This is a Task Assignment Notification Form (Task Assignment No. 89) issued by the Florida Department of Environmental Protection (FDEP) under Contract CN230 with Weiler Engineering Corporation for design and permitting services at Gasparilla Island State Park. The project involves the relocation of the state park's access, parking facilities, and utilities within the park boundary.
The contract scope encompasses design and permitting services only, specifically excluding construction administration. Services include 30% preliminary design, survey work, geotechnical reports, 60% design plans, 100% design plans, and permit applications and approvals from the Southwest Florida Water Management District, FDEP Coastal Construction Control Line, and Lee County. The fixed price cost is $89,795.38 with cost reimbursement authorization of $6,000.00 for permit application fees (SFWMD application fee of $3,500 and Lee County LDO fee of $2,500), for a total task amount of $95,795.38. The project execution began upon contract execution with a completion date of April 29, 2025. The contract includes performance measures requiring deliverables to be reviewed by the FDEP to confirm completeness, accuracy, and timeliness, with payment contingent on approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 89 FDEP 61509C
Road Paving
Weiler Engineering Corp.
Robin Palmer (941) 646-8612 rpalmer@weilerengineering.org
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Design and permitting services only to relocate the state park's access and parking within the boundary of the park. This includes relocation of park's entry / exit at Belcher Rd, main driveway, utilities reconfiguration, and paving of main parking lot and South parking lot per proposal dated 10/03/24.
Meena Senthil or successor
Upon Execution $ 89,795.38 04/29/2025 $ 6,000.00
$ 95,795.38
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.10.15 15:25:04 -04'00'
Meena Senthil Meena Senthil Digitally signed by Meena Senthil Date: 2024.10.15 16:15:15 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.10.16 10:53:49 -04'00'
Robin Palmer Robin C. Palmer Digitally signed by Robin C.
Palmer Date: 2024.10.16 11:16:00 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2024.10.28 09:30:31 -04'00'
61509C 37504003191 080039/23 423001 U3200 131500 QK $ 95,795.38
$ 95,795.38
Gasparilla Island State Park
September 11, 2024- Rev 1 October 3, 2024
Ms. Meen Senthil Design Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Gasparilla Island State Park – Road Paving, CN - 230, TA - 89
Dear Ms. Senthil, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to relocate the state park’s access and reconfigure the parking lots within the boundary of the park.
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
September 11, 2024, Rev 1: October 3, 2024 Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Our services will include:
Design, permitting, and construction administration services to relocate the state park's access and parking within the boundary of the park. This includes relocation of park's entry / exit at Belcher Rd, main driveway, utilities reconfiguration, and paving of main parking lot and South parking lot
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
Services during construction are removed and not in included in this contract
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Gasparilla Island State Park Road Paving
Contract Number 230, Task Assignment Number 89
Subtask 1: 30% Preliminary Design
1) A – 30% Preliminary Design
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Water Management District, FDEP
CCCL, and Lee County. No USACE permitting is anticipated for this project.
c) Consultant will prepare Preliminary Design Plans.
1) B – Surveys
a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topographic information for the project area.
1) C –Geotechnical Reports
a) Consultant will coordinate with Geotechnical Sub-Consultant to prepare a geotechnical Report recommending piling depths
Deliverable:
1) A – 30% Preliminary Design
Meeting minutes from the site visit and all permitting pre-application meeting minutes will be provided in PDF format. For the 30% Design Plans, Consultant shall deliver 30% design plans to the client via digital PDF. Plans will include:
Cover sheet Existing Conditions Site Plan Opinion of Probable Cost
1) B - Survey
Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a Special Purpose Survey via digital PDF, and CAD.
