CN-370000-CN230-T34.pdf
PDF 4 MB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This is a Task Assignment Notification Form and supporting proposal from the Florida Department of Environmental Protection (FDEP) for design and permitting services related to the Rookery Bay Preserve State Park Maintenance Building Replacement project. The consultant performing the work is Weiler Engineering Corporation, with Jeff Weiler serving as the consultant representative. The project is located at Shell Island in Collier County, Florida, and is managed by FDEP Project Manager Richard J. Rowe and Contract Manager Jeffrey Whitfield. The work was authorized under FDEP Contract No. CN230, Task Assignment No. 34, with project identification number RBF1052.
The contract encompasses comprehensive engineering design and permitting services to replace a pole barn and kayak cover facility damaged by Hurricane Michael, with construction anticipated for January 2022. Services include civil engineering, building foundation and structural design, survey work, geotechnical investigation, lead and asbestos testing, and permit applications and approvals. The contract is structured in four primary subtasks: (1) preliminary design including 30% plans, surveys, and lead/asbestos assessment ($19,217.68); (2) 60% design documents ($6,505.00); (3) 100% design documents with specifications ($2,115.00); and (4) permitting services ($7,055.00). The total contract amount is $34,892.68, consisting of $31,637.68 in fixed-price costs and $3,255.00 in reimbursable costs. The project completion date is December 30, 2022, and payment will be made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 34 FDEP RBF1052
Shell Island Replacement Pole Barn and Kayak Cover
Weiler Engineering Corp.
Jeff Weiler 941-505-1700 weiler7@mac.com
Alyssa Skehan or successor 850-245-2781 Alyssa.Skehan@FloridaDEP.gov
Design and permitting services to replace a pole barn and Kayak cover damaged by Hurricane Michael. Please see the agreement dated 8/11/2021 for reference.
Richard J. Rowe or Successor
Upon Execution $ 31,637.68 12/30/22 $ 3,255.00
$ 34,892.68
Lisa Yarborough Lisa Yarborough Digitally signed by Lisa Yarborough Date: 2021.08.31 12:33:58 -04'00'
Richard J. Rowe Richard J. Rowe Digitally signed by Richard J.
Rowe Date: 2021.09.01 08:17:37 -04'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2021.09.01 12:00:57 -04'00'
Jeff Weiler R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2021.09.01 12:19:45 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2021.09.15 13:41:07 -04'00'
RBF1052 F1052 37538020000 102080/00 261019 U3210 241000 LH $ 34,892.68
$ 34,892.6837202261019375004000010208000
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
May 24, 2021 - Revision 2 - August 11, 2021
Mr. Richard Rowe
Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Rookery Bay Preserve State Park - Maintenance Building Replacement
Dear Mr. Rowe;
Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to replace the two restroom/bathhouse facilities in Rookery Bay Preserve State Park.
• Project is funded by NOAA for park improvements for hurricane resiliency
◦ Grant expires in August 2023
• Construction is anticipated for January 2022
• Project Components:
◦ Survey
◦ Geotech
◦ Lead & Asbestos Testing (demolishing existing building)
◦ Replace the existing building with a prefabricated structure
▪ New pre-fab to match existing with 2 bay doors on front and 2 bay doors on the back generally replicating existing building.
▪ New kayak cover to be added (Prefabricated) similar to existing conditions
▪ Flood proofing likely required.
• Site is AE 7
• Lidar was obtained and the existing ground elevation ranges between 2.5’- 4.5’ NAVD
▪ New building to contain 4000 pound chain hoist mounted to a track running from front to back
▪ Existing boat lift in front of the existing building to remain
▪ Building location will be behind the existing building.
• TBD based on existing grade and FEMA requirements
May 24, 2021 - Rev 2 - 08/11/2021 Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
▪ New building to have an eye wash station and sink if it does not require additional treatment
• Water service to be capped
• 500gal existing water tank is located at the adjacent building with
RO plant that feeds the water service
• 220 electric is available under existing conditions
• Project Permitting:
◦ Project is landward of CCCL, no CCCL permit required
◦ SFWMD Verification of Exemption
◦ Collier County: Insubstantial Change to a Site Development Plan and Special
Treatment Permit
• Building Comments:
◦ No bathroom.
