This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for design, permitting, and construction services related to water treatment plant repairs at Little Manatee State Park. The document represents Task Assignment No. 60 under FDEP Contract No. CN230, with The Weiler Engineering Corporation designated as the consultant. The project is located at Little Manatee State Park in Florida, with FDEP Project Manager Garland Sandel or successor overseeing the work. Consultant Representative Jeff Weiler serves as the primary contact, and FDEP Contract Manager Ralph Perkins manages the contract administration.
The project scope encompasses design, permitting, and construction services to repair the water treatment plant, with work divided into six major subtasks: evaluation (including design, lead/asbestos testing, and geotechnical analysis); 100% design documentation; permitting (applications and approvals); pre-bid meeting; and five construction phase services (pre-construction meeting, submittal review, regulatory response, RFI responses, and substantial/final completion inspections). The total task amount is $36,087.38, consisting of $34,841.08 in fixed-price costs and $1,246.30 in cost reimbursement, with payment due upon FDEP approval of deliverables for each subtask. The project schedule extends from the execution date through June 30, 2025, with design and permitting activities anticipated to conclude within approximately 150 days and construction phase services extending to day 360. The work will be funded through FDEP's budget coding structure (Project 61521C, Fund 423001, Module U3200, Object Code 131500).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 60 FDEP-DRP 61521C
Little Manatee State Park Water System Upgrades
The Weiler Engineering Corporation
Jeff Weiler (941)628-4732 weiler7@mac.com
Ralph Perkins 850.245.2460 Ralph.Perkins@FloridaDEP.gov
The project consists of design, permitting and construction to repair the water treatment plant. See proposal dated 1.26.23
Garland Sandel or Successor
Execution date $ 34,841.08
6.30.25 $ 1,246.30
$ 36,087.38
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.14 12:43:11 -05'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.02.14 13:01:09 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.14 16:04:28 -05'00'
Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.02.14 16:20:26 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.02.17 10:57:50 -05'00'
61521C 37504000115 080039/23 423001 U3200 131500 QK $ 36,087.38
$ 36,087.38
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
· It was mentioned by FDEP staff that the current report says the aeration tank needed to be lined and the air vent tower needed to be replaced, along with a leaking valve on the water system coming from the well.
· Upon further inspection, it was observed by all that the joint between the tower and the aeration tank is under severe corrosion.
· The outer coating of the aeration tank is bubbling in several spots, and some have peeled away showing rust. This appears to be surface rust as of this time. This may become an issue down the road to cause more problems.
· Also, the bottom of the tank abutting the concrete is showing severe rust.
· The staff said that the current system is being serviced by U.S. Water and that they were supposed to be getting FDEP prices and information on restoring the tank and vent pipe.
· During the inspection, FDEP staff mentioned it probably would be better to just replace the whole aeration tank and vent pipe.
January 26, 2023 Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
· There is currently a vacant 12.5’ diameter concrete slab sitting close to the existing tank that could be utilized for a new tank. This slab is at least 8” thick
· The current tank is sitting on a 10.75’ x 10.75’ concrete slab that is at least 8” thick.
· The current tank is steel 9’ diameter and the main body is 8.5’ high.
· The pumps are located on a 9’x10’ concrete slab, with a 9’x9’ metal carport style covering.
· The leaking valve should be replaced and is 4”.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President The Weiler Engineering Corporation
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Water Treatment Plant Repairs
Little Manatee State Park
Contract Number 230, Task Assignment Number 60
Subtask 1: Evaluation
1) A - Design
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the FDEP and the Local Regulatory agency.
c) Consultant will prepare an evaluation report of the necessary repairs including replacing the aeration tank or repairing the existing tank and;
d) Consultant will prepare an opinion of probable cost for each option
1) B – Lead/Asbestos Report
a) Consultant will coordinate with Universal Engineering to complete lead and asbestos reports.
1) C – Geotech
a) Consultant will coordinate with Universal Engineering to complete borings and evaluation of the subsurface and assist with base and foundation design.