1) C –Geotechnical Report
Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report with (2) Standard Penetration Test (SPT) borings and (60 hand auger borings to a depth of 6ft within the area to be paved. Deliverable shall be via digital PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Fixed Price Cost:
Subtask 1A: 30% Preliminary Design
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 14 2030.00
Weiler Engineering Principal in Charge 195 .25 48.75
Weiler Engineering
Registered Professional Engineer 145 26 3770.00
Weiler Engineering Registered Engineer Intern 115 32 3680.00
Weiler Engineering Senior Engineering Designer 100 50 5000.00
Weiler Engineering Engineering Technician 80 40 3200.00
Weiler Engineering Clerical 55 2 110.00
Total 30% Preliminary Design 17838.75
Subtask 1B: Survey
Firm Name Position Classification Unit Unit Rate Number Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 9 1305.00
CHW 3 Person Field Crew Hr 177.54 26 4616.04
CHW Project Surveyor Hr 74.75 23 1719.25
CHW Senior CAD/GIS Hr 103.13 16 1650.08
CHW Professional Surveyor & Mapper
Hr 163.93 4 655.72
Total Survey 9946.09
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 1C: Geotechnical Report
Firm Name Position Classification Unit Unit Rate Number Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 7 1015.00
Geotech Tierra
Tierra Senior Engineer Hr 178.60 12 2143.20
Tierra Senior Project Engineer Hr 146.53 16 2344.48
Tierra Geotechnical Technician Hr 68.45 25 1711.25
Tierra Clerical Hr 75.67 8 605.36
Total Geotech 7819.29
Reimbursable Cost: (if applicable)
Description Number @ Total
Postage Not Anticipated
Printing Not Anticipated
Overnight Travel (if applicable)
Not Anticipated
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 1
Total Subtask 1 35604.13
Subtask 2: 60% Design Plans
September 11, 2024, Rev 1: October 3, 2024 Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 2: 60% Design Plans Description: Plans completed to 60% incorporating comments from 30%.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 14 2030.00
Weiler Engineering Principal in Charge 195 0.25 48.75
Weiler Engineering
Registered Professional Engineer 145 30 4350.00
Weiler Engineering Registered Engineer Intern 115 30 3450.00
Weiler Engineering Senior Engineering Designer 100 45 4500.00
Weiler Engineering Engineering Technician 80 36 2880.00
Weiler Engineering Clerical 55 4 220.00
Total 17478.75
Total for Subtask 2 17478.75
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 3: 100% Design Plans
Description: Plans completed to 100%.
Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver two sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Updated Opinion of Probable Cost Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3: 100% Design Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 14 2030.00
Weiler Engineering Principal in Charge 195 .5 97.50
Weiler Engineering
Registered Professional Engineer 145 22 3190.00
Weiler Engineering Registered Engineer Intern 115 26 2990.00
Weiler Engineering Senior Engineering Designer 100 32 3200.00
Weiler Engineering Engineering Technician 80 32 2560.00
Weiler Engineering Clerical 55 3 165.00
Total 100% Design Plans 14232.50
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Reimbursable Cost:
Description Number @ Total
Postage Not anticipated
35 0
Printing Not anticipated
2.30 0
Overnight Travel (if applicable)
Reimbursable Total Cost
Total for Subtask 3
14,232.50
Subtask 4: Permitting
Description:
4) A – Permit Applications
Consultant will assist Client to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for an Individual or General Permit, the FDEP for a CCCL Permit, and coordinate with the Lee County on a Limited Development Order.
4) B – Permit Approvals
Consultant will coordinate with agencies and respond to agencies for additional information.
Depending on the agencies, the anticipated timeline for approval is 90 days after submittal.
Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation. Permit approvals will include: FDEP CCCL and SWFWMD ERP/General Permit, and Lee County LDO.
Deliverable:
4) A – Permit Applications
Incorporate Client review comments from 60% plans and deliver a digital set of the permit applications for signature. Deliverable will be in PDF format.
4) B – Permit Approvals
Approvals will be obtained from SWFWMD (Individual or General Permit), FDEP CCCL Permit, and Lee County LDO. Deliverable will be in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA
Fixed Price Cost:
Subtask 4A:
Permit Applications
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 14 2030.00
Weiler Engineering Principal in Charge 195 .25 48.75
Weiler Engineering Registered Professional Engineer 145 28 4060.00
Weiler Engineering Registered Engineer Intern 115 60 6900.00
Weiler Engineering Senior Engineering Designer 100 32 3200.00
Weiler Engineering Engineering Technician 80 36 2880.00
Weiler Engineering Clerical 55 1 55.00
Total Permit Applications 19,173.75
Subtask 4B Permit Approvals
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290.00
Weiler Engineering Principal in Charge 195 .25 48.75
Weiler Engineering Registered Professional Engineer 145 4 580.00
Weiler Engineering Registered Engineer Intern 115 8 920.00
Weiler Engineering Senior Engineering Designer 100 8 800.00
Weiler Engineering Engineering Technician 80 8 640.00
Weiler Engineering Clerical 55 0.5 27.50
Total Permit Approvals 3,306.25
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Reimbursable Cost:
Description Number @ Total
Postage Not anticipated 35 0
Printing Not anticipated 2.3 0
SFWMD
Application Fees
1 3500 3500.00
Lee County
LDO
1 2500 2500.00
Reimbursable Total Cost for 4A
6000.00
Total for Subtask 4
28,480.00
Subtask 5A – 5G: Construction Phase Services
Subtask 5A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Not in contract
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 0 0
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total Attend Pre-Construction Meeting
Reimbursable Cost:
Description Number @ Total
Postage 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 5A 2080
Subtask 5B: Review Contractor submittals
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Fixed Price Cost:
Subtask 5B: Review Submittals
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 12 1200
Weiler Engineering Engineering Technician 80 2 160
Weiler Engineering Clerical 55 2 110
Total Review Submittals 2680
Reimbursable Cost:
Description Number @ Total
Postage Not Anticipated 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 5B 2680.00
Subtask 5C: Respond to Building Department Comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department within 7 days, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Deliverable: RFI response documents submitted to Building Department within 7 days (14 days for plan revisions) in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5C: Respond to Building Department Comments
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1980
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.30 0.00
Overnight Travel
(if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
Total: 5C 1980
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 5D: Respond to Contractor RFI's
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. If any plan changes are required, these changes will be completed within 14 days.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format within 7 days.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5D: Respond to RFI’s
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 2 290
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 4 220
Total Respond to RFI’s 2520
Reimbursable Cost:
Description Number @ Total
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 5D 2520
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 5E: Interim Site Inspection # 1
Description: WEC will provide an interim inspection during construction upon request from BDC.
Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of the site visit.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5E – Interim Site Inspection #1
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00
Weiler Engineering Principal in Charge 195 0 0.00
Weiler Engineering Registered Professional Engineer
145 .5 72.50
Weiler Engineering Registered Engineer Intern 115 10 1150.00
Weiler Engineering Senior Engineering Designer 100 1 100.00
Weiler Engineering Engineering Technician 80 0 0.00
Weiler Engineering Clerical 55 0 0.00
Total Interim Site Inspection #1 1467.50
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 5E 1467.50
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 5F: Interim Site Inspection #2
Description: WEC will provide an interim inspection during construction upon request from BDC.
Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of the site visit.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5F: Interim Site Inspection #2
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145.00
Weiler Engineering Principal in Charge 195 0 0.00
Weiler Engineering Registered Professional Engineer
145 .5 72.50
Weiler Engineering Registered Engineer Intern 115 10 1150.00
Weiler Engineering Senior Engineering Designer 100 1 100.00
Weiler Engineering Engineering Technician 80 0 0.00
Weiler Engineering Clerical 55 0 0.00
Total 1467.50
Reimbursable Cost:
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost
Total Subtask 5F 1467.50
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Subtask 5G: Substantial Completion w/ Certification
Description: WEC will assist Client with the Substantial Completion inspection, with WEC representative attending the Substantial Completion inspection with punchlist.
Deliverable: WEC will also provide complete the substantial completion certification form required by FDEP Project Manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5G: Substantial Completion
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 3 435.00
Weiler Engineering Principal in Charge 195 0 0.00
Weiler Engineering Registered Professional Engineer
145 2 290.00
Weiler Engineering Registered Engineer Intern 115 14 1610.00
Weiler Engineering Senior Engineering Designer 100 8 800.00
Weiler Engineering Engineering Technician 80 0 0.00
Weiler Engineering Clerical 55 0 0.00
Total 3135.00
Reimbursable Cost:
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 5G 3135.00
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Project Schedule:
Activity Duration (Calendar Days) Days from Execution
Subtask 1A: 30% Preliminary Design
60 60
Subtask 1B: Survey 60 60
Subtask 1C: Geotechnical Report 60 60
Subtask 2: 60% Design 30 - includes 7 days for Client review
Subtask 3: 100% Design 30 – includes 7 days for Client review
Subtask 4A: Permit Applications 30 – includes 7 days for Client review
Subtask 4B: Permit Approvals 60 – includes response for additional information
Subtask 5A: Pre-Construction TBD TBD
Subtask 5B: Review Submittals TBD TBD Subtask 5C: Respond to TBD TBD
Subtask 5D: Respond to Contractor RFI's
TBD TBD
Subtask 5E: Interim Site Inspection #1
TBD TBD
Subtask 5F: Interim Site Inspection #2
TBD TBD
Subtask 5G: Substantial Completion Walk-Through w/ Punchlist
TBD TBD
Ms. Meena Senthil Gasparilla Island State Park Road Paving
CN 230/TA8
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A: 30% Preliminary Design
$17838.75 $0.00
Subtask 1B: Survey $9946.09 $0.00
Subtask 1C: Geotech $7819.29 $0.00
Subtask 2: 60% Design $17478.75 $0.00
Subtask 3: 100% Design $14232.50 $0.00
Subtask 4A: Permit Applications $19173.75 $6000.00
Subtask 4B: Permit Approvals $3306.25 $0.00
Total Design & Permitting $89,795.38 $6,000.00
Subtask 5A:Pre-Construction Meeting
$2080.00 $0.00
Subtask 5B: Submittal Review $2680.00 $0.00
Subtask 5C: $1980.00 $0.00
Subtask 5D: $2520.00 $0.00
Subtask 5E: Interim Site Inspection #1
$1467.50 $0.00
Subtask 5F: Interim Site Inspection #2
$1467.50 $0.00
Subtask 5G: Substantial Completion
$3135.00 $0.00
Total during Construction 15,330.00 $0.00
Total Fixed Price Cost: $105125.38
Total Fixed Price Cost: $6000.00
Overall Total Cost: $111125.38
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
$89,795.38
$95,795.38