of Fees:

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost

$0.00

Total Subtask 13 $2885.00

Activity Duration (Calendar Days) Dates to be based on date of execution of task order

Subtask 1 Survey 45

Subtask 2 Benthic 30

Subtask 3 Asbestos 30

Subtask 4 30% Plans 45 - includes 14 days for Client review

Subtask 5: 60% plans 30 - includes 14 days for Client review

Subtask 6A: Permit applications 30 – includes 7 days for Client review

Subtask 6B: Permit approvals 240 – includes 7 days for Client review

Subtask 7: 100% plans 30 – includes response for additional information

Subtask’s 8-13 240

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 1 Survey $2956.00 $0.00

Subtask 2 Benthic $4779.80 $0.00

Subtask 3 Asbestos $1083.08 $0.00

Subtask 4 30% Plans $9390.00 $0.00

Subtask 5: 60% plans $8990.00 $0.00

Subtask 6A: Permit applications $6325.00 $1100.00

Subtask 6B: Permit approvals $1540.00 $0.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Don Pedro Island SP - Dock Repair/Replacement

CN 230 TN 37

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

Subtask 7: 100% plans $5915.00 $81.00

Total Design & Permitting $42159.88 $40978.88 $1181.00

Subtask 8: Assistance during bidding

$1580.00 $0.00

Subtask 9: Attend Pre-Con Mtg $1300.00 $0.00

Subtask 10: Review Submittals $1625.00 $0.00

Subtask 11: Assistance during Construction - 3 Months

$2125.00 $0.00

Subtask 12: Substantial Completion Walk-Through w/ Punchlist

$1800.00 $0.00

Subtask 13: Final Completion w/ Certification

$2885.00 $0.00

Subtotal Construction Services $11315.00 $11315.00 $0.00

Total Fixed Price $52293.88

Total Reimbursable Cost $1181.00

Total Overall Cost $53474.88