This is a Task Assignment Notification Form and detailed scope of work proposal for the Myakka River State Park Road and Culvert Repairs project under Florida Department of Environmental Protection (FDEP) Contract CN230. The contract involves Weiler Engineering Corporation as the consultant, with FDEP/Division of Recreation and Parks as the owner. The project is located at Myakka River State Park in Florida, with Ralph Perkins serving as the FDEP Contract Manager and Garland Sandel as the FDEP Project Manager.
The contract authorizes Weiler Engineering to provide design, survey, geotechnical, and construction phase services to overlay the existing roadway and repair associated drainage facilities across two segments of the park road. The scope encompasses six major phases: preliminary design (30% plans), survey work, geotechnical investigations, intermediate design (60% and 100% plans), permitting assistance, pre-bid coordination, and comprehensive construction oversight including eight monthly inspections, submittal reviews, regulatory responses, and final completion certification. The total fixed price cost is $191,717.14 with reimbursable costs of $2,027.20, for an overall total task amount of $193,744.34. The project timeline extends 600 calendar days from execution, with key milestones including 60-day survey and geotechnical phases, 120-day completion of final plans, 180-day permit approval process, and eight consecutive 30-day construction inspection periods. Payment is made upon FDEP approval of deliverables for each subtask, with the contract effective upon execution through June 30, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 59 FDEP/DRP 61519C
Myakka River State Park Road and Culvert Repairs
Weiler Engineering
Jeff Weiler (941) 628-4732 weiler7@mac.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@floridadep.gov
To overlay the existing roadway and repair the associated drainage facilities. See proposal dated 2.14.23
Garland Sandel or Successor
Upon Execution $ 191,717.14
6.30.24 $ 2,027.20
$ 193,744.34
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.03.24 15:56:06 -04'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.03.24 16:31:05 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.03.27 10:54:30 -04'00'
Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.03.27 13:04:51 -04'00'
Bryan J. Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.04.04 14:27:20 -04'00'
61519C 37504000056 080039/23 423001 U3200 134000 QK $ 193,744.34
$ 193,744.34
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Segment I
January 10, 2023 - Rev 4 - 02/14/23 Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Our services will generally include: Survey, design and permitting to overlay the existing roadway in two segments utilizing the existing drainage facilities.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
Segment II
Mr. Garland Sandel Myakka State Park Overlay Program
Subtask 1: 30% Design
1) A - Design
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Water Management District or FDEP and the Local Regulatory agency.
c) Consultant will prepare a site plan and typical sections separated into two segments and;
d) Consultant will prepare an opinion of probable cost for each segment
1) B – Surveys
a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey of the existing roadway.
1) C –Geotechnical Reports
a) Consultant will coordinate with Geotechnical Sub-Consultant to conduct core drilling at approximately 1 per 1/2 Mile and prepare a geotechnical Report identifying existing pavement section and LBR’s at every other core.
Deliverable:
1) A - Conceptual Design, Conceptual Site & Structural Plans – Consultant shall deliver 30% Plans to the client via digital PDF. Plans will include:
Cover sheet Survey Existing Conditions Site Plan Typical Sections Opinion of probable cost for two segments
1) B - Surveys
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey via digital PDF, CAD and a Signed and Sealed copy.