◦ No Fire Sprinklers because building is less than 5000 sf
◦ Existing 2,500SF building to be demolished
• A separate project by others will be completed in the area with (2) 10’x15’ sheds
• Existing building has 2 bay doors on front and 2 bay doors on back. New building to match.
◦ Replace existing kayak cover (overhang on side)
Our services will include:
A. Civil Engineering
Civil Engineering includes providing all site design necessary to permit through both local government and Water Management District for an exemption (or Florida Department of Environmental Protection (FDEP), where appropriate). WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.
B. Building foundation Design/Structural Engineering
WEC will coordinate with the building manufacturer and prepare plans and specifications for the foundations to support the new building of sufficient detail to allow for bidding and construction. And; a steel column and beam system to mount a +/- 4000 pound hoist.
And; design of a small second story storage facility with stairs.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services tasks identified below:
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
Maintenance Building Replacement
Rookery Bay Preserve State Park
Contract Number 230, Task Assignment Number 34
Subtask 1: Preliminary
1) A - Preliminary investigation,
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP and the Local Building Department.
c) Consultant will discuss with Building department whether or not a small AC unit for climate controlled storage upstairs will require addition permitting
d) Consultant will prepare 30% plans including:
i) Site Plan
ii) Floor plan of proposed storage area
1) B – Surveys
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topo extending 25 feet outside of the building envelope.
1) C – Lead & Asbestos Survey
a) Consultant will coordinate with Geotechnical Sub-Consultant to prepare a Lead and asbestos report.
b) Consultant will coordinate with Geotechnical Sub-Consultant to provide a subsurface investigation in the area of the proposed building.
Deliverable:
1) A - Preliminary investigation, Conceptual Site & Foundation Plans – Consultant shall deliver 30% plans to the client for each building via digital PDF. Plans will include:
Opinion of probable cost Cover sheet Survey Existing Conditions Site Plan Floor Plan Front and Rear Elevations
1) B - Surveys
Completed Survey – Thirty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey for each site (2) via digital PDF, CAD and a Signed and Sealed copy.
1) C – Lead/Asbestos Survey
Completed asbestos and lead based paint assessment and report via PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A - Preliminary Design 30% Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Weiler Engineering Project Manager 145 11 1595
Principal in Charge 195 2 390
Registered Professional Engineer 145 8 1160
Registered Engineer Intern 115 10 1150
Senior Engineering Designer 100 30 3000
Engineering Technician 80 30 2400
Clerical 55 1 55
Total - 30% Plans 9750
Subtask 1B - Survey
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 2 290
3 Person Field Crew Hr 121.50 8 972
Survey Technician Hr 54.00 8 432
PSM Manager Hr 162 10 1620
Total Survey 3314
Subtask 1C - Lead/Asbestos
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 2 290
Geotech Universal *** Senior Geotechnical Engineer. PE
Hr 165.84 4 663.36
Hr 94.50 12 1134
Staff Engineer, EI Hr 68.46 18 1232.28
Total Lead/Asbestos 3319.64
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
]Reimbursable Cost: (if applicable)
Subtask 1D - Geotech
Firm Name Position Classification Unit Unit Rate
Number Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 3 $435.00
Universal Engineering
Senior Geotechnical Engineer. PE
Hr 165.84 4 $663.36
Project Engineer Hr 94.5 8 $756.00
Staff Engineer Hr 68.46 8 $547.68
CAD Drafting Hr 54.00 8 $432.00
Total Geotech $2834.04
Description Number @ Total
Postage 0
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
0 130 0
Reimbursable Total Cost 1A
Total Subtask 1 19217.68
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Subtask 2: 60% documents
Description: Plans completed to 60% incorporating comments from 30%.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost to construct;
Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes
Foundation/Piling Plans and details;
Plan and details for beam & Column hoist rack.
Floor plan, sections and details for second story storage area
Exterior Elevations;
Building Cross sections and details;
Electrical Plans
Subtask 2 - 60% Plans
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 4 580
Principal in Charge 195 1 195
Registered Professional Engineer 145 3 435
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 24 2400
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Subtask 3: 100% documents
Description: Plans completed to 100%.
Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver five sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Opinion of Probable Cost to construct;
Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes
Foundation/Piling Plans and details;
Plan and details for beam & Column hoist rack.
Floor plan, sections and details for second story storage area
Exterior Elevations;
Building Cross sections and details;
Electrical Plans Specifications
Engineering Technician 80 24 1920
Clerical 55 1 55
Total 6505
Total for Subtask 2
Subtask 3 - 100% Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Reimbursable Cost:
Subtask 4: Permitting
Description:
4) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for County and State approvals. WEC will complete applications for the Water Management District for exemption, and Collier County for approval for Insubstantial Change to a Site Development Plan and Special Treatment Permit
WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.
B – Permit Approvals, Principal in Charge 195 1 195
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 4 400
Engineering Technician 80 2 160
Clerical 55 1 55
Total 1850
Description Number @ Total
Postage 1 35 35
Printing 100 2.30 230
Overnight Travel
(if applicable)
Reimbursable Total Cost
Total for Subtask 3
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
4) A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five sets of permit applications with 100% plans.
4) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation
Subtask 4A Permit Applications
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 1 195
Registered Professional Engineer 145 3 435
Registered Engineer Intern 115 2 230
Senior Engineering Designer 100 8 800
Engineering Technician 80 8 640
Clerical 55 1 55
Total 2645
Subtask 4B Permit Approvals
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Reimbursable Cost:
Schedule
Principal in Charge 195 1 195
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 2 230
Senior Engineering Designer 100 2 200
Engineering Technician 80 2 160
Clerical 55 1 55
Total 1420
Description Number @ Total
Postage 1 35 35
Printing 100 2.3 230
County Permit fee
Estimated based on the value of construction
FWC Application fee
1 225 225
Reimbursable Total Cost for 4A
Total for Subtask 4
Activity Duration (Calendar Days) Dates to be based on date of execution of task order
Subtask 1A ** Preliminary 30
Subtask 1B Survey 45
Subtask 1C Lead/Asbestos 30
Subtask 1D - Geotech 30
Subtask 2: 60% plans 28 - includes 7 days for Client review
Subtask 3: 100% plans 28 – includes 7 days for Client review
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Summary of Fees:
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Subtask 4A: Permit applications 28 – includes 7 days for Client review
Subtask 4B: Permit approvals 60 – includes response for additional information
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A 30% Plans 9750 0
Subtask 1B Survey 3314 $0.00
Subtask 1C Lead/Asbestos 3319.64 $0.00
Subtask 1D Geotech $2834.04 0.00
Subtask 2: 60% plans 6505 $0.00
Subtask 3: 100% plans 1850 265
Subtask 4A Permit applications 2645 2990
Subtask 4B Permit approvals 1420 $0.00
Total Fixed Price Cost: $31637.68
Total Fixed Price Cost: $3255.00
Overall Total Cost: $34892.68
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Labor Rates Surveying Unloaded
Labor Benefits Fringe Profit Rate Loaded
Three-Person Field Crew $45.00 $18.00 $54.00 $4.5
0 $121.50
Two-Person Field Crew $32.00 $12.80 $38.40 $3.2
0 $86.40
GIS Technician $22.50 $9.00 $27.00 $2.2
5 $60.75
Survey Technician $20.00 $8.00 $24.00 $2.0
0 $54.00
CADD Technician $18.50 $7.40 $22.20 $1.8
5 $49.95
Professional Surveyor & Mapper Manager $60.00 $24.00 $72.00
$6.0 0 $162.00
Professional Surveyor & Mapper $33.50 $13.40 $40.20 $3.3
5 $90.45
Clerical $16.50 $6.60 $19.80 $1.6
5 $44.55
Fringe Benefit Rate 40.00%
General Overhead Rate 120.00%
Profit Percentage on Labor and Overhead 10.00%
Total Muliplier 2.7
Mr Richard Rowe Rookery Bay Preserve - Maintenance Bldg. Replacements
Labor Rates – Universal Engineering