CN-370000-CN230-T37CO2.pdf
PDF 5 MB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
Summary
This is a Task Assignment Change Order Form from the Florida Department of Environmental Protection (FDEP) for contract CN230, Task Assignment No. 37, issued to Weiler Engineering Corporation for the Don Pedro Island State Park Visitor Dock Repairs project (Project No. 61366C). The change order was executed on June 19-22, 2023, and approved by FDEP budget, project management, and contract authority representatives, as well as the consultant.
The change order extends the project timeline by 184 days at no additional cost to FDEP. The original task end date of June 30, 2023, was extended to December 31, 2023, to allow sufficient time for the U.S. Army Corps of Engineers permit to be issued and 100 percent construction plans to be completed. The total task amount remains $46,059.88, consisting of $3,581.00 in reimbursable expenses and $42,478.88 in fixed fees. The scope of work is limited to permitting and design services only, as specified in the consultant's proposal dated June 16, 2023. No budget or cost adjustments were made under this change order.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 37 02 61366C
Don Pedro Island State Park Visitor Dock Repairs
Weiler Engineering
Robin Palmer 941.505.1700 rpalmer@weilerengineering.org
Ralph Perkins 850.245.2640 Ralph.Perkins@FloridaDEP.gov
Time only for permitting and design per the attached proposal dated 6/16/23.
$ 1,181.00 $ 40,978.88 $ 42,159.88 $ 3,581.00 $ 42,478.88 $ 46,059.88
$ 0.00 $ 3,581.00 $ 42,478.88 $ 46,059.88
12/1/2021
6/30/2023
6/30/2023
12/31/2023
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.19 11:08:06 -04'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.06.19 11:28:46 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.19 13:17:21 -04'00'
Jeff Weiler, PE Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.06.19 15:03:36 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.06.22 13:56:16 -04'00'
$ 0.00
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
June 16, 2023
Theresa Carron
Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
850-245-2721
Re: Don Pedro Island State Park: Visitor Dock Replacement FDEP Contract No: CN230 Task Assignment
No: 37, Project No: 61366C
Ms. Carron, We are requesting a time extension for the Don Pedro Island State Park: Visitor Dock Repairs project. This extension would be at no additional cost to the FDEP. The current contract expires on 06/30/2023. We are requesting an extension until 12/31/2023 to allow enough time for the USACE permit to be issued and the
100% construction plans to be completed.
If you have any questions, or require additional information, please do not hesitate to contact me at (941)
505-1700 or electronically at rpalmer@weilerengineering.org.
Sincerely, Robin Palmer, P.E.
Project Manager
Weiler Engineering Corporation
File details come from the government source that posted it. Updated .