This is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) establishing a professional services contract with Weiler Engineering Corporation for design and engineering services related to the Mangrove Trail Boardwalk replacement project at John Pennekamp Coral Reef State Park in the Florida Keys. The contract is designated as FDEP Contract No. CN230, Task Assignment No. 69, with a project number 61489C and was executed on June 30, 2023, with a completion date of September 30, 2025.
The scope of work encompasses professional services for the complete replacement of an approximately 1,500-foot wood boardwalk, including environmental assessment, geotechnical investigation, survey work, structural and civil engineering design, permitting, and construction administration. The contract is structured in multiple subtasks spanning conceptual design, 60% and 100% design documents, permit applications and approvals, pre-bid and pre-construction meetings, contractor submittal review, regulatory agency response, eight monthly construction inspections, and substantial and final completion inspections. The total contract value is $143,852.64, consisting of $142,090.64 in fixed-price costs and $1,762.00 in reimbursable costs not to exceed. Payment is contingent upon FDEP approval of deliverables for each subtask. The project schedule extends over 600 calendar days from execution, with design and permitting activities anticipated to conclude approximately 210 days after execution, followed by construction phase services spanning an estimated eight months.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 69 FDEP-BDC 61489C
John Pennekamp Coral Reef State Park Mangrove Trail Boardwalk
Weiler Engineering Corporation
Robin Palmer, PE 941-505-1700 rpalmer@weilerengineering.org
Ralph Perkins 850-245-2560 ralph.perkins@floridadep.gov
Professional services to replace the Mangrove Trail Boardwalk including environmental, geotechnical, survey, structural & civil engineering, permitting and construction administration per the attached proposal dated 6/21/2023.
Theresa Carron
6/30/2023 $ 142,090.64 9/30/2025 $ 1,762.00
$ 143,852.64
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.26 09:25:32 -04'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.06.26 09:33:17 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.26 12:55:56 -04'00'
R. Jeff Weiler, PE Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.06.27 09:33:57 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.06.30 15:18:03 -04'00'
61489C 37505018015 080039/23 423001 U3200 134000 QK $ 143,852.64
$ 143,852.64
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
June 2, 2023 - Revision 2 - June 21, 2023
Ms. Theresa Carron
Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: John Pennekamp State Park - Boardwalk Replacement, CN - 230, TA - 69
Dear Ms. Carron, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to demolish and replace the existing boardwalk and accessory structures identified below.
June 2, 2023 - Rev 2 - 06/21/23 Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Our services will include:
Design and permitting to remove the existing +/- 1500 ft. long wood boardwalk and replace it in the same place.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Boardwalk Replacement
John Pennekamp State Park
Contract Number 230, Task Assignment Number 69
Subtask 1: Conceptual Design
1) A - Conceptual Design
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP, the USACOE and the Local Building Department.
c) Consultant will prepare conceptual site plans & include typical sections.
1) B – Surveys
a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topo extending 5 feet each side of the existing boardwalk. To be cleared by Client.
1) C –Geotechnical Reports (Universal Engineering)
a) Consultant will coordinate with Geotechnical Sub-Consultant to prepare a geotechnical Report recommending piling depths and seasonal high water elevation.Consultant will coordinate with a consultant to complete lead and asbestos reports for the existing structure.
1) D – Lead/Asbestos Reports (Universal Engineering)
a) Consultant will coordinate with Sub-consultant to prepare lead and asbestos reports on existing structure.
1) E – FLUCFCS Map & Listed Species
a) Consultant will coordinate with Sub-consultant to prepare a FLUCFCS Map and Listed Species Report.
Deliverable:
1) A - Conceptual Design, Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Conceptual Site & Structural Plans – Consultant shall deliver conceptual plans to the client via digital PDF. Plans will include:
Cover sheet Survey Existing Conditions Site Plan Boardwalk Plan View Typical Sections Opinion of probable cost
1) B - Surveys
Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey via digital PDF, CAD and a Signed and Sealed copy.
