About this file

This is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) establishing a professional services contract with Weiler Engineering Corporation for design and engineering services related to the Mangrove Trail Boardwalk replacement project at John Pennekamp Coral Reef State Park in the Florida Keys. The contract is designated as FDEP Contract No. CN230, Task Assignment No. 69, with a project number 61489C and was executed on June 30, 2023, with a completion date of September 30, 2025.

The scope of work encompasses professional services for the complete replacement of an approximately 1,500-foot wood boardwalk, including environmental assessment, geotechnical investigation, survey work, structural and civil engineering design, permitting, and construction administration. The contract is structured in multiple subtasks spanning conceptual design, 60% and 100% design documents, permit applications and approvals, pre-bid and pre-construction meetings, contractor submittal review, regulatory agency response, eight monthly construction inspections, and substantial and final completion inspections. The total contract value is $143,852.64, consisting of $142,090.64 in fixed-price costs and $1,762.00 in reimbursable costs not to exceed. Payment is contingent upon FDEP approval of deliverables for each subtask. The project schedule extends over 600 calendar days from execution, with design and permitting activities anticipated to conclude approximately 210 days after execution, followed by construction phase services spanning an estimated eight months.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
CN-370000-CN230-T53CO1.pdf PDF
CN-370000-CN230-T57.pdf PDF
CN-370000-CN230-T59.pdf PDF
CN-370000-CN230-T60.pdf PDF
CN-370000-CN230-T64.pdf PDF
CN-370000-CN230-T66.pdf PDF
CN-370000-CN230-T7.pdf PDF
CN-370000-CN230-T70.pdf PDF
CN-370000-CN230-T72.pdf PDF
CN-370000-CN230-T75.pdf PDF
CN-370000-CN230-T8.pdf PDF
CN-370000-CN230-T80.pdf PDF
CN-370000-CN230-T82CO1.pdf PDF
CN-370000-CN230-T86.pdf PDF
CN-370000-CN230-T87.pdf PDF
CN-370000-CN230-T89.pdf PDF
CN-370000-CN230-T90.pdf PDF
CN-370000-CN230-TA30.pdf PDF
CN-370000-CN230-TA5CO1.pdf PDF
CN-370000-CN230.pdf PDF
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T21CO1.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 69 FDEP-BDC 61489C

John Pennekamp Coral Reef State Park Mangrove Trail Boardwalk

Weiler Engineering Corporation

Robin Palmer, PE 941-505-1700 rpalmer@weilerengineering.org

Ralph Perkins 850-245-2560 ralph.perkins@floridadep.gov

Professional services to replace the Mangrove Trail Boardwalk including environmental, geotechnical, survey, structural & civil engineering, permitting and construction administration per the attached proposal dated 6/21/2023.

Theresa Carron

6/30/2023 $ 142,090.64 9/30/2025 $ 1,762.00

$ 143,852.64

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.26 09:25:32 -04'00'

Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.06.26 09:33:17 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.26 12:55:56 -04'00'

R. Jeff Weiler, PE Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.06.27 09:33:57 -04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.06.30 15:18:03 -04'00'

61489C 37505018015 080039/23 423001 U3200 134000 QK $ 143,852.64

$ 143,852.64

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

June 2, 2023 - Revision 2 - June 21, 2023

Ms. Theresa Carron

Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399

RE: John Pennekamp State Park - Boardwalk Replacement, CN - 230, TA - 69

Dear Ms. Carron, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to demolish and replace the existing boardwalk and accessory structures identified below.

June 2, 2023 - Rev 2 - 06/21/23 Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Our services will include:

Design and permitting to remove the existing +/- 1500 ft. long wood boardwalk and replace it in the same place.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, R. Jeff Weiler, P.E.

President

The Weiler Engineering Corporation

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Boardwalk Replacement

John Pennekamp State Park

Contract Number 230, Task Assignment Number 69

Subtask 1: Conceptual Design

1) A - Conceptual Design

a) WEC will conduct one site visit.

b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP, the USACOE and the Local Building Department.

c) Consultant will prepare conceptual site plans & include typical sections.

1) B – Surveys

a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topo extending 5 feet each side of the existing boardwalk. To be cleared by Client.

1) C –Geotechnical Reports (Universal Engineering)

a) Consultant will coordinate with Geotechnical Sub-Consultant to prepare a geotechnical Report recommending piling depths and seasonal high water elevation.Consultant will coordinate with a consultant to complete lead and asbestos reports for the existing structure.

