About this file

This is a Task Assignment Notification Form and associated proposal from the Florida Department of Environmental Protection (FDEP) Contract CN230, Task Assignment 27, for design and permitting services at Charlotte Harbor Preserve State Park. The consultant is Weiler Engineering Corporation, with Robin Palmer serving as the consultant representative and Alyssa Skehan as the FDEP contract manager. The project involves modifications to the Old Datsun Trail Parking and Parking Entrance at the park located in Punta Gorda, Florida.

The scope of work encompasses a comprehensive engineering design and permitting process with twelve subtasks spanning survey, preliminary design, 60% and 100% plan development, permit applications and approvals, and construction-phase services. The project aims to increase parking capacity by 12 to 15 shell parking spaces and add one ADA-compliant asphalt parking spot. The fixed price cost is $27,376.00, with cost reimbursement not to exceed $4,190.00, for a total task amount of $31,566.00. The completion date is June 30, 2022, with work commencing upon execution. Services include coordination with the City of Punta Gorda, Charlotte County, and Southwest Florida Water Management District for required permits. Payment will be made upon FDEP approval of deliverables for each subtask. The full scope includes design phases, permitting, bidding assistance, pre-bid and pre-construction meetings, submittal review, construction phase response services, and final completion certification.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 27 FDEP 61305C

Charlotte Harbor Preserve State Park Old Datsun Trail Parking and Parking Entrance

Weiler Engineering Corporation

Robin Palmer 941-505-1700 rpalmer@weilerengineering.org

Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov

Consultant to design and provide all applicable permits for the modification of the parking area at the park. Design to include an increase of 12 to 15 shell parking spaces and one ADA asphalted parking spot as per the proposal dated 11/10/20.

Wayne Thomas

Upon execution $ 27,376.00 6/30/2022 $ 4,190.00

$ 31,566.00

Greg Turral

Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2020.11.12 10:09:24 -05'00'

Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2020.11.12 10:29:45 -05'00'

Jeff Weiler R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2020.11.12 14:34:01 -05'00'

Michael W. Foster Jr. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2020.11.16 13:33:08 -05'00'

61305C 37504000029 088130/21 675002 U3200 131500 XR $ 31,566.00

$ 31,566.00

Gregory Turral Digitally signed by Gregory Turral Date: 2020.11.12 10:05:23 -05'00'

October 9, 2020 - Revision 3 - November 10, 2020

Mr. Wayne Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: Charlotte Harbor Preserve Parking - Contract 230, TA 24

Dear Mr. Thomas;

We are pleased to submit this proposal for design and permitting to modify the existing parking facilities at the Charlotte Harbor Preserve State Park.

Our general understanding of the project includes:

• FDEP wishes to increase this size to 12-15 parking spaces.

◦ New parking is preferred to be shell

◦ New fence to be placed around the parking lot area with walk through openings

◦ Existing gate to be relocated for park driveway access

◦ Driveway should be assessed to make sure turning radius and width is appropriate

• FDEP wishes to keep the existing asphalt parking spaces for ADA parking if possible.

• Burnt Store Rd is currently under construction and lanes are being added/shifted and utilities are being shifted.

• Parking orientation may be parallel or perpendicular to Burnt Store Rd.

• New park information kiosk to be added to replace the existing

• 1 Gopher tortoise on-site, but will be outside of project area

◦ FDEP biologist to perform any environmental and endangered species assessments

◦ Known protected species on-site including a caracara, indigo snakes, and bonneted bats but it is the intent to avoid any mitigation

Permitting

• This is in the City of Punta Gorda.

• The entrance will require a Right of Way permit from Charlotte County

October 9, 2020 - Rev 3- 11/10/2020 Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

• A Stormwater Management permit from the Southwest Florida Water Management District

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Charlotte Harbor Preserve Parking Area Renovations

Contract Number 230, Task Assignment Number

Subtask 1: Survey Description: The Weiler Engineering Corporation (Consultant) will coordinate with a Florida Registered Engineer to prepare a special purpose survey adequate for design and permitting.