1) C –Geotechnical Reports
Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report recommending piling depths and seasonal high water elevation via digital PDF.
1) D –Lead/Asbestos Reports
Lead/Asbestos Report – Sixty days from execution of task assignment, consultant shall deliver a completedLead and Asbestos report via digital PDF
1) E –FLUCFCS & Listed Species Reports
FLUCFCS Map & Listed Species Report – Sixty days from execution of task assignment, consultant shall deliver a completed report via digital PDF
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A - Conceptual Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 20 2900
Weiler Engineering Principal in Charge 195 1 195
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Weiler Engineering
Registered Professional Engineer 145 14 2030
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 60 6000
Weiler Engineering Engineering Technician 80 80 6400
Weiler Engineering Clerical 55 8 440
Total 20725
Subtask 1B - Survey
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 4 580
CHW 3 Person Field Crew Hr 177.54 16 2840.64
CHW Project Surveyor Hr 74.75 16 1196
CHW Senior CAD/GIS Hr 103.13 8 825.04
CHW Professional Surveyor & Mapper
Hr 163.93 4 655.72
Total Survey 6097.4
Subtask 1C Geotech
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 6 870
Geotech Universal
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Universal Senior Project Engineer Hr 165.84 32 5306.88
Universal Project Engineer Hr 94.50 32 3024
Universal Staff Engineer Hr 68.46 32 2190.72
Universal CAD Drafting Hr 54.00 16 864
Total Geotech 12255.6
Subtask 1D - Lead/Asbestos survey
Firm Name Position Classification
Unit Rate Hours Total Fixed Price Cost
Weiler Engineering Registered Professional Engineer
145 4 $580.00
Weiler Engineering Registered Engineer Intern
115 8 $920.00
Universal Engineering Senior Geotechnical Engineer. PE
165.84 24 $3980.16
Universal Engineering Sr Engineering Technician
49.14 42 $2063.88
Total Lead/ Asbestos Survey
$7544.04
Total Subtask 1D $7544.04
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Reimbursable Cost: (if applicable)
Subtask 1E - FLUCFCS & Listed Species
Firm Name Position Classification
Unit Rate Hour s
Total Fixed Price Cost
Weiler Engineering Registered Professional Engineer
145 4 $580.00
Weiler Engineering Registered Engineer Intern
115 12 $1380.00
Passaarella Senior Ecologist 149.50 16 $2392.00
Passaarella Ecologist 104.65 32 $3348.80
Passaarella Design/GIS 89.70 24 $2152.80
Total Sub-task E
FLUCFCS &
Listed Species
$9853.60
Postage
Printing
Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost $0.00
Total Subtask 1E $9853.60
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Reimbursable Cost: (if applicable)
Subtask 2: 60% documents
Description: Plans completed to 60% incorporating comments from 30%.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost;
Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes
Foundation/Piling Plans and details;
Beam schedules;
ADA Ramp Plan with sections & details;
Description Number @ Total
Postage
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 1A
Total Subtask 1 39078
Subtask 2 - 60% Plans
Robinson_MS Text Box 56,475.64
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 3: 100% documents
Description: Plans completed to 100%.
Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Updated Opinion of Probable Cost;
Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Utility Plan Site Details and General Notes
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 20 2900
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering
Registered Professional Engineer 145 16 2320
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 60 6000
Weiler Engineering Engineering Technician 80 80 6400
Weiler Engineering Clerical 55 8 440
Total 21015
Total for Subtask 2
21015
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Foundation/Piling Plans and details;
Beam schedules;
ADA Ramp Plan with sections & details;
Specifications
Reimbursable Cost:
Subtask 3 - 100% Plans
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 14 2030
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering
Registered Professional Engineer 145 12 1740
Weiler Engineering Registered Engineer Intern 115 18 2070
Weiler Engineering Senior Engineering Designer 100 40 4000
Weiler Engineering Engineering Technician 80 56 4480
Weiler Engineering Clerical 55 4 220
Total 14735
Description Number @ Total
Postage 1 35 35
Printing 40 2.30 92
Reimbursable Total Cost
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 4: Permitting
Description:
4) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for exemption, the USACE, the State Fire Marshall, Building for site development approval. WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.
