CN-370000-CN230-T13CO1.pdf
PDF 3 MB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for contract CN230 involving The Weiler Engineering Corporation as the consultant. The change order pertains to Task Assignment No. 13 for the Curry Hammock State Park New Mitchell Property Residences project located in Curry Hammock State Park, Florida. Key personnel include R. Jeff Weiler, PE as the consultant representative, and Philip Stone as the FDEP Contract Manager.
This no-cost change order extends the task execution period by one year without any modification to the contract amount. The original task end date of December 31, 2020 was extended to December 31, 2021, representing a net change of 365 days. The total contract amount remains unchanged at $163,810.53, comprised of $4,831.07 in reimbursement and $158,979.46 in fixed fees. The extension was requested by the consultant to allow additional time for completion of remaining construction task items. The change order was approved and digitally signed by all required parties between November 9 and December 16, 2020.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 13 1 61228C
Curry Hammock State Park New Mitchell Property Residences
The Weiler Engineering Corporation
R. Jeff Weiler, PE 941-505-1700 weiler7@mac.com
Philip Stone or successor 850-245-2570 Philip.Stone@FloridaDEP.gov
This is a no-cost change order to extend the expiration date by a year per email dated 11/6/2020.
$ 4,831.07 $ 158,979.46 $ 163,810.53 $ 4,831.07 $ 158,979.46 $ 163,810.53
$ 0.00 $ 0.00 $ 0.00 $ 4,831.07 $ 158,979.46 $ 163,810.53
1/25/2019
12/31/2020
12/31/2020
12/31/2021
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2020.11.09 11:50:27 -05'00'
Laura Ross Laura S. Ross Digitally signed by Laura S. Ross Date: 2020.11.09 11:54:59 -05'00'
Philip Stone P.T. Stone Digitally signed by P.T. Stone Date: 2020.11.12 14:07:54 -05'00'
R. Jeff Weiler R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2020.11.12 14:31:36 -05'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2020.12.16 09:12:13 -05'00'
$ 0.00
Ross, Laura S.
From: rpalmer@weilerengineering.org Sent: Friday, November 6, 2020 11:05 AM To: Ross, Laura S.
Subject: Curry Hammock-Mitchell Property 7 Residences Time Extension
Good morning Laura, I would like to request a time extension on our contract for 1 year for task assignment #61228C (Curry Hammock Mitchell Property) in order to have time to complete the remaining construction task items. If you need anything else, please let me know.
Thank you, Robin Palmer, P.E.
Environmental Engineer