1) D – Lead/Asbestos Reports (Universal Engineering)

a) Consultant will coordinate with Sub-consultant to prepare lead and asbestos reports on existing structure.

1) E – FLUCFCS Map & Listed Species

a) Consultant will coordinate with Sub-consultant to prepare a FLUCFCS Map and Listed Species Report.

Deliverable:

1) A - Conceptual Design, Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Conceptual Site & Structural Plans – Consultant shall deliver conceptual plans to the client via digital PDF. Plans will include:

Cover sheet Survey Existing Conditions Site Plan Boardwalk Plan View Typical Sections Opinion of probable cost

1) B - Surveys

Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey via digital PDF, CAD and a Signed and Sealed copy.

1) C –Geotechnical Reports

Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report recommending piling depths and seasonal high water elevation via digital PDF.

1) D –Lead/Asbestos Reports

Lead/Asbestos Report – Sixty days from execution of task assignment, consultant shall deliver a completedLead and Asbestos report via digital PDF

1) E –FLUCFCS & Listed Species Reports

FLUCFCS Map & Listed Species Report – Sixty days from execution of task assignment, consultant shall deliver a completed report via digital PDF

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1A - Conceptual Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 20 2900

Weiler Engineering Principal in Charge 195 1 195

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Weiler Engineering

Registered Professional Engineer 145 14 2030

Weiler Engineering Registered Engineer Intern 115 24 2760

Weiler Engineering Senior Engineering Designer 100 60 6000

Weiler Engineering Engineering Technician 80 80 6400

Weiler Engineering Clerical 55 8 440

Total 20725

Subtask 1B - Survey

Firm Name Position Classification Unit Unit Rate Numbe r Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

CHW 3 Person Field Crew Hr 177.54 16 2840.64

CHW Project Surveyor Hr 74.75 16 1196

CHW Senior CAD/GIS Hr 103.13 8 825.04

CHW Professional Surveyor & Mapper

Hr 163.93 4 655.72

Total Survey 6097.4

Subtask 1C Geotech

Firm Name Position Classification Unit Unit Rate Numbe r Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 6 870

Geotech Universal

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Universal Senior Project Engineer Hr 165.84 32 5306.88

Universal Project Engineer Hr 94.50 32 3024

Universal Staff Engineer Hr 68.46 32 2190.72

Universal CAD Drafting Hr 54.00 16 864

Total Geotech 12255.6

Subtask 1D - Lead/Asbestos survey

Firm Name Position Classification

Unit Rate Hours Total Fixed Price Cost

Weiler Engineering Registered Professional Engineer

145 4 $580.00

Weiler Engineering Registered Engineer Intern

115 8 $920.00

Universal Engineering Senior Geotechnical Engineer. PE

165.84 24 $3980.16

Universal Engineering Sr Engineering Technician

49.14 42 $2063.88

Total Lead/ Asbestos Survey

$7544.04

Total Subtask 1D $7544.04

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Reimbursable Cost: (if applicable)

Subtask 1E - FLUCFCS & Listed Species

Firm Name Position Classification

Unit Rate Hour s

Total Fixed Price Cost

Weiler Engineering Registered Professional Engineer

145 4 $580.00

Weiler Engineering Registered Engineer Intern

115 12 $1380.00

Passaarella Senior Ecologist 149.50 16 $2392.00

Passaarella Ecologist 104.65 32 $3348.80

Passaarella Design/GIS 89.70 24 $2152.80

Total Sub-task E

FLUCFCS &

Listed Species

$9853.60

Postage

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost $0.00

Total Subtask 1E $9853.60

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Reimbursable Cost: (if applicable)

Subtask 2: 60% documents

Description: Plans completed to 60% incorporating comments from 30%.

Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost;

Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes

Foundation/Piling Plans and details;

Beam schedules;

ADA Ramp Plan with sections & details;

Description Number @ Total

Postage

Printing

Overnight Travel

(if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost 1A

Total Subtask 1 39078

Subtask 2 - 60% Plans

Robinson_MS Text Box 56,475.64

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 3: 100% documents

Description: Plans completed to 100%.

Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Updated Opinion of Probable Cost;

Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Utility Plan Site Details and General Notes

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 20 2900

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering

Registered Professional Engineer 145 16 2320

Weiler Engineering Registered Engineer Intern 115 24 2760

Weiler Engineering Senior Engineering Designer 100 60 6000

Weiler Engineering Engineering Technician 80 80 6400

Weiler Engineering Clerical 55 8 440

Total 21015

Total for Subtask 2

21015

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Foundation/Piling Plans and details;

Beam schedules;

ADA Ramp Plan with sections & details;

Specifications

Reimbursable Cost:

Subtask 3 - 100% Plans

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 14 2030

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering

Registered Professional Engineer 145 12 1740

Weiler Engineering Registered Engineer Intern 115 18 2070

Weiler Engineering Senior Engineering Designer 100 40 4000

Weiler Engineering Engineering Technician 80 56 4480

Weiler Engineering Clerical 55 4 220

Total 14735

Description Number @ Total

Postage 1 35 35

Printing 40 2.30 92

Reimbursable Total Cost

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 4: Permitting

Description:

4) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for exemption, the USACE, the State Fire Marshall, Building for site development approval. WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.

4) B – Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.

Deliverable:

4) A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five sets of permit applications with 100% plans.

4) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation

Total for Subtask 3

14862

Subtask 4A Permit Applications

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 12 1740

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering Registered Professional Engineer 145 20 2900

Weiler Engineering Registered Engineer Intern 115 20 2300

Weiler Engineering Senior Engineering Designer 100 40 4000

Weiler Engineering Engineering Technician 80 64 5120

Weiler Engineering Clerical 55 5 275

Total 16530

Subtask 4B Permit Approvals

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 12 1740

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering Registered Professional Engineer 145 8 1160

Weiler Engineering Registered Engineer Intern 115 16 1840

Weiler Engineering Senior Engineering Designer 100 24 2400

Weiler Engineering Engineering Technician 80 24 1920

Weiler Engineering Clerical 55 1 55

Total 9310

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 5: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.

Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Description Number @ Total

Postage 1 35 35

Printing 200 2.3 460

Permit application fees estimate

1 1000 1000

Reimbursable Total Cost for 4A

Total for Subtask 4

27335

Subtask 5 - Pre-bid

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Weiler Engineering Principal in Charge 195 0 $0.00

Weiler Engineering Registered Professional Engineer

145 0 $0.00

Weiler Engineering Registered Engineer Intern 115 8 $920.00

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Subtask 6A - 6N: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)

Subtask 6A: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Weiler Engineering Senior Engineering Designer 100 8 $800.00

Weiler Engineering Engineering Technician 80 8 $640.00

Weiler Engineering Clerical 55 0 $0.00

Total $3520.00

Description Number @ Total Postage Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost $0.00

Total Subtask 5 $3520.00

Subtask 6A - Pre-Construction Mtg

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6B: Review Contractor submittals

Description:WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 0 0

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 2080

Description Number @ Total

Postage 0

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile) 0

Reimbursable Total Cost 0

Total subtask 6A 2080

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6C: Respond to Building Department comments

Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.

Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.

Subtask 6B - Review Submittals

Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 12 1200

Weiler Engineering Engineering Technician 80 2 160

Weiler Engineering Clerical 55 2 110

Total 2680

Description Number @ Total

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 6B 2715

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Deliverable: RFI response documents submitted to Building Department.

Subtask 6D: Respond to Contractor RFI's

Subtask 6C

Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 1 145

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 1 55

Total 1980

Description Number @ Total

Postage 35 0

Printing 2.30 0.00

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated

Reimbursable Total Cost

Total - 6C 1980

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Subtask 6D- Respond to RFI’s

Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 2 290

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 4 220

Total 2520

Description Number @ Total

Postage 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6E: Provide Construction Inspections (Month 1)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of each inspection.

Total Subtask 6D 2520

Subtask 6E - Month 1 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6F: Construction Inspection (Month 2)

Reimbursable Total Cost

Total Subtask 6E 1007.5

Subtask 6F

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Description Number @ Total

Postage 35 0

Printing 0

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6G: Construction Inspection (Month 3)

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost

Total Subtask 6F 1007.5

Subtask 6G Month 3 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 1007.5

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6H: Construction Inspection (Month 4)

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 7G 1007.5

Subtask 6H - Inspection Month 4

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6I: Construction Inspection (Month 5)

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost 0

Total Subtask 6H 1007.5

Subtask 6I Month 5 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6J: Construction Inspection (Month 6)

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 35

Total Subtask 6I 1042.5

Subtask 6J Month 6 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6K: Construction Inspection (Month 7)

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

320 0

Reimbursable Total Cost 35

Total Subtask 6J 1042.5

Subtask 6K Month 7 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6L: Construction Inspection (Month 8)

Postage 1 35 35

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 35

Total Subtask 6K 1042.5

Subtask 6L Month 8 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 1 100

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6M: Substantial Completion Walk-Through w/Punchlist

Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist and Certification provided by FDEP Project Manager via PDF within one (1) day of Substantial Completion inspection.

