This is a Task Assignment Notification Form from the Florida Department of Environmental Protection (FDEP) for Contract CN230, Task Assignment 80. The document represents a professional services agreement between FDEP and Weiler Engineering Corporation (WEC) for construction engineering and inspection (CEI) services related to the Koreshan State Park Sewage Collection System project located in Osprey, Florida. The project manager is John Goss, with Ralph Perkins serving as the FDEP Contract Manager and Jeff Weiler, P.E., representing WEC as the consultant.

The scope of work comprises seven major subtasks spanning 180 calendar days from execution through April 29, 2025, with a total fixed-price cost of $42,202.50 and no reimbursable expenses. Subtask 1 covers a Cultural Resource Assessment Study including a 1A-32 Florida Permit Application and archaeological work totaling $14,995.00. Subtasks 2 through 7 address pre-construction meeting attendance ($1,790.00), contractor submittal reviews ($3,290.00), requests for information responses ($3,275.00), on-site observation across three months with individual monthly site visits ($7,132.50 combined), sanitary hot tap inspections at three locations ($3,360.00 combined), lift station start-up observations at three sites ($2,415.00 combined), substantial completion walk-through and punchlist assistance ($1,380.00), and final completion certification with as-built drawings and regulatory closeout documentation ($4,565.00). Payment will be made upon FDEP approval of deliverables for each subtask. The project budget is allocated across two fiscal year codes (080039/21 and 080039/22) totaling $42,202.50.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T21CO1.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
CN-370000-CN230-T34CO1.pdf PDF
CN-370000-CN230-T37.pdf PDF
CN-370000-CN230-T37CO1.pdf PDF
CN-370000-CN230-T42CO1.pdf PDF
CN-370000-CN230-T42CO3.pdf PDF
CN-370000-CN230-T43.pdf PDF
CN-370000-CN230-T44.pdf PDF
CN-370000-CN230-T48.pdf PDF
CN-370000-CN230-T51CO2.pdf PDF
CN-370000-CN230-T54CO1.pdf PDF
CN-370000-CN230-T58.pdf PDF
CN-370000-CN230-T63.pdf PDF
CN-370000-CN230-T65.pdf PDF
CN-370000-CN230-T67.pdf PDF
CN-370000-CN230-T6CO1.pdf PDF
CN-370000-CN230-T72CO1.pdf PDF
CN-370000-CN230-T74.pdf PDF
CN-370000-CN230-T81.pdf PDF
CN-370000-CN230-T81CO1.pdf PDF
CN-370000-CN230-T82.pdf PDF
CN-370000-CN230-T83.pdf PDF
CN-370000-CN230-T84.pdf PDF
CN-370000-CN230-T85.pdf PDF
CN-370000-CN230-T88.pdf PDF
CN-370000-CN230-TA31.pdf PDF
CN-370000-CN230-TA5.pdf PDF
PC-370000-CN230.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 TA 80 FDEP 61367C

Sewage Connection

Weiler Engineering Corporation

Jeff Weiler, P.E. (941) 505-1700 weiler7@mac.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

CRAS Study and Construction Assistance for construction of the sewage collection system project at Koreshan Historic State Park, per the attached proposal dated August 16, 2024.

John Goss or successor

Upon Execution $ 42,202.50 April 29, 2025 $ 0.00

$ 42,202.50

Tamika Bass

John Goss

Ralph Perkins

Jeff Weiler, P.E.

Michael W. Foster, Jr., P.E.