Deliverable:
1) A - Evaluation, Report – Consultant shall deliver report and opinion of probable cost for two options to the client via digital PDF.
1) B - Lead/Asbestos Report
Written results of asbestos lead and survey will be delivered via email in PDF and AutoCad format via email to the District Project Manager
1) C - Geotech
Consultant will coordinate with Universal Engineering to complete borings and evaluation of the subsurface and assist with base and foundation requirements.
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A - Evaluation
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 6 870
Weiler Engineering Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer 145 5 725
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 8 640
Weiler Engineering Clerical 55 1 55
Weiler Engineering Total 6240
Subtask 1B - Lead/Asbestos
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 4 580
Universal Senior Geotechnical Engineer, P.E.
Hr 165.84 8 1326.72
Universal Sr. Engineering Technician Hr 49.14 12 589.68
Total 2496.40
Subtask 1C - Geotech
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Reimbursable Cost: (if applicable)
Subtask 2: 100% Documents
Description: Plans completed to 100%.
Deliverable: Incorporate Client choice of option and review of Evaluation Report Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Opinion of Probable Cost;
Cover sheet Existing Conditions Equipment Specifics and Installation Requirements
Details and General Notes
Specifications
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 4 580
Universal Senior Geotechnical Engineer, P.E.
Hr 165.84 16 2653.44
Universal Sr. Engineering Technician Hr 49.14 16 786.24
Total 4019.68
Description Number @ Total
Postage
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 1A
Total Subtask 1 12756.08
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Reimbursable Cost:
Subtask 2 - 100% Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer 145 4 580
Weiler Engineering Registered Engineer Intern 115 16 1840
Weiler Engineering Senior Engineering Designer 100 24 2400
Weiler Engineering Engineering Technician 80 40 3200
Weiler Engineering Clerical 55 1 55
Total 8755
Description Number @ Total
Postage 1 35 35
Printing 10 2.30 23
Reimbursable Total Cost
Total for Subtask 2
Mr. Garland Sandel Little Manatee State Park WTP Repairs
Subtask 3: Permitting
Description:
3A - Applications Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals.
3B - Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
3A – Permit Applications, Incorporate Client review comments from 30% plans and deliver permit applications with 100% plans.
3B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation
Subtask 3A Permit Applications
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 6 870
Weiler Engineering Principal in Charge 195 0 0
Mr. Garland Sandel Little Manatee State Park WTP Repairs
Weiler Engineering Registered Professional Engineer 145 2 290
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 4 400
Weiler Engineering Engineering Technician 80 4 320
Weiler Engineering Clerical 55 1 55
Total 2855
Subtask 3B Permit Approvals
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 2 230
Weiler Engineering Senior Engineering Designer 100 4 400
Weiler Engineering Engineering Technician 80 4 320
Weiler Engineering Clerical 55 1 55
Total 1295
Description Number @ Total
Postage 1 35 35
Printing 21 2.3 48.3
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Subtask 4: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Permit application fees estimate
1 1000 1000
Reimbursable Total Cost for 3A
1083.3
Total for Subtask 3
5233.3
Subtask 4 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 $580.00
Weiler Engineering Principal in Charge 195 0 $0.00
Weiler Engineering Registered Professional Engineer
145 0 $0.00
Weiler Engineering Registered Engineer Intern 115 4 $460.00
Weiler Engineering Senior Engineering Designer 100 0 $0.00
Weiler Engineering Engineering Technician 80 0 $0.00
Weiler Engineering Clerical 55 0 $0.00
Total $1040.00
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Subtask 5A - 5F: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)
Subtask 5A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Description Number @ Total Postage Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
$0.00
Reimbursable Total Cost $0.00
Total Subtask 4 $1040.00
Subtask5A - Pre-Construction Mtg
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 4 580
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Mr. Garland Sandel Little Manatee State Park WTP Repairs
Subtask 5B: Review Contractor submittals
Description:WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Weiler Engineering Registered Engineer Intern 115 4 460
Weiler Engineering Senior Engineering Designer 100 0 0
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1040
Description Number @ Total
Postage 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 0
Reimbursable Total Cost 0
Total subtask 5A 1040
Subtask 5B - Review Submittals
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Mr. Garland Sandel Little Manatee State Park WTP Repairs
Subtask 5C: Respond to Building Department comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Deliverable: RFI response documents submitted to Building Department.