Deliverable: Consultant will provide a Signed and Sealed Special Purpose survey (Not a Boundary Survey) in PDF format via email to the Bureau of Design and Construction (BDC).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1 - Survey

Firm Name Position Classification Unit Unit Rate Numbe r Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 2 290

Survey ARS *** 3 Person Field Crew Hr 121.50 8 972

Survey ARS *** Survey Technician Hr 54.00 8 432

Survey ARS *** PSM Manager Hr 162 6 972

Survey ARS *** Total Survey 2666

Postage

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 1 Survey

$2666.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Subtask 2: Preliminary Design - 30% Plans Description: The Weiler Engineering Corporation (Consultant) shall conduct one site visit with staff to inspect the parking area and entrance to Burnt Store Road and to discuss proposed ideas, research existing/available data and permits, conduct a pre-application meeting with the City, County and Water Management District.

Deliverable: Consultant will provide a summary of meetings with local and State regulatory agencies outlining permit requirements, plans prepared to 30% and a preliminary opinion of probable cost in PDF format via email to the Bureau of Design and Construction (BDC).

Cover sheet Existing Conditions Special Purpose Survey Best Management Plan Demolition Plan Site Plans Site & Entrance Details

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 2 - Preliminary Design

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Weiler Engineering Principal in Charge 195 2 $390.00

Weiler Engineering Registered Professional Engineer 145 6 $870.00

Weiler Engineering Registered Engineer Intern 115 8 $920.00

Weiler Engineering Senior Engineering Designer 100 22 $2200.00

Weiler Engineering Engineering Technician 80 26 $2080.00

Weiler Engineering Clerical 55 2 $110.00

Total $7440.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Reimbursable Cost: (if applicable)

Subtask 3: 60% documents Description: Plans completed to 60% incorporating comments from 30%.

Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost;

Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plans Site Details and General Notes

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:

Postage

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 2 Preliminary Design

$7440.00

Subtask 3– 60% Plans

Firm Name Position Classification

Hour ly

Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 7 $1015.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Reimbursable Cost:

Subtask 4: 100% documents Description: Plans completed to 100%.

Deliverable: Consultant shall deliver five sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Updated Opinion of Probable Cost;

Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan

Principal in Charge 195 1 $195.00 Registered Professional Engineer

145 5 $725.00

Registered Engineer Intern 115 9 $1035.00

Senior Engineering Designer 100 10 $1000.00

Engineering Technician 80 24 $1920.00

Clerical 55 2 $110.00

Total $6000.00

Postage No prints/provided digitally via email

Printing Not anticipated

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

$0.00

Total Subtask 3 $6000.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Site & Grading Plan Site Details and General Notes Specifications

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:

Reimbursable Cost:

Subtask 5: Permitting

A – Permit Applications, Subtask 4 - 100 % Plans

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 4 $580.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 14 $1400.00

Engineering Technician 80 20 $1600.00

Clerical 55 2 $110.00

Total $5155.00

Postage 3 Fed-x at $35 = $105 105 Printing 400 sheets @ $2.30 per sheet

Overnight Travel (if applicable)

Not anticipated

Reimbursable Total Cost

$1025.00

Total for Subtask 4 $6180.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Description: Consultant will assist Client to submit permit applications for County - Driveway, City - Development Review Committee and State - Southwest Florida Water Management District permits.

Deliverable: Consultant shall deliver five sets of permit applications with 100% plans.

B – Permit Approvals, Description Consultant will coordinate with Client to respond to regulatory requests for additional information through approval.

Deliverable: Consultant will provide via email to the BDC the completed permits for the County, City and SWFWMD for site approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 5A Permit Applications

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 7 $1015.00

Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 5 $725.00

Registered Engineer Intern 115 9 $1035.00

Senior Engineering Designer 100 8 $800.00

Engineering Technician 80 8 $640.00

Clerical 55 3 $165.00

Total $4575.00

Subtask 5B Permit Approvals

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Reimbursable Cost:

Subtask 6: Assistance during bidding

Description: Consultant will respond to bidders’ questions and provide clarifications during bidding.

Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Principal in Charge 195 0 $0.00 Registered Professional Engineer 145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 5 $500.00

Engineering Technician 80 4 $320.00

Clerical 55 1 $55.00

Total $1540.00

Postage 3 Fed-x at $35 $105.00

Printing 200 sheets @ $2.30/ sheet

$460.00

County Permits Estimate $1000.00

City DRC $1500.00

SFWMD Exemption $100.00

Reimbursable Total Cost $3165.00

Total for Subtask 5 $9280.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Fixed Price Cost:

Reimbursable Cost:

Subtask 7: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.