61367C 37504000045 080039/21 423001 U3200 131500 QK $ 17,271.70

61367C 37504000045 080039/22 423001 U3200 131500 QK $ 24,930.80

$ 42,202.50

November 7, 2023, Revision 6: August 16, 2024

Mr. John Goss Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 1843 South Tamiami Trail Osprey, Florida 34229

RE: Koreshan State Park - Sewage Collection System - Services During Construction - Contract 230, TA 80

Dear Mr. Goss;

We are pleased to submit this proposal for a cultural resources survey and services during construction of the new wastewater collection and transmission system at Koreshan State Park.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

11/07/23, Rev 6: 8/16/2024 Mr. John Goss Koreshan State Park CEI Sewage Collection System

CN 230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Mr. John Goss Koreshan State Park CEI Sewage Collection System

CN 230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Koreshan State Park Sewage Collection System CEI

Contract Number 230, Task Assignment Number 80

Subtask 1: Cultural Resource Assessment (CRAS)

Description: Consultant will provide a cultural resource assessment for the areas to be disturbed. This includes a 1A-32 Florida Permit Application, Archival and Literature Review, Field Work, and final report.

Deliverable: Consultant will provide digital pdf of the report.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1 Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 3 $435.00

Registered Engineer Intern 115 1 $115.00

Archaeological and Historic Conservancy, Inc. Historian 67.50 34 $2295.00

Project Archaeologist 137.50 56 $7700.00

Field Archaeologist 92.50 40 $3700.00

Administrative 75 10 $750.00

Total $14995.00

Reimbursable Cost:

Postage Not anticipated

Mr. John Goss Koreshan State Park CEI Sewage Collection System

CN 230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Printing

Overnight Travel

(if applicable) Mileage ($0.445 per mile) Reimbursable Total Cost

Not anticipated

Not anticipated

Not anticipated

$0.00

Total for Subtask 1 $14995.00

Subtask 2: Attend Pre-Construction Meeting

Description: WEC staff will attend one pre-construction meeting on site, respond to questions, and prepare meeting minutes.

Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2 - Pre-construction Mtg

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 8 $920.00

Senior Engineering Designer

100 $0.00

Engineering Technician 80 0 $0.00

Clerical 55 0 $0.00

Mr. John Goss Koreshan State Park CEI Sewage Collection System

CN 230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Total $1790.00

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

Not anticipated

Not anticipated

$0

$0.00

Total Subtask 2 $1790.00

Subtask 3: Review Contractor Submittals

Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.

Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 3 - Submittal Review

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 16 $1840.00

Senior Engineering Designer

100 6 $600.00

Mr. John Goss Koreshan State Park CEI Sewage Collection System

CN 230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Engineering Technician

80 2 $160.00

Clerical 55 2 $110.00

Total $3290.00

Postage Not anticipated (all deliverables in digital form only)

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

Not anticipated (all deliverables in digital form only)

$0.00

Total Subtask 3 - Submittals

$3490.00

Subtask 4: Assistance during construction (3 Months)

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Deliverable: Correspondence with Contractor and regulatory agencies provided via

PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 4

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Registered Professional Engineer

145 4 $580.00

Registered Engineer Intern

115 8 $920.00

Senior Engineering Designer

100 6 $600.00

Engineering Technician 80 0 $0.00

Clerical 55 2 $110.00

Total $3275.00

Postage

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all deliverables in digital form only)

$0.00

Total Subtask 4 $3275.00

Subtask 5a-5i On-Site Observation

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5a: Site Visit Month #1

Description: Utilizing photos and reports from the Contractor and weekly visits by a WEC inspector, WEC will provide on-site observation during installation of the sewer.

Deliverable: Monthly progress reports provided via PDF.

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Subtask 5a

Firm Name Position Classification Hourly

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 12 $1200.00

Engineering Technician 80 0 $0.00

Clerical 55 .5 $27.50

Total $2377.50

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all

$0.00

Total Subtask 5a $2377.50

Subtask 5b: Site Visit Month #2 by a WEC inspector, WEC will provide on-site observation during installation of the sewer.

Deliverable: Progress reports provided via PDF.

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 5b

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 12 $1200.00

Engineering Technician 80 0 $0.00

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all

Total Subtask 5b $2377.50

Subtask 5c: Site Visit Month #3

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162 by a WEC inspector, WEC will provide on-site observation during installation of the sewer.

Deliverable: Progress reports provided via PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5C

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 12 $1200.00

Engineering Technician 80 0 $0.00

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all

Total Subtask 5c $2377.50

Subtask 5d: Sanitary Hot Tap Inspection (Site 1)

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Description: WEC will attend the sanitary hot tap at Site 1.

