CN-370000-CN230-T36.pdf
PDF 2 MB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This is a Task Assignment Notification Form and supporting proposal from the Florida Department of Environmental Protection (FDEP) to Weiler Engineering Corporation for engineering services related to the South Beach Access Day Use Restroom Replacement project at Fort Pierce Inlet State Park. The task assignment is designated as CN230, Task Assignment No. 36, with Project No. 61384C. The consultant is Weiler Engineering, represented by Jeff Weiler, and the FDEP contract manager is Alyssa Skehan. The project manager is Richard J. Rowe or successor.
The scope of work encompasses comprehensive engineering services spanning design and permitting phases through construction administration. Services include updating existing plans to comply with the 2020 Florida Building Code and revised FEMA flood zone requirements (changing from AE to VE zone), preparing 60% and 100% construction documents, surveying, permitting assistance with St. Lucie County and Water Management District, bidding support, pre-construction meeting attendance, contractor submittal review, building department coordination, and five months of construction phase inspections and administration services. The total fixed price cost is $32,944.50 with cost reimbursement not to exceed $750.00 (for permit fees), bringing the total task amount to $33,694.50. The contract execution date is upon execution, with completion required by December 31, 2022. Subtasks are organized into design and permitting phases ($15,972 fixed price plus $750 reimbursable) and construction phase services ($16,972.50 fixed price). Payment is made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 36 FDEP-DRP 61384C
Ft. Pierce Inlet State Park South Beach Access Day Use Restroom Replacement
Weiler Engineering
Jeff Weiler 941-505-1700 weiler7@mac.com
Alyssa Skehan 850-245-2781 alyssa.skehan@dep.state.fl.us
Update existing plans to 2020 Florida Building code and revise to accommodate redrawn FEMA flood map. Bidding and construction administration services are also included. See attached proposal dated 7/30/2021 for reference.
Richard J. Rowe or Successor
Upon Execution $ 32,944.50 12/31/2022 $ 750.00
$ 33,694.50
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.09.29 16:24:02 -04'00' 09-29-2021
Richard J. Rowe Richard J. Rowe Digitally signed by Richard J.
Rowe Date: 2021.09.29 16:40:33 -04'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.09.30 15:05:31 -04'00'
Jeff Weiler R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2021.10.05 13:37:45 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2021.10.14 16:35:50 -04'00'
61384C 37505000106 080039/22 423001 U3200 131500 QK $ 33,694.50
$ 33,694.50
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
July 2, 2021 - Revision 15 - July 30, 2021
Mr. Richard Rowe
Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: WEC Number 16045.001
Ft Pierce Inlet - South Restroom Replacement
Dear Mr. Rowe;
Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to replace the South restroom/bathhouse facilities in Fort Pierce Inlet State Park.
It is our general understanding that the Department of Environmental Protection - BDC (Client) wishes to replace the South beach access restroom facilities located in Fort Pierce Inlet State Park. WEC recently prepared construction plans for the building in accordance with the 2017 building code in an AE flood zone, but the Flood Zone has changed to VE and the structure is now required to meet the 2020 building code. The Department wishes for WEC to revise the plans to meet the current Building code and flood zone requirements necessary for permitting and construction and provide services during construction.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
July 2, 2021 - Rev 14, 07/22/21 Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
South Restroom Replacement
Fort Pierce Inlet State Park
Contract Number 230, Task Assignment Number 35
Subtask 1: 60% Plans
1) A - Consultant will prepare a preliminary site plan with building and ramp locations as required coordinated with the new flood zone requirements. The existing septic is in an X flood zone and the Client has indicated that they would like to utilize the existing septic.
Consultant will visually inspect and load test the existing system to evaluate its capacity to serve the new restroom. If it is determined that the system is not capable of serving the new restroom, an additional fee will be required to design a new system.
1) B – Surveys
a) Consultant will coordinate with Survey Sub-Consultant to update the special Purpose Survey with topo extending 25 feet outside of the building envelope.
b) Consultant will coordinate with Universal Engineering to obtain the geotechnical report already completed for this area.
c) Consultant will coordinate with DEP staff to verify changes are not required to the previous study.