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 6L 1007.5

Subtask 6M substantial

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Poject Manager 145 6 870

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 1 145

Weiler Engineering Registered Engineer Intern 115 6 690

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Subtask 6N: Final Completion

Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.

Deliverable: WEC will assure that punch list items from Substantial are addressed and provide a punchlist of items not addressed from Substantial via PDF to the FDEP Project Manager..

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Clerical 55 0 0

Total 1805

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 6M 1805

Subtask 6N - Final

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Poject Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 1 145

Ms. Theresa Carron John Pennekamp State Park Boardwalk

Project Schedule:

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 2 200

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 1 55

Total 1380

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 6N 1380

Activity Duration (Calendar Days) Days from Execution

Subtask 1A Conceptual 60 60

Subtask 1B Survey 60 60

Subtask 1C Geotech 60 60

Subtask 1D Lead/asbestos 60 60

Subtask 1E FLUCFCS/Species 60 60

Subtask 2: 60% plans 30 - includes 7 days for Client review

Subtask 3: 100% plans 30 – includes 7 days for Client review

Subtask 4A: Permit applications 30 – includes 7 days for Client review

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Summary of Fees:

Subtask 4B: Permit approvals 60 – includes response for additional information

Subtask 5: Prebid 30 210

Subtask 6A - Pre construction 30 210

Subtask 6B: Review Submittals 30 240

Subtask 6C: Respond to RAI's 60 300

Subtask 6D: Respond to Contractor RFI's

240 (Est max overall calendar days;

RFI's will be responded to within 7 days of receipt from Contractor)

Subtask 6E: Provide Construction Inspections w/ (Month 1)

30 330

Subtask 6F: Provide Construction Inspections w/ Report (Month 2)

30 360

Subtask 6G: Provide Construction Inspections w/ Report (Month 3)

30 390

Subtask 6H: Provide Construction Inspections w/ (Month 4)

30 420

Subtask 6I: Provide Construction Inspections w/ Report (Month 5)

30 450

Subtask 6J: Provide Construction Inspections w/ (Month 6)

30 480

Subtask 6K: Provide Construction Inspections w/ (Month 7)

30 510

Subtask 6L: Provide Construction Inspections w/ (Month 8)

30 540

Subtask 6M: Substantial Completion Walk-Through w/ Punchlist

30 570

Subtask 6N: Final Completion w/ Certification

30 600

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1A Conceptual $20725.00 $0.00

Subtask 1B Survey $6097.40 $0.00

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Subtask 1C Geotech $12255.60 $0.00

Subtask 1D Lead/Asbestos $7544.04 $0.00

Subtask 1E FLUCFCS/Species $9853.60 $0.00

Subtask 2: 60% plans $21015.00 $0.00

Subtask 3: 100% plans $14735.00 $127.00

Subtask 4A Permit applications $16530.00 $1495.00

Subtask 4B Permit approvals $9310.00 $0.00

Subtask 5 Pre-Bid $3520.00 $0.00

Total Design & Permitting $121585.64 $1622.00

Subtask 6A - Pre-Construction Meeting

$2080.00 $0.00

Subtask 6B - Submittal Review $2680.00 $35.00

Subtask 6C - Regulatory Response

$1980.00 $0.00

Subtask 6D Assistance during construction

$2520.00 $0.00

Subtask 6E Inspection 1 $1007.50 $0.00

Subtask 6F Inspection 2 $1007.50 $0.00

Subtask 6G Inspection 3 $1007.50 $0.00

Subtask 6H Inspection 4 $1007.50 $0.00

Subtask 6I Inspection 5 $1007.50 $35.00

Subtask 6J Inspection 6 $1007.50 $35.00

Subtask 6K Inspection 7 $1007.50 $35.00

Subtask 6L Inspection 8 $1007.50 $0.00

Subtask 6M Substantial Completion

$1805.00 $0.00

Subtask 6N Final Completion $1380.00 $0.00

Total during Construction $20505.00 $140.00

Total Fixed Price Cost: $142090.64

Total Fixed Price Cost: $1762.00

Ms. Theresa Carron John Pennekamp State Park Boardwalk

CN 230/TA69

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

Overall Total Cost: $143852.64