1) C –Geotechnical Reports
Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report identifying existing pavement, base and subbase at approximately 1 per 2600 feet of roadway & LBR’s each mile via digital PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A - 30% Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 26 3770
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering
Registered Professional Engineer 145 22 3190
Weiler Engineering Registered Engineer Intern 115 36 4140
Weiler Engineering Senior Engineering Designer 100 88 8800
Weiler Engineering Engineering Technician 80 120 9600
Weiler Engineering Clerical 55 10 550
Total 30245
Subtask 1B - Survey
Mr. Garland Sandel Myakka State Park Overlay Program
Reimbursable Cost: (if applicable)
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 8 1160
CHW 3 Person Field Crew Hr 177.54 200 35508
CHW Project Surveyor Hr 74.75 120 8970
CHW Senior CAD/GIS Hr 103.13 120 12375.6
CHW Professional Surveyor & Mapper
Hr 163.93 6 983.58
Total Survey 58997.18
Subtask 1C Geotech
Firm Name Position Classification Unit Unit Rate Numbe r Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 4 580
Geotech
Universal Senior Project Engineer Hr 165.84 24 3980.16
Universal Project Engineer Hr 94.50 24 2268
Universal Staff Engineer Hr 68.46 30 2053.8
Universal CAD Drafting Hr 54.00 12 648
Total Geotech 9529.96
Description Number @ Total
Postage
Printing
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 2: 60% documents
Description: Plans completed to 60% incorporating comments from 30%.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost;
Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plans Site Details and General Notes
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 1A
Total Subtask 1 98772.14
Subtask 2 - 60% Plans
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 26 3770
Weiler Engineering Principal in Charge 195 1 195
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 3: 100% documents
Description: Plans completed to 100%.
Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Opinion of Probable Cost;
Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site/Drainage Details and General Notes
Specifications
Engineering
Registered Professional Engineer 145 22 3190
Weiler Engineering Registered Engineer Intern 115 35 4025
Weiler Engineering Senior Engineering Designer 100 88 8800
Weiler Engineering Engineering Technician 80 121 9680
Weiler Engineering Clerical 55 7 385
Total 30045
Total for Subtask 2
30045
Subtask 3 - 100% Plans
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Reimbursable Cost:
Subtask 4: Permitting
Description:
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 18 2610
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering
Registered Professional Engineer 145 14 2030
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 58 5800
Weiler Engineering Engineering Technician 80 80 6400
Weiler Engineering Clerical 55 8 440
Total 20235
Description Number @ Total
Postage 1 35 35
Printing 64 2.30 147.2
Reimbursable Total Cost
182.2
Total for Subtask 3
20417.2
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
4) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for exemption.
4) B – Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
4) A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five sets of permit applications with 100% plans.
4) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation
Subtask 4A Permit Applications
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 18 2610
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering Registered Professional Engineer 145 15 2175
Engineering Registered Engineer Intern 115 23 2645
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Engineering Senior Engineering Designer 100 24 2400
Weiler Engineering Engineering Technician 80 24 1920
Weiler Engineering Clerical 55 7 385
Total 12330
Subtask 4B Permit Approvals
Rate Hours Total Fixed
Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering Registered Professional Engineer 145 6 870
Weiler Engineering Registered Engineer Intern 115 10 1150
Weiler Engineering Senior Engineering Designer 100 16 1600
Weiler Engineering Engineering Technician 80 16 1280
Weiler Engineering Clerical 55 1 55
Total 6310
Description Number @ Total
Postage 1 35 35
Printing 200 2.3 460
Permit application fees estimate
1 1000 1000
Mr. Garland Sandel Myakka State Park Overlay Program
Subtask 5: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Reimbursable Cost:
Reimbursable Total Cost for 4A
Total for Subtask 4
20135
Subtask 5 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 $1160.00
Weiler Engineering Principal in Charge 195 0 $0.00
Weiler Engineering Registered Professional Engineer
145 0 $0.00
Weiler Engineering Registered Engineer Intern 115 8 $920.00
Weiler Engineering Senior Engineering Designer 100 8 $800.00
Weiler Engineering Engineering Technician 80 8 $640.00
Weiler Engineering Clerical 55 0 $0.00
Total $3520.00
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6A - 6N: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)
Subtask 6A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Description Number @ Total Postage Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
$0.00
Reimbursable Total Cost $0.00
Total Subtask 5 $3520.00
Subtask 6A - Pre-Construction Mtg
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6B: Review Contractor submittals
Description:WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Weiler Engineering Senior Engineering Designer 100 0 0
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 2080
Description Number @ Total
Postage 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 0
Reimbursable Total Cost 0
Total subtask 6A 2080
Subtask 6B - Review Submittals
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6C: Respond to Building Department comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Deliverable: RFI response documents submitted to Building Department.