Deliverable: Progress report provided via PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5d

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 6 $600.00

Engineering Technician 80 0 $0.00

Total $1120.00

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all

Total Subtask 5d $1120.00

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Subtask 5e: Sanitary Hot Tap Inspection (Site 2)

Description: WEC will attend the sanitary hot tap at Site 2.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5e

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 6 $600.00

Engineering Technician 80 0 $0.00

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all

Total Subtask 5e $1120.00

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Subtask 5f: Sanitary Hot Tap Inspection (Site 3)

Description: WEC will attend the sanitary hot tap at Site 3.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5f

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 6 $600.00

Engineering Technician 80 0 $0.00

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated (all

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Total Subtask 5f $1120.00

Subtask 5g: Lift Station Start-Up (Site 1)

Description: WEC will attend the Lift Station start-up at Site 1.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5g

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 1 $115.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Total $805.00

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Not anticipated

Not anticipated (all

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Reimbursable Total Cost

Total Subtask 5g $805.00

Subtask 5h: Lift Station Start-Up (Site 2)

Description: WEC will attend the Lift Station start-up at Site .

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5h

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 1 $115.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Printing

Overnight Travel (if applicable)

Not anticipated

Not anticipated (all

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Total Subtask 5h $805.00

Subtask 5i: Lift Station Start-Up (Site 3)

Description: WEC will attend the Lift Station start-up at Site 3.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5i

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 1 $115.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Printing

Not anticipated

Not anticipated (all

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated

Total Subtask 5i $805.00

Subtask 6: Substantial Completion Walk-Through w/Punchlist

Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.

Deliverable: WEC will provide punchlist and input on punch list within one (1) day of Substantial Completion inspection.

Subtask 6

Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 0 $0.00

Engineering Technician 80 0 $0.00

Total $1380.00

Printing Not anticipated

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

Not anticipated

$0.00

Total Subtask 6 $1380.00

Subtask 7: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion Certification of the site with WEC representative attending the Final Completion inspection.

Deliverable: WEC will prepare final as-built drawings based on surveyed information from Contractor and prepare certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 7 - Final

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer

100 8 $800.00

Engineering Technician 80 24 $1920.00

Clerical 55 1 $55.00

Total $4565.00

Mr. John Goss Koreshan State Park CEI Sewage Collection System CN

230 TN 80

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated

Not anticipated

$0.00

Total Subtask 7 $4565.00

Project Schedule:

1-7 180

Summary of Fees:

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 1: Cultural Resources Survey $ 14,995.00 $ 0.00 Subtask 2: Pre-Con Meeting $ 1,790.00 $ 0.00 Subtask 3: Submittals $ 3,290.00 $ 0.00 Subtask 4: RFIs $ 3,275.00 $ 0.00 Subtask 5a: Site Visit Month 1 $ 2,377.50 $ 0.00 Subtask 5b: Site Visit Month 2 $ 2,377.50 $ 0.00 Subtask 5c: Site Visit Month 3 $ 2,377.50 $ 0.00 Subtask 5d: Hot Tap Site 1 $ 1,120.00 $ 0.00 Subtask 5e: Hot Tap Site 2 $ 1,120.00 $ 0.00 Subtask 5f: Hot Tap Site 3 $ 1,120.00 $ 0.00 Subtask 5g: Lift Station Start Up Site 1 $ 805.00 $ 0.00 Subtask 5h: Lift Station Start Up Site 2 $ 805.00 $ 0.00 Subtask 5i: Lift Station Start Up Site 3 $ 805.00 $ 0.00 Subtask 6: Substantial Completion $ 1,380.00 $ 0.00 Subtask 7: Final Completion $ 4,565.00 $ 0.00 Total Fixed Price $ 42,202.50 $ 0.00 total Reimbursable Cost

$ 0.00

Total Overall Cost $ 42,202.50

File details come from the government source that posted it. Updated .