CN-370000-CN230-T37CO3.pdf
PDF 410 KB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. 03) issued by the Florida Department of Environmental Protection (FDEP) for a contract with Weiler Engineering Corporation. The contract pertains to the Don Pedro Island State Park Visitor Dock Repairs project located at Don Pedro Island State Park in Florida. The FDEP Contract Manager is Ralph Perkins, and the Consultant Representative is Robin Palmer of Weiler Engineering Corporation. The change order was digitally signed and approved by all required parties between November 27, 2023 and December 11, 2023.
The change order modifies the time requirements for Task Assignment No. 37 to permit permitting and design services only, extending the task end date from June 30, 2023 to April 29, 2025—an extension of 485 days. The modification is a no-cost time extension, with no change to the financial terms. The original task amount of $42,159.88 ($1,181.00 reimbursement and $40,978.88 fixed fee) remains unchanged, as does the revised task amount of $46,059.88 ($3,581.00 reimbursement and $42,478.88 fixed fee) including all previous change orders. The project is funded through the State of Florida's FLAIR accounting system under Project No. 61366C. The extension was requested because the project remains in permitting review with the U.S. Army Corps of Engineers (USACE).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 37 03 61366C
Don Pedro Island State Park Visitor Dock Repairs
Weiler Engineering Corporation
Robin Palmer 941.505.1700 rpalmer@weilerengineering.org
Ralph Perkins 850.245.2640 Ralph.Perkins@FloridaDEP.gov
Time only for permitting and design per the attached correspondence dated 11/16/23.
$ 1,181.00 $ 40,978.88 $ 42,159.88 $ 3,581.00 $ 42,478.88 $ 46,059.88
$ 0.00 $ 3,581.00 $ 42,478.88 $ 46,059.88
12/01/2021
06/30/2023
12/31/2023
04/29/2025
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.11.27 09:39:37 -05'00'
Richard Marcil Richard Rene Marcil, III Digitally signed by Richard Rene Marcil, III Date: 2023.11.30 08:40:02 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.11.30 12:52:12 -05'00'
Jeff Weiler, P.E. Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.12.04 11:53:45 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.12.11 16:02:53 -05'00'
61366C
$ 0.00
From: Robin Palmer To: Marcil, Richard Cc: Carron, Theresa Subject: Don Pedro Visitor Dock-CN 37 Request for Time Extension Date: Thursday, November 16, 2023 12:06:43 PM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Good afternoon Rene, TA 37 for the Don Pedro Visitor Dock Replacement expires on 12/31/2023. This project is still in permitting review with USACE so we are requesting a No Cost Time Extension (CO3) that extends to our continuing services end date of April 29, 2025. Please let me know if you have any questions.
Thank you, Robin Palmer, P.E.Environmental Engineer