This is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) establishing a contract with Weiler Engineering Corporation for engineering and design services related to a boardwalk construction project at Honeymoon Island State Park. The contract is identified as FDEP Contract No. CN230, Task Assignment No. TA86, with project number 61432C. The project location is Honeymoon Island State Park, and the consultant representative is Robin Palmer of Weiler Engineering Corporation, with FDEP Contract Manager Ralph Perkins overseeing the engagement.

The scope of work encompasses the design, permitting, and construction administration services for a new approximately 250-foot composite boardwalk providing pedestrian and pet access to South Beach. Services are structured in five major subtasks: Subtask 1 includes 30% design development with conceptual designs, surveys, and geotechnical reports (total $28,181.58); Subtask 2 covers 60% design plans ($8,388.75); Subtask 3 includes 100% design plans ($5,467.50); Subtask 4 encompasses permitting activities including applications and approvals from SWFWMD, FDEP, and USACE ($14,087.50); and Subtask 5 includes construction phase services such as pre-construction meetings, submittal reviews, regulatory responses, RFI coordination, and interim inspections ($15,330.00). The fixed price cost is $71,205.33 with reimbursable costs of $250.00 (SWFWMD application fees), resulting in a total task amount of $71,455.33. The project start date is upon execution with a completion date of April 29, 2025. Payment will be made upon FDEP approval of deliverables for each subtask. The project is funded through FDEP account code 61432C with FLAIR code 37504008120.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
CN-370000-CN230-T53CO1.pdf PDF
CN-370000-CN230-T57.pdf PDF
CN-370000-CN230-T59.pdf PDF
CN-370000-CN230-T60.pdf PDF
CN-370000-CN230-T64.pdf PDF
CN-370000-CN230-T66.pdf PDF
CN-370000-CN230-T7.pdf PDF
CN-370000-CN230-T70.pdf PDF
CN-370000-CN230-T72.pdf PDF
CN-370000-CN230-T75.pdf PDF
CN-370000-CN230-T8.pdf PDF
CN-370000-CN230-T80.pdf PDF
CN-370000-CN230-T82CO1.pdf PDF
CN-370000-CN230-T87.pdf PDF
CN-370000-CN230-T89.pdf PDF
CN-370000-CN230-T90.pdf PDF
CN-370000-CN230-TA30.pdf PDF
CN-370000-CN230-TA5CO1.pdf PDF
CN-370000-CN230.pdf PDF
CN-370000-CN230-A1.pdf PDF
CN-370000-CN230-CMC1.pdf PDF
CN-370000-CN230-T11.pdf PDF
CN-370000-CN230-T13CO1.pdf PDF
CN-370000-CN230-T2.pdf PDF
CN-370000-CN230-T27.pdf PDF
CN-370000-CN230-T28.pdf PDF
CN-370000-CN230-T34.pdf PDF
CN-370000-CN230-T36.pdf PDF
CN-370000-CN230-T37CO3.pdf PDF
CN-370000-CN230-T3CO2.pdf PDF
CN-370000-CN230-T4.pdf PDF
CN-370000-CN230-T42.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 TA86 FDEP 61432C

New Boardwalk to South Beach

Weiler Engineering Corporation

Robin Palmer (941) 505-1700 rpalmer@weilerengineering.org

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

New boardwalk for the access of pedestrians and pets along the existing pathway to pet beach (South Beach) per the proposal dated 06/25/2024, which includes the design, permit and CA services.

Meena Senthil or successor

Upon Execution $ 71,205.33 04/29/2025 $ 250.00

$ 71,455.33

Tamika Bass

Meena Senthil

Ralph Perkins

Robin Palmer

Michael W. Foster Jr., P.E.

61432C 37504008120 080039/23 000286 U3100 131500 AD $ 71,455.33

$ 71,455.33

June 17, 2024 -Revision 1 June 25, 2024

Ms. Meen Senthil Design Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399

RE: Honeymoon Island State Park New Boardwalk to Pet Beach, CN - 230, TA - 8

Dear Ms. Senthil, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to construct the new pet boardwalk identified below.

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941- 505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX

305 -289- 416 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT

INFO@WEILERENGINEERING.ORG

June 17, 2024, Revision 1 June 25, 2024 Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Our services will include:

Design and permitting for the new +/- 250 ft. long composite boardwalk to access the Honeymoon Island State Park Pet Beach.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Honeymoon Island State Park New Boardwalk to Pet Beach

Contract Number 230, Task Assignment Number 8

Subtask 1: 30% Design

1) A - Conceptual Designs

a) WEC will conduct one site visit.

b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP, the USACE and the Local Building Department.

c) Consultant will prepare up to (3) conceptual site plans with design options for the FDEP to select the design of their choice.

