This Task Assignment Notification Form, issued by the Florida Department of Environmental Protection (FDEP) and assigned to Weiler Engineering Corporation, establishes a design and permitting task (CN230, Task Assignment No. 28) for the Accessible Launch project at Lovers Key State Park. The contract is executed between FDEP and the consultant, with Robin Palmer serving as the Consultant Representative and Alyssa Skehan as the FDEP Contract Manager. The project is located at Lovers Key State Park in Florida.
Weiler Engineering Corporation will provide comprehensive design and permitting services including preparation of a special purpose survey, preliminary 30% design plans, 60% design documents, and final 100% signed and sealed construction plans. Additional services encompass permit applications and approvals from regulatory agencies (City of Bonita Springs, Southwest Florida Water Management District, and Army Corps of Engineers), assistance during the bidding phase, attendance at pre-bid and pre-construction meetings, contractor submittal reviews, construction phase support for three months, substantial completion and final completion inspections with certifications. The total contract value is $27,790.50, consisting of $24,101.00 in fixed price costs and $3,689.50 in cost reimbursement, with a completion date of June 30, 2022. Payment is contingent upon FDEP approval of deliverables for each subtask. The scope includes design of an ADA-accessible kayak launch using EZ Dock technology, erosion control measures for existing launch areas, and addition of at least one ADA parking space near the new kayak launch facility.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 28 FDEP 61306C
Lovers Key State Park Accessible Launch
Weiler Engineering Corporation
Robin Palmer 941-505-1700 rpalmer@weilerengineering.org
Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov
Consultant to provide design and all applicable permits for the construction of an accessible kayak launch for one side of the existing launch area, provide erosion control measures for the other existing launch area to make it safer to use and add at least 1 ADA parking spot near ADA kayak launch as per proposal dated 11/10/2020.
Wayne Thomas
Upon execution $ 24,101.00 6/30/2022 $ 3,689.50
$ 27,790.50
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2020.11.13 16:58:10 -05'00'
Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2020.11.16 08:07:36 -05'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2020.11.16 10:35:00 -05'00'
Jeff Weiler R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2020.11.16 13:16:47 -05'00'
Michael W. Foster Jr. PE Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2020.12.08 10:35:57 -05'00'
61306C 37504000193 080039/21 675002 U3200 131500 XR $ 27,790.50
$ 0.00
October 10, 2020 - Revision 3 -November 10, 2020
Mr. Wayne Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: Lovers Key Kayak Launch - Contract 230, TA
Dear Mr. Thomas;
We are pleased to submit this proposal for design and permitting to modify the existing parking facilities at the Lovers Key State Park.
Our general understanding of the project includes:
• Existing conditions
◦ (2) existing shell/earthen kayak launches that are challenging to access during low tide, not ADA accessible, and have erosion issues that make the slope steep
◦ Existing shell parking lot located near the kayak launch
• Proposed conditions
◦ Design an ADA accessible kayak launch (EZ Dock) for one side of the existing launch area
◦ Provide erosion control for the other existing launch as well as make it easier/safer to use
◦ Add at least 1 ADA parking space near the ADA kayak launch
• Permitting
◦ SFWMD ERP
◦ ACOE permit
◦ City of Bonita Springs Limited Development Order and Dock and Shorline
Permits
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.
Please feel free to contact me if you have any questions or wish to discuss matters further.
October 10, 2020 - Rev 3 - 11/10/2020
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Sincerely, R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Lovers Key Kayak Launch
Contract Number 230, Task Assignment Number
Subtask 1: Survey Description: The Weiler Engineering Corporation (Consultant) will coordinate with a Florida Registered Engineer to prepare a special purpose survey including the upland and bathymetric in the area of the new dock adequate for design and permitting.
Deliverable: Consultant will provide a Signed and Sealed Special Purpose survey (Not a Boundary Survey) in PDF format via email to the Bureau of Design and Construction (BDC).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 - Survey
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 2 290
Survey ARS *** 3 Person Field Crew Hr 121.50 16 1944
Survey ARS *** Survey Technician Hr 54.00 20 1080
Survey ARS *** PSM Manager Hr 162 6 972
Survey ARS *** Total Survey 4286
Postage
Printing
Overnight Travel (if applicable) Mileage (@ $0.445 per mile)
Reimbursable Total Cost $0.00
Total Subtask 1 Survey
$4286.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Subtask 2: Preliminary Design - 30% Plans Description: The Weiler Engineering Corporation (Consultant) shall conduct one site visit with staff to inspect the parking area and entrance to Burnt Store Road and to discuss proposed ideas, research existing/available data and permits, conduct a pre-application meeting with the City, ACOE and Water Management District.