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 4 460
Weiler Engineering Senior Engineering Designer 100 4 400
Weiler Engineering Engineering Technician 80 2 160
Weiler Engineering Clerical 55 1 55
Total 1365
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 5B 1400
Subtask 5C
Mr. Garland Sandel Little Manatee State Park WTP Repairs
Subtask 5D: Respond to Contractor RFI's
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase based on a sixty (6) day construction schedule.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 1 115
Weiler Engineering Senior Engineering Designer 100 4 400
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1005
Description Number @ Total
Postage 35 0
Printing 2.30 0.00
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
Total - 5C 1005
Mr. Garland Sandel Little Manatee State Park WTP Repairs
Subtask 5E: Substantial Completion Walk-Through w/Punchlist
Subtask 5D- Respond to RFI’s
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 6 870
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 2 200
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 2105
Description Number @ Total
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 5D 2105
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.
Subtask 5F: Final Completion w/ Certification
Subtask 5E substantial
Cost
Weiler Engineering Poject Manager 145 4 580
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 4 460
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1285
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 5E 1320
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager.
Project Schedule:
Subtask 5F - Final
Cost
Weiler Engineering Poject Manager 145 4 580
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 4 460
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1340
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 5F 1375
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Summary of Fees:
Activity Duration (Calendar Days) Days from NTP
Subtask 1A Evaluation 60 60
Subtask 1B Lead/Asbestos 60 60
Subtask 1C Geotech 60 60
Subtask 2: 100% plans 30 – includes 7 days for Client review
Subtask 3A: Permit applications 30 – includes 7 days for Client review
Subtask 3B: Permit approvals 60 – includes response for additional information
Subtask 4: Prebid 30 180
Subtask 5A - Pre construction 30 210
Subtask 5B: Review Submittals 30 240
Subtask 5C: Respond to RAI's 60 300
Subtask 5D: Respond to Contractor RFI's
60 (Est max overall calendar days;
RFI's will be responded to within 7 days of receipt from Contractor)
Subtask 5E: Substantial Completion Walk-Through w/Punchlist
30 330
Subtask 5F: Final Completion w/ Certification
30 360
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A Evaluation $6240.00 $0.00
Subtask 1B Lead/Asbestos $2496.40 $0.00
Subtask 1C: Geotech $4019.68 $0.00
Subtask 2: 100% plans $8755.00 $58.00
Subtask 3A Permit applications $2855.00 $1083.30
Subtask 3B Permit approvals $1295.00 $0.00
Subtask 4 Pre-Bid $1040.00 $0.00
Total Design & Permitting $26701.08 $1141.30
Mr. Garland Sandel Little Manatee State Park WTP Repairs
CN 230/TA60
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Subtask 5A - Pre-Construction Meeting
$1040.00 $0.00
Subtask 5B - Submittal Review $1365.00 $35.00
Subtask 5C - Regulatory Response
$1005.00 $0.00
Subtask 5D Assistance during construction
$2105.00 $0.00
Subtask 5E Substantial Completion
$1285.00 $35.00
Subtask 5F Final Completion $1340.00 $35.00
Total during Construction $8140.00 $105.00
Total Fixed Price Cost: $34841.08
Total Fixed Price Cost: $1246.30
Overall Total Cost: $36087.38
| Blank TA Form.pdf |
| CN230 TA60 Little Manatee-Water System Upgrades.pdf |
File details come from the government source that posted it. Updated .