Subtask 6 Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1580.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage ($0.445 per mile)

Not anticipated

Reimbursable Total Cost

$0.00

Total for Subtask 6 $1580.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Reimbursable Cost:

Subtask 7 - Pre-bid

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern 115 4 $460.00

Senior Engineering Designer 100 0 $0.00

Engineering Technician 80 4 $320.00

Clerical 55 0 $0.00

Total $1360.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated $0.00

Reimbursable Total Cost

$0.00

Total Subtask 7

$1360.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Subtask 8: Attend Pre-Construction Meeting Description: WEC staff will attend one pre-construction meeting on site, respond to questions and prepare minutes.

Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 8 - Pre-construction Mtg

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 0 $0.00

Senior Engineering Designer

100 8 $800.00

Engineering Technician 80 8 $640.00

Clerical 55 0 $0.00

Total $2600.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0

Reimbursable Total Cost

$0.00

Total Subtask 8 $2600.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Subtask 9: Review Contractor submittals

Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.

Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 9 - Submittal Review

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 8 $920.00

Senior Engineering Designer

100 8 $800.00

Engineering Technician

80 2 $160.00

Clerical 55 2 $110.00

Total $2280.00

Postage Not anticipated (all deliverables in digital form only)

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable)

Not anticipated

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Subtask 10: Assistance during construction (3 Months)

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Deliverable: Correspondence with Contractor and regulatory agencies provide via PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Mileage (@ $0.445 per mile)

Not anticipated

Reimbursable Total Cost

$0.00

Total Subtask 9 - Submittals

$2280.00

Subtask 10

Firm Name Position Classification Hourly Rate

Ho urs

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 4 $580.00

Registered Engineer Intern

115 6 $690.00

Senior Engineering Designer

100 6 $600.00

Engineering Technician 80 0 $0.00

Clerical 55 2 $110.00

Total $3045.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Subtask 11: Substantial Completion Walk-Through w/Punchlist Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.

Deliverable: WEC will provide comments and input on punch list within one (1) day of Substantial Completion inspection.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Postage Not anticipated

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost $0.00

Total Subtask 10 $3045.00

Subtask 11

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 1 $100.00

Engineering Technician 80 4 $320.00

Clerical 55 0 $0.00

Total $1800.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Reimbursable Cost:

Subtask 12: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion inspection of the site with WEC representative attending the Final Completion inspection.

Deliverable: WEC will prepare final certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost

$0.00

Total Subtask 11 $1800.00

Subtask 12 - Final

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Prroject Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer

100 8 $800.00

Engineering Technician 80 8 $640.00

Clerical 55 1 $55.00

Total $3285.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Reimbursable Cost:

Project Schedule:

Summary of Fees:

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost

$0.00

Total Subtask 12 $3285.00

Activity Duration (Calendar Days) Dates to be based on date of execution of task order

Subtask 1 Survey 30

Subtask 2 Preliminary 30

Subtask 3: 60% plans 30 - includes 7 days for Client review

Subtask 4: 100% plans 30 – includes 7 days for Client review

Subtask 5A: Permit applications 30 – includes 7 days for Client review

Subtask 5B: Permit approvals 60 – includes response for additional information

Subtask’s 6-12 240

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 1A - Survey $2666.00 $0.00

Subtask 2 - 30% Plans $7440.00 $0.00

Subtask 3: 60% plans $6000.00 $0.00

Subtask 4: 100% plans $5155.00 $1025.00

Subtask 5A Permit applications $4575.00 $3165.00

Subtask 5B Permit approvals $1540.00 $0.00

Subtotal Design & Permitting $27376.00 $4190.00

Total Design & Permitting $31566.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas Charlotte Harbor Preserve Parking

CN 230 TN

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

Subtask 6: Assistance during bidding

$1580.00 $0.00

Subtask 7: Pre-bid meeting $1360.00 $0.00 Subtask 7A: Attend Pre-Con Mtg $2600.00 $0.00

Subtask 7B: Review Submittals $2280.00 $0.00

Subtask 7C: Assistance during Construction - 3 Months

$3045.00 $0.00

Subtask 7D: Substantial Completion Walk-Through w/ Punchlist - Site

$1800.00 $0.00

Subtask 7E: Final Completion w/ Certification

$3285.00 $0.00

Subtotal Construction Services $15950.00 $0.00

Total Fixed Price $43326.00

Total Reimbursable Cost $4190.00

Total Overall Cost $47516.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702