1) B Surveys

a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topographic information for the project area.

1) C Geotechnical Reports (Tierra, Inc.)

a) Consultant will coordinate with Geotechnical Sub-Consultant to prepare a geotechnical Report recommending piling depths.

Deliverable:

1) A - Conceptual Design

Meeting minutes from the site visit and all permitting pre-application meeting minutes will be provided in PDF format. Conceptual Site & Structural Plans Consultant shall deliver conceptual plans to the client via digital PDF. Plans will include:

Cover sheet Site Plan Boardwalk Plan View (1 per Option) Typical Sections (1 per Option) Opinion of Probable Cost (1 per Option)

1) B - Surveys

Completed Survey Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey via digital PDF, CAD and a Signed and Sealed copy.

1) C Geotechnical Reports

Geotechnical Report Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report recommending piling depths via digital PDF.

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1A - 30% Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 12 1740.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 12 1740.00

Weiler Engineering

Registered Engineer Intern 115 16 1840.00

Weiler Engineering Senior Engineering Designer 100 48 4800.00

Weiler Engineering Engineering Technician 80 35 2800.00

Weiler Engineering Clerical 55 2 110.00

Total 13078.75

Subtask 1B - Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 7 1015.00

CHW 3 Person Field Crew Hr 177.54 18 3195.72

CHW Project Surveyor Hr 74.75 17 1270.75

CHW Senior CAD/GIS Hr 103.13 16 1650.08

CHW Professional Surveyor & Mapper

Hr 163.93 4 655.72

Total Survey 7787.27

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 1C Geotech

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 7 1015.00

Geotech Tierra

Tierra Senior Engineer Hr 178.60 10 1786.00

Tierra Senior Project Engineer Hr 146.53 15 2197.95

Tierra Geotechnical Technician Hr 68.45 25 1711.25

Tierra Clerical Hr 75.67 8 605.36

Total Geotech 7315.56

Reimbursable Cost: (if applicable)

Description Number @ Total

Postage Not Anticipated

Printing Not Anticipated

Overnight Travel

(if applicable)

Not Anticipated

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost 1

Total Subtask 1 28,181.58

Subtask 2 - 60% Plans

June 17, 2024, Revision 1 June 25, 2024 Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 2: 60% documents

Description: Plans completed to 60% incorporating comments from 30%. Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including: Opinion of Probable Cost;

Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes Foundation/Piling Plans and Details Ramp Plan with Sections & Details

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 1160.00

Weiler Engineering

Principal in Charge 195 0.25 48.75

Weiler Engineering

Registered Professional Engineer 145 8 1160.00

Weiler Engineering Registered Engineer Intern 115 12 1380.00

Weiler Engineering Senior Engineering Designer 100 25 2500.00

Weiler Engineering Engineering Technician 80 24 1920.00

Weiler Engineering Clerical 55 4 220.00

Total 8388.75

Total for Subtask 2 8388.75

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 3: 100% documents Description:

Plans completed to 100%.

Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver two sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Updated Opinion of Probable Cost Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes Foundation/Piling Plans and Details Ramp Plan with Sections & Details Specifications

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 3 - 100% Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 6 870.00

Weiler Engineering

Principal in Charge 195 .5 97.50

Weiler Engineering

Registered Professional Engineer 145 6 870.00

Weiler Engineering Registered Engineer Intern 115 8 920.00

Weiler Engineering Senior Engineering Designer 100 10 1000.00

Weiler Engineering Engineering Technician 80 20 1600.00

Weiler Engineering Clerical 55 2 110.00

Total 5467.50

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Reimbursable Cost:

Description Number @ Total

Postage Not anticipated

35 0

Printing Not anticipated

2.30 0

Overnight Travel

(if applicable)

Reimbursable Total Cost

Total for Subtask 3

5467.50

Subtask 4: Permitting

Description:

4) A Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for exemption or General Permit, the FDEP for a CCCL Permit, and coordinate with the City of Dunedin on Building Department Permit application submittal (will not be approved until a contractor is selected). WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.

4) B Permit Approvals, Consultant will coordinate with agencies and respond to agencies for additional information. Note:

The City of Dunedin permit application may be submitted by the engineer; but will not be approved until the contractor is selected. City approval is not part of this Permit Approval subtask. Depending on the agencies, the anticipated timeline for approval is 90 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation. Permit approvals will include: FDEP CCCL and SWFWMD ERP/General Permit/or Exemption.