4) B – Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
4) A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five sets of permit applications with 100% plans.
4) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation
Total for Subtask 3
14862
Subtask 4A Permit Applications
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 12 1740
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering Registered Professional Engineer 145 20 2900
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 40 4000
Weiler Engineering Engineering Technician 80 64 5120
Weiler Engineering Clerical 55 5 275
Total 16530
Subtask 4B Permit Approvals
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 12 1740
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering Registered Professional Engineer 145 8 1160
Weiler Engineering Registered Engineer Intern 115 16 1840
Weiler Engineering Senior Engineering Designer 100 24 2400
Weiler Engineering Engineering Technician 80 24 1920
Weiler Engineering Clerical 55 1 55
Total 9310
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 5: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Description Number @ Total
Postage 1 35 35
Printing 200 2.3 460
Permit application fees estimate
1 1000 1000
Reimbursable Total Cost for 4A
Total for Subtask 4
27335
Subtask 5 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 $1160.00
Weiler Engineering Principal in Charge 195 0 $0.00
Weiler Engineering Registered Professional Engineer
145 0 $0.00
Weiler Engineering Registered Engineer Intern 115 8 $920.00
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Subtask 6A - 6N: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)
Subtask 6A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Weiler Engineering Senior Engineering Designer 100 8 $800.00
Weiler Engineering Engineering Technician 80 8 $640.00
Weiler Engineering Clerical 55 0 $0.00
Total $3520.00
Description Number @ Total Postage Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
$0.00
Reimbursable Total Cost $0.00
Total Subtask 5 $3520.00
Subtask 6A - Pre-Construction Mtg
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6B: Review Contractor submittals
Description:WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 0 0
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 2080
Description Number @ Total
Postage 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 0
Reimbursable Total Cost 0
Total subtask 6A 2080
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6C: Respond to Building Department comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Subtask 6B - Review Submittals
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 12 1200
Weiler Engineering Engineering Technician 80 2 160
Weiler Engineering Clerical 55 2 110
Total 2680
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 6B 2715
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Deliverable: RFI response documents submitted to Building Department.
Subtask 6D: Respond to Contractor RFI's
Subtask 6C
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1980
Description Number @ Total
Postage 35 0
Printing 2.30 0.00
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
Total - 6C 1980
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Subtask 6D- Respond to RFI’s
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 2 290
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 4 220
Total 2520
Description Number @ Total
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6E: Provide Construction Inspections (Month 1)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of each inspection.
Total Subtask 6D 2520
Subtask 6E - Month 1 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6F: Construction Inspection (Month 2)
Reimbursable Total Cost
Total Subtask 6E 1007.5
Subtask 6F
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Description Number @ Total
Postage 35 0
Printing 0
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6G: Construction Inspection (Month 3)
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost
Total Subtask 6F 1007.5
Subtask 6G Month 3 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6H: Construction Inspection (Month 4)
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 7G 1007.5
Subtask 6H - Inspection Month 4
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6I: Construction Inspection (Month 5)
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 0
Total Subtask 6H 1007.5
Subtask 6I Month 5 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6J: Construction Inspection (Month 6)
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6I 1042.5
Subtask 6J Month 6 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6K: Construction Inspection (Month 7)
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
320 0
Reimbursable Total Cost 35
Total Subtask 6J 1042.5
Subtask 6K Month 7 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6L: Construction Inspection (Month 8)
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6K 1042.5
Subtask 6L Month 8 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6M: Substantial Completion Walk-Through w/Punchlist
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist and Certification provided by FDEP Project Manager via PDF within one (1) day of Substantial Completion inspection.