Deliverable:
1) A - Opinion as to the acceptability of the existing septic system to handle the new restroom and;
Conceptual Site & Foundation Plans – Consultant shall deliver 60% plans to the client for each building via digital PDF. Plans will include:
Opinion of probable Cost Cover sheet Survey Existing Conditions Best Management Plan
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Demolition Plan Site, Utility & Grading Plan Site Details and General Notes
Foundation/Piling Plans and details;
Exterior Elevations;
Building foundations Cross sections and details;
ADA Ramp Plan with sections & details;
1) B - Completed Survey – Thirty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey for the site via digital PDF, CAD and a Signed and Sealed hard copy.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A -60% Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 6 870
Principal in Charge 195 2 390
Registered Professional Engineer 145 8 1160
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 10 1000
Engineering Technician 80 10 800
Clerical 55 2 110
Total 4790
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Reimbursable Cost: (if applicable)
Subtask 2: 100% documents
Description: Plans completed to 100%.
Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver five hard copy sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Opinion of Probable Cost;
Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan
Subtask 1B - Survey Update
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 2 290
Survey ARS *** 3 Person Field Crew Hr 121.50 0 0
Survey Technician Hr 54.00 6 324
PSM Manager Hr 162 4 648
Total Survey 1262
Description Number @ Total
Postage
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 1A
Total Subtask 1 6052
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Site & Grading Plan Utility Plan Site Details and General Notes
Foundation/Piling Plans and details;
Beam schedules;
Exterior Elevations;
Building foundations Cross sections and details;
ADA Ramp Plan with sections & details;
Specifications
Reimbursable Cost:
Subtask 2 - 100% Plans
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 1 195
Registered Professional Engineer 145 4 580
Registered Engineer Intern 115 6 690
Senior Engineering Designer 100 4 400
Engineering Technician 80 2 160
Clerical 55 1 55
Total 2370
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 3: Permitting
Description:
A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for St Lucie County and Water Management District, Department of Environmental Protection, CCCL and State Fire Marshall approvals. WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.
B – Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five hard copy sets of permit applications with 100% plans.
B – Permit Approvals, Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation
Description Number @ Total
Postage 35 0
Printing 2.30 0.00
Reimbursable Total Cost
Total for Subtask 2
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 3A Permit Applications
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 6 870
Principal in Charge 195 1 195
Registered Professional Engineer 145 4 580
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 4 400
Engineering Technician 80 10 800
Clerical 55 1 55
Total 3360
Subtask 3B Permit Approvals
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 1 195
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 2 200
Engineering Technician 80 2 160
Clerical 55 1 55
Total 1650
Description Number @ Total
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 4: Bidding
Description: Consultant will attend one pre-bid meeting on site and respond in writing to written requests throughout bidding for information and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Postage 35 0
Printing 2.3 0
County Permit fee
500000
Estimated cost to construct @ .0015/$ of cost
FWC Application fee
0 0
Reimbursable Total Cost for 3A
Total for Subtask 3
Subtask 4 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 12 $1740.00
Principal in Charge 195 0 $0.00
Registered Professional Engineer
145 0 $0.00
Registered Engineer Intern 115 0 $0.00
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5A - 5I: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)
Subtask 5A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes PDF within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Senior Engineering Designer 100 8 $800.00
Engineering Technician 80 0 $0.00
Clerical 55 0 $0.00
Total $2540.00
Description Number @ Total Postage Not anticipated
FWC application fee Not anticipated
Overnight Travel
(if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
0.445 $0.00
Reimbursable Total Cost $0.00
Total Subtask 4 $2540.00
Subtask 5A - Pre-Construction Mtg
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5B: Review Contractor submittals
Description:WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 0 0
Registered Professional Engineer 145 0 0
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 0 0
Engineering Technician 80 0 0
Clerical 55 0 0
Total 2080
Description Number @ Total
Postage 0
Printing 0 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 0 0.445 0
Reimbursable Total Cost 0
Total subtask 5A 2080
Subtask 5B - Review Submittals
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5C: Respond to Building Department comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Deliverable: RFI response documents digital or hard copy as required submitted to Building Department.
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 0 0
Registered Professional Engineer 145 0 0
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 6 600
Engineering Technician 80 2 160
Clerical 55 2 110
Total 1620
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 5B 1620
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5D: Assistance During Construction
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.