Deliverable: Consultant will provide a summary of meetings with local and State regulatory agencies outlining permit requirements, plans prepared to 30% and a preliminary opinion of probable cost in PDF format via email to the Bureau of Design and Construction (BDC).
Cover sheet Existing Conditions Special Purpose Survey Best Management Plan Demolition Plan Site Plans Details
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Subtask 2 - Preliminary Design
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 $870.00
Weiler Engineering Principal in Charge 195 2 $390.00
Weiler Engineering Registered Professional Engineer 145 12 $1740.00
Weiler Engineering Registered Engineer Intern 115 6 $690.00
Weiler Engineering Senior Engineering Designer 100 16 $1600.00
Weiler Engineering Engineering Technician 80 16 $1280.00
Weiler Engineering Clerical 55 2 $110.00
Total $6680.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost: (if applicable)
Subtask 3: 60% documents Description: Plans completed to 60% incorporating comments from 30%.
Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost;
Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plans Dock Plans and Details Site Details and General Notes
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:
Postage
Printing
Overnight Travel (if applicable) Mileage (@ $0.445 per mile)
100 RT $44.50
Reimbursable Total Cost $44.50
Total Subtask 2 Preliminary Design
$6724.50
Subtask 3– 60% Plans
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Subtask 4: 100% documents Description: Plans completed to 100%.
Deliverable: Consultant shall deliver five sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Firm Name Position Classification
Hour ly
Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 $870.00
Principal in Charge 195 1 $195.00 Registered Professional Engineer
145 1 $145.00
Registered Engineer Intern 115 6 $690.00
Senior Engineering Designer 100 8 $800.00
Engineering Technician 80 12 $960.00
Clerical 55 2 $110.00
Total $3770.00
Postage No prints/provided digitally via email
Printing Not anticipated
Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost
$0.00
Total Subtask 3 $3770.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Updated Opinion of Probable Cost;
Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Dock Plans and Details Site Details and General Notes Specifications
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:
Reimbursable Cost:
Subtask 4 - 100 % Plans
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 2 $290.00
Registered Engineer Intern 115 6 $690.00
Senior Engineering Designer 100 8 $800.00
Engineering Technician 80 8 $640.00
Clerical 55 1 $55.00
Total $3250.00
Postage 1 Fed-x at $35 = $105 35 Printing 400 sheets @ $2.30 per sheet
Overnight Travel (if applicable)
Not anticipated
Reimbursable Total Cost
$955.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Subtask 5: Permitting
A – Permit Applications, Description: Consultant will assist Client to submit permit applications for City Limited Development Order (LDO) and Dock & Shorline permits, Water Management or FDEP ERP and ACOE approvals.
Deliverable: Consultant shall deliver five sets of permit applications with 100% plans.
B – Permit Approvals, Description Consultant will coordinate with Client to respond to regulatory requests for additional information through approval.
Deliverable: Consultant will provide via email to the BDC the completed permits for the County, City and SWFWMD for site approvals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Total for Subtask 4 $4205.00
Subtask 5A Permit Applications
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 7 $1015.00
Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 5 $725.00
Registered Engineer Intern 115 9 $1035.00
Senior Engineering Designer 100 8 $800.00
Engineering Technician 80 8 $640.00
Clerical 55 3 $165.00
Total $4575.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Subtask 6: Assistance during bidding
Subtask 5B Permit Approvals
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 0 $0.00 Registered Professional Engineer 145 1 $145.00
Registered Engineer Intern 115 2 $230.00
Senior Engineering Designer 100 5 $500.00
Engineering Technician 80 4 $320.00
Clerical 55 1 $55.00
Total $1540.00
Postage 3 Fed-x at $35 $105.00
Printing 200 sheets @ $2.30/ sheet
$460.00
County Permits Estimate $1000.00
City LDO & Dock & Shorline
$1025.00
SFWMD Exemption $100.00
Reimbursable Total Cost $2690.00
Total for Subtask 5 $8805.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Description: Consultant will respond to bidders’ questions and provide clarifications during bidding.
Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Reimbursable Cost:
Subtask 6 Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 $290.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 1 $145.00
Registered Engineer Intern 115 6 $690.00
Senior Engineering Designer 100 4 $400.00
Engineering Technician 80 0 $0.00
Clerical 55 1 $55.00
Total $1580.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage ($0.445 per mile)
Not anticipated
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Subtask 7: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Reimbursable Cost:
Reimbursable Total Cost
$0.00
Total for Subtask 6 $1580.00
Subtask 7 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern 115 4 $460.00
Senior Engineering Designer 100 0 $0.00
Engineering Technician 80 4 $320.00
Clerical 55 0 $0.00
Total $1360.00
Postage Not anticipated
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Subtask 8: Attend Pre-Construction Meeting Description: WEC staff will attend one pre-construction meeting on site, respond to questions and prepare minutes.
Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.50
Reimbursable Total Cost
$44.50
Total Subtask 7
$1404.50
Subtask 8 - Pre-construction Mtg
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern
115 0 $0.00
Senior Engineering Designer
100 4 $400.00
Engineering Technician 80 4 $320.00
Clerical 55 0 $0.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Subtask 9: Review Contractor submittals
Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.
Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Total $1300.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.5
Reimbursable Total Cost
$44.50
Total Subtask 8 $1344.50
Subtask 9 - Submittal Review
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 $290.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern
115 8 $920.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Subtask 10: Assistance during construction (3 Months)
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Deliverable: Correspondence with Contractor and regulatory agencies provide via PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Senior Engineering Designer
100 8 $800.00
Engineering Technician
80 2 $160.00
Clerical 55 2 $110.00
Total $2280.00
Postage Not anticipated (all deliverables in digital form only)
Printing Not anticipated (all deliverables in digital form only)
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
$0.00
Total Subtask 9 - Submittals
$2280.00
Subtask 10
Firm Name Position Classification Hourly Rate
Ho urs
Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 $870.00
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Subtask 11: Substantial Completion Walk-Through w/Punchlist Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.
Deliverable: WEC will provide comments and input on punch list within one (1) day of Substantial Completion inspection.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Principal in Charge 195 1 $195.00
Registered Professional Engineer
145 4 $580.00
Registered Engineer Intern
115 6 $690.00
Senior Engineering Designer
100 6 $600.00
Engineering Technician 80 0 $0.00
Clerical 55 2 $110.00
Total $3045.00
Postage Not anticipated
Printing Not anticipated (all deliverables in digital form only)
Overnight Travel (if applicable) Not anticipated
Mileage (@ $0.445 per mile) Not anticipated
Reimbursable Total Cost $0.00
Total Subtask 10 $3045.00
Subtask 11
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Subtask 12: Final Completion w/ Certification
Description: WEC will assist Client with the Final Completion inspection of the site with WEC representative attending the Final Completion inspection.
Deliverable: WEC will prepare final certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Principal in Charge 195 1 $195.00
Registered Professional Engineer
145 1 $145.00
Registered Engineer Intern
115 4 $460.00
Senior Engineering Designer
100 1 $100.00
Engineering Technician 80 8 $640.00
Clerical 55 0 $0.00
Total $2120.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.50
Reimbursable Total Cost
$44.50
Total Subtask 11 $2164.50
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Reimbursable Cost:
Project Schedule:
Subtask 12 - Final
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Prroject Manager 145 4 $580.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 2 $290.00
Registered Engineer Intern 115 4 $460.00
Senior Engineering Designer
100 4 $400.00
Engineering Technician 80 4 $320.00
Clerical 55 1 $55.00
Total $2105.00
Postage Not anticipated
Printing Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
100 $44.50
Reimbursable Total Cost
$44.50
Total Subtask 12 $2149.50
Activity Duration (Calendar Days) Dates to be based on date of execution of task order
Subtask 1 Survey 30
Subtask 2 Preliminary 30
Subtask 3: 60% plans 30 - includes 7 days for Client review
Subtask 4: 100% plans 30 – includes 7 days for Client review
Subtask 5A: Permit applications 30 – includes 7 days for Client review
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Summary of Fees:
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Subtask 5B: Permit approvals 60 – includes response for additional information
Subtask’s 6-12 240
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 1A - Survey $4286.00 $0.00
Subtask 2 - 30% Plans $6680.00 $44.50
Subtask 3: 60% plans $3770.00 $0.00
Subtask 4: 100% plans $3250.00 $955.00
Subtask 5A Permit applications $4575.00 $2690.00
Subtask 5B Permit approvals $1540.00 $0.00
Subtotal Design & Permitting $24101.00 $3689.50
Total Design & Permitting $27790.50
Subtask 6: Assistance during bidding
$1580.00 $0.00
Subtask 7: Pre-bid meeting $1360.00 $44.50 Subtask 7A: Attend Pre-Con Mtg $1300.00 $44.50
Subtask 7B: Review Submittals $2280.00 $0.00
Subtask 7C: Assistance during Construction - 3 Months
$3045.00 $0.00
Subtask 7D: Substantial Completion Walk-Through w/ Punchlist - Site
$2120.00 $44.50
Subtask 7E: Final Completion w/ Certification
$2105.00 $44.50
Subtotal Construction Services $13790.00 $178.00
Total Fixed Price $37891.00
Total Reimbursable Cost $3867.50
Total Overall Cost $41758.50
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
Mr. Wayne Thomas Lovers Key Kayak Launch
CN 230 TN
Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702
File details come from the government source that posted it. Updated .