4) C- Permit Application (USACE)

If needed, Consultant will prepare the application for USACE approval.

4) D- Permit Approval (USACE)

Consultant will coordinate with USACE and respond to agencies for additional information for permit approval

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Deliverable:

4) A Permit Applications

Incorporate Client review comments from 60% plans and deliver a digital set of the permit applications for signature. Deliverable will be in PDF format.

4) B Permit Approvals

Approvals will be obtained from SWFWMD (Exemption or General Permit) and FDEP CCCL Permit.

Deliverable will be in PDF format.

4) C Permit Applications (USACE)

Incorporate Client review comments from 60% plans and deliver a digital set of the permit application for signature. Deliverable will be in PDF format.

4) D Permit Approvals (USACE)

Consultant will respond to agency requests for additional information and copy Client on all responses. Permit approvals will include: FDEP CCCL and SWFWMD ERP/General Permit/or Exemption. Approvals will be obtained in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 4A Permit Apps

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering

Project Manager 145 6 870.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering Registered Professional Engineer 145 8 1160.00

Weiler Engineering Registered Engineer Intern 115 20 2300.00

Weiler Engineering Senior Engineering Designer 100 10 1000.00

Weiler Engineering Engineering Technician 80 18 1440.00

Weiler Engineering

Clerical 55 1 55.00

Total 6873.75

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 4B Permit Approvals

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 2 290.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 4 580.00

Weiler Engineering Registered Engineer Intern 115 6 690.00

Weiler Engineering Senior Engineering Designer 100 4 400.00

Weiler Engineering Engineering Technician 80 6 480.00

Weiler Engineering Clerical 55 0.5 27.50

Total 2516.25

Subtask 4C Permit Application- USACE

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering Registered Professional Engineer 145 4 580.00

Weiler Engineering Registered Engineer Intern 115 8 920.00

Weiler Engineering Senior Engineering Designer 100 10 1000.00

Weiler Engineering

Engineering Technician 80 6 480.00

Weiler Engineering Clerical 55 0.5 27.50

Total 3346.25

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 4D Permit Approvals- USACE

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 1 145.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 2 290.00

Weiler Engineering

Registered Engineer Intern 115 2 230.00

Weiler Engineering Senior Engineering Designer 100 2 200.00

Weiler Engineering Engineering Technician 80 2 160.00

Weiler Engineering Clerical 55 0.5 27.50

Total 1101.25

Reimbursable Cost:

Description Number @ Total

Postage Not anticipated 35 0

Printing Not anticipated 2.3 0

SWFWMD

Application Fees

1 250 250.00

Reimbursable Total Cost for 4A

250.00

Total for Subtask 4

14087.50

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5A 5G: Construction Phase Services

Performance Measure: Deliverables will be reviewed by the Department to they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5A: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Fixed Price Cost:

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 0 0

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 2080

Reimbursable Cost:

Description Number @ Total

Postage 0

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total subtask 5A 2080

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5B: Review Contractor submittals

Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable: Stamped acceptance of submittals in PDF digital form to FDEP Project Manager within 7 days of

Fixed Price Cost:

Subtask 5B - Review Submittals

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 12 1200

Weiler Engineering Engineering Technician 80 2 160

Weiler Engineering Clerical 55 2 110

Total 2680

Reimbursable Cost:

Description Number @ Total

Postage Not Anticipated 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 5B 2680.00

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5C: Respond to Building Department comments

Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department within 7 days, and revise plans accordingly within 14 days of receipt of comments.

when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.

Deliverable: RFI response documents submitted to Building Department within 7 days (14 days for plan revisions) in PDF format.

Fixed Price Cost:

Subtask 5C

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 1 145

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 1 55

Total 1980

Reimbursable Cost:

Description Number @ Total

Postage 35 0

Printing 2.30 0.00

Overnight Travel

(if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated

Reimbursable Total Cost

Total - 5C 1980

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5D: Respond to Contractor RFI's

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. If any plan changes are required, these changes will be completed within 14 days.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format within 7 days.

Fixed Price Cost:

Subtask 5D- Respond to

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 2 290

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 4 220

Total 2520

Reimbursable Cost:

Description Number @ Total

Postage 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 5D 2520

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5E: Provide Construction Inspections (Interim Site Visit # 1)

Description: WEC will provide an interim inspection during construction upon request from BDC.

Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of the site visit.