Subtask 5C
Cost
Weiler Engineering Project Manager 145 3 435
Principal in Charge 195 0 0
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 2 230
Senior Engineering Designer 100 4 400
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1410
Description Number @ Total
Postage 0 35 0
Printing 0 2.30 0
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
Total - 5C 1410
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Subtask 5E: Provide Construction Inspections (Month 1)
Subtask 5D- Respond to RFI’s
Cost
Weiler Engineering Project Manager 145 4 580
Principal in Charge 195 0 0
Registered Professional Engineer 145 4 580
Registered Engineer Intern 115 2 230
Senior Engineering Designer 100 2 200
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1645
Description Number @ Total
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 5D 1645
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) hard copy original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 5E - Month 1 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 1 100
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1292.5
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0 0.445 0
Reimbursable Total Cost
Total Subtask 5E 1292.5
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5F: Construction Inspection (Month 2)
Deliverable: WEC will provide two (2) original signed and sealed hard copy reports to the FDEP
Subtask 5F
Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 1 100
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1292.5
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0 0.445 0
Reimbursable Total
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5G: Construction Inspection (Month 3)
Total Subtask 5F 1292.5
Subtask 5G Month 3 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 1 100
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1292.5
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0 0.445 0
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5H: Construction Inspection (Month 4)
Total Subtask 5G 1292.5
Subtask 5H Month 4 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 1 100
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1292.5
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5I: Construction Inspection (Month 5)
Total Subtask 5H 1292.5
Subtask 5I Month 5 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 1 100
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1292.5
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5J: Substantial Completion Walk-Through w/Punchlist
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist via PDF within one (1) day of Substantial Completion inspection.
Total Subtask 5I 1292.5
Subtask 5J substantial
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Poject Manager 145 6 870
Principal in Charge 195 0 0
Registered Professional Engineer 145 1 145
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 1 100
Engineering Technician 80 0 0
Clerical 55 1 55
Total 2090
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Subtask 5K: Final Completion w/ Certification
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will also provide complete the final completion certification form hard copy and PDF required by FDEP Project Manager.
Mileage (@ $0.445 per
0 0.445 0
Reimbursable Total Cost 0
Total Subtask 5J 2090
Subtask 5K - Final
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Poject Manager 145 2 290
Principal in Charge 195 0 0
Registered Professional Engineer 145 1 145
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 2 200
Engineering Technician 80 0 0
Clerical 55 2 110
Total 1665
Description Number @ Total
Postage 0 35 0
Printing 0
Overnight Travel (if applicable)
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Project Schedule:
Mileage (@ $0.445 per
0 0.445 0
Reimbursable Total Cost 0
Total Subtask 5K 1665
Activity Duration (Calendar Days) Dates to be provided based on date of agreement execution
Subtask 1A - 60% Plans 30
Subtask 1B Survey 30
Subtask 2: 100% plans 28 – includes 7 days for Client review
Subtask 3A: Permit applications 28 – includes 7 days for Client review
Subtask 3B: Permit approvals 60 – includes response for additional information
Subtask 4: Prebid 30
Subtask 5A: Attend Pre-Con Mtg 30
Subtask 5B: Review Submittals 14
Subtask 5C: Respond to Bldg Dept RAI's
Subtask 5D: Respond to Contractor RFI's
180 (Est max overall calendar days;
RFI's will be responded to within 7 days of receipt from Contractor)
Subtask 5E: Provide Construction Inspections w/ (Month 1)
Subtask 5F: Provide Construction Inspections w/ Report (Month 2)
Subtask 5G: Provide Construction Inspections w/ Report (Month 3)
Subtask 5H: Provide Construction Inspections w/ Report (Month 4)
Subtask 5I: Provide Construction Inspections w/ Report (Month 5)
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
** Assumes pre-manufactured building plans available at the date of execution of the task order WEC to coordinate with Leesburg Concrete.
Summary of Fees:
Subtask 5J: Substantial Completion Walk-Through w/Punchlist
Subtask 5K: Final Completion w/ Certification
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A 60% Plans 4790 0
Subtask 1B Survey 1262 0.00
Subtask 2: 100% plans 2370 0
Subtask 3A Permit applications 3360 750
Subtask 3B Permit approvals 1650 0.00
Subtask 4 Pre-Bid 2540 0
Total Design & Permitting $15972.00 $750.00
Subtask 5A - Pre-Construction Meeting
2080 0
Subtask 5B - Submittal Review 1620 0
Subtask 5C - Bldg Dept Response 1410 0
Subtask 5D Assistance during construction
1645 0
Subtask 5E Inspection 1 1292.5 0
Subtask 5F Inspection 2 1292.5 0
Subtask 5G Inspection 3 1292.5 0
Subtask 5H Inspection 4 1292.5 0
Subtask 5I Inspection 5 1292.5 0
Subtask 5J Substantial Completion
2090 0
Subtask 5K Final Completion 1665 0
Total during Construction $16972.50 $0.00
Total Fixed Price Cost: $32944.50
Mr Richard Rowe Fort Pierce Inlet State Park - South Restroom Replacement
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Total Fixed Price Cost: $750.00
Overall Total Cost: $33694.50
File details come from the government source that posted it. Updated .