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 6L 1007.5
Subtask 6M substantial
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Poject Manager 145 6 870
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Subtask 6N: Final Completion
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will assure that punch list items from Substantial are addressed and provide a punchlist of items not addressed from Substantial via PDF to the FDEP Project Manager..
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Clerical 55 0 0
Total 1805
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 6M 1805
Subtask 6N - Final
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Poject Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Ms. Theresa Carron John Pennekamp State Park Boardwalk
Project Schedule:
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 2 200
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1380
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 6N 1380
Activity Duration (Calendar Days) Days from Execution
Subtask 1A Conceptual 60 60
Subtask 1B Survey 60 60
Subtask 1C Geotech 60 60
Subtask 1D Lead/asbestos 60 60
Subtask 1E FLUCFCS/Species 60 60
Subtask 2: 60% plans 30 - includes 7 days for Client review
Subtask 3: 100% plans 30 – includes 7 days for Client review
Subtask 4A: Permit applications 30 – includes 7 days for Client review
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Summary of Fees:
Subtask 4B: Permit approvals 60 – includes response for additional information
Subtask 5: Prebid 30 210
Subtask 6A - Pre construction 30 210
Subtask 6B: Review Submittals 30 240
Subtask 6C: Respond to RAI's 60 300
Subtask 6D: Respond to Contractor RFI's
240 (Est max overall calendar days;
RFI's will be responded to within 7 days of receipt from Contractor)
Subtask 6E: Provide Construction Inspections w/ (Month 1)
30 330
Subtask 6F: Provide Construction Inspections w/ Report (Month 2)
30 360
Subtask 6G: Provide Construction Inspections w/ Report (Month 3)
30 390
Subtask 6H: Provide Construction Inspections w/ (Month 4)
30 420
Subtask 6I: Provide Construction Inspections w/ Report (Month 5)
30 450
Subtask 6J: Provide Construction Inspections w/ (Month 6)
30 480
Subtask 6K: Provide Construction Inspections w/ (Month 7)
30 510
Subtask 6L: Provide Construction Inspections w/ (Month 8)
30 540
Subtask 6M: Substantial Completion Walk-Through w/ Punchlist
30 570
Subtask 6N: Final Completion w/ Certification
30 600
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A Conceptual $20725.00 $0.00
Subtask 1B Survey $6097.40 $0.00
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Subtask 1C Geotech $12255.60 $0.00
Subtask 1D Lead/Asbestos $7544.04 $0.00
Subtask 1E FLUCFCS/Species $9853.60 $0.00
Subtask 2: 60% plans $21015.00 $0.00
Subtask 3: 100% plans $14735.00 $127.00
Subtask 4A Permit applications $16530.00 $1495.00
Subtask 4B Permit approvals $9310.00 $0.00
Subtask 5 Pre-Bid $3520.00 $0.00
Total Design & Permitting $121585.64 $1622.00
Subtask 6A - Pre-Construction Meeting
$2080.00 $0.00
Subtask 6B - Submittal Review $2680.00 $35.00
Subtask 6C - Regulatory Response
$1980.00 $0.00
Subtask 6D Assistance during construction
$2520.00 $0.00
Subtask 6E Inspection 1 $1007.50 $0.00
Subtask 6F Inspection 2 $1007.50 $0.00
Subtask 6G Inspection 3 $1007.50 $0.00
Subtask 6H Inspection 4 $1007.50 $0.00
Subtask 6I Inspection 5 $1007.50 $35.00
Subtask 6J Inspection 6 $1007.50 $35.00
Subtask 6K Inspection 7 $1007.50 $35.00
Subtask 6L Inspection 8 $1007.50 $0.00
Subtask 6M Substantial Completion
$1805.00 $0.00
Subtask 6N Final Completion $1380.00 $0.00
Total during Construction $20505.00 $140.00
Total Fixed Price Cost: $142090.64
Total Fixed Price Cost: $1762.00
Ms. Theresa Carron John Pennekamp State Park Boardwalk
CN 230/TA69
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Overall Total Cost: $143852.64