Fixed Price Cost:

Subtask 5E Interim Site Inspection #1

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Weiler Engineering Principal in Charge 195 0 0.00

Weiler Engineering Registered Professional Engineer

145 .5 72.50

Weiler Engineering Registered Engineer Intern 115 10 1150.00

Weiler Engineering Senior Engineering Designer 100 1 100.00

Weiler Engineering Engineering Technician 80 0 0.00

Weiler Engineering Clerical 55 0 0.00

Total 1467.50

Reimbursable Cost:

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 5E 1467.50

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5F: Construction Inspection (Interim Site Visit #2)

Description: WEC will provide an interim inspection during construction upon request from BDC.

Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of the site visit.

Fixed Price Cost:

Subtask 5F Interim Site Inspection #2

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Weiler Engineering Principal in Charge 195 0 0.00

Weiler Engineering Registered Professional Engineer

145 .5 72.50

Weiler Engineering Registered Engineer Intern 115 10 1150.00

Weiler Engineering Senior Engineering Designer 100 1 100.00

Weiler Engineering Engineering Technician 80 0 0.00

Weiler Engineering Clerical 55 0 0.00

Total 1467.50

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost

Total Subtask 5F 1467.50

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 5G: Substantial Completion w/ Cert cation

Description: WEC will assist Client with the Substantial Completion inspection, with WEC representative attending the Substantial Completion inspection with punchlist.

Deliverable: WEC will also provide complete the substantial completion certi tion form required by FDEP Project Manager.

Fixed Price Cost:

Subtask 5G- Substantial Completion

Firm Name Position tion Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 3 435.00

Weiler Engineering Principal in Charge 195 0 0.00

Weiler Engineering Registered Professional Engineer

145 2 290.00

Weiler Engineering Registered Engineer Intern 115 14 1610.00

Weiler Engineering Senior Engineering Designer 100 8 800.00

Weiler Engineering Engineering Technician 80 0 0.00

Weiler Engineering Clerical 55 0 0.00

Total 3135.00

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 5G 3135.00

Project Schedule:

Activity Duration (Calendar Days) Days from Execution

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 1A Preliminary 60 60

Subtask 1B Survey 60 60

Subtask 1C Geotech 60 60

Subtask 2: 60% plans 30 - includes 7 days for Client review

Subtask 3: 100% plans 30 includes 7 days for Client review

Subtask 4A: Permit applications 30 includes 7 days for Client review

Subtask 4B: Permit approvals 60 includes response for additional information

Subtask 4A: Permit applications

(USACE)

30 includes 7 days for Client review

Subtask 4C: Permit approvals

(USACE)

180 includes response for additional information

Subtask 5A - Pre Construction TBD TBD

Subtask 5B: Review Submittals TBD TBD

Subtask 5C: Respond to RAI's TBD TBD

Subtask 5D: Respond to Contractor RFI's

TBD TBD

Subtask 5E: Interim Site Inspection #1

TBD TBD

Subtask 5F: Interim Site Inspection #2

TBD TBD

Subtask 5G: Substantial Completion Walk-Through w/ Punchlist

TBD TBD

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1A Preliminary $13078.75 $0.00

Subtask 1B Survey $7787.27 $0.00

Subtask 1C Geotech $7315.56 $0.00

Subtask 2: 60% plans $8388.75 $0.00

Subtask 3: 100% plans $5467.50 $0.00

Subtask 4A Permit applications $6873.75 $250.00

Subtask 4B Permit approvals $2516.25 $0.00

Subtask 4C Permit Application

(USACE)

$3346.25 $0.00

Ms. Meena Senthil Honeymoon Island State Park New Boardwalk to Pet Beach

CN 230/TA8

Subtask 4D Permit Approval

(USACE)

$1101.25 $0.00

Total Design & Permitting $55875.33 $250.00

Subtask 5A - Pre-Construction Meeting

$2080.00 $0.00

Subtask 5B - Submittal Review $2680.00 $0.00

Subtask 5C - Regulatory Response

$1980.00 $0.00

Subtask 5D Assistance during construction

$2520.00 $0.00

Subtask 5E Interim Site Inspection #1

$1467.50 $0.00

Subtask 5F Interim Site Inspection #2

$1467.50 $0.00

Subtask 5G Substantial Completion

$3135.00 $0.00

Total during Construction 15330.00 $0.00

Total Fixed Price Cost: $71205.33

Total Fixed Price Cost: $250.00

Overall Total Cost: $71455.33

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

File details come from the government source that posted it. Updated .