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 12 1200
Weiler Engineering Engineering Technician 80 2 160
Weiler Engineering Clerical 55 2 110
Total 2680
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 6B 2715
Subtask 6C
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6D: Respond to Contractor RFI's
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1980
Description Number @ Total
Postage 35 0
Printing 2.30 0.00
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
Total - 6C 1980
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Subtask 6D- Respond to RFI’s
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 2 290
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 4 220
Total 2520
Description Number @ Total
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 6D 2520
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6E: Provide Construction Inspections (Month 1)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 6E - Month 1 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6F: Construction Inspection (Month 2)
Total Subtask 6E 1007.5
Subtask 6F
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6G: Construction Inspection (Month 3)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost
Total Subtask 6F 1042.5
Subtask 6G Month 3 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Postage 1 35 35
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6H: Construction Inspection (Month 4)
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 7G 1042.5
Subtask 6H - Inspection Month 4
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6I: Construction Inspection (Month 5)
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 35
Total Subtask 6H 1042.5
Subtask 6I Month 5 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6J: Construction Inspection (Month 6)
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6I 1042.5
Subtask 6J Month 6 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6K: Construction Inspection (Month 7)
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6J 1042.5
Subtask 6K Month 7 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6L: Construction Inspection (Month 8)
Weiler Engineering Clerical 55 0 0
Total 1007.5
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6K 1042.5
Subtask 6L Month 8 Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6M: Substantial Completion Walk-Through w/Punchlist
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6L 1042.5
Subtask 6M substantial
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 6N: Final Completion w/ Certification
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager.
Weiler Engineering Poject Manager 145 6 870
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1805
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6M 1840
Subtask 6N - Final
Mr. Garland Sandel Myakka State Park Overlay Program
Project Schedule:
Weiler Engineering Poject Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 2 200
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1380
Description Number @ Total
Postage 1 35 35
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 35
Total Subtask 6N 1415
Activity Duration (Calendar Days) Days from Execution
Subtask 1A ** Preliminary 60 60
Subtask 1B Survey 60 60
Subtask 1C Geotech 60 60
Subtask 2: 60% plans 30 - includes 7 days for Client review
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Subtask 3: 100% plans 30 – includes 7 days for Client review
Subtask 4A: Permit applications 30 – includes 7 days for Client review
Subtask 4B: Permit approvals 60 – includes response for additional information
Subtask 5: Prebid 30 210
Subtask 6A - Pre construction 30 210
Subtask 6B: Review Submittals 30 240
Subtask 6C: Respond to RAI's 60 300
Subtask 6D: Respond to Contractor RFI's
240 (Est max overall calendar days;
RFI's will be responded to within 7 days of receipt from Contractor)
Subtask 6E: Provide Construction Inspections w/ (Month 1)
30 330
Subtask 6F: Provide Construction Inspections w/ Report (Month 2)
30 360
Subtask 6G: Provide Construction Inspections w/ Report (Month 3)
30 390
Subtask 6H: Provide Construction Inspections w/ (Month 4)
30 420
Subtask 6I: Provide Construction Inspections w/ Report (Month 5)
30 450
Subtask 6J: Provide Construction Inspections w/ (Month 6)
30 480
Subtask 6K: Provide Construction Inspections w/ (Month 7)
30 510
Subtask 6L: Provide Construction Inspections w/ (Month 8)
30 540
Subtask 6M: Substantial Completion Walk-Through w/ Punchlist
30 570
Subtask 6N: Final Completion w/ Certification
30 600
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A Preliminary $30245.00 $0.00
Subtask 1B Survey $58997.18 $0.00
Subtask 1C Geotech $9529.96 $0.00
Subtask 2: 60% plans $30045.00 $0.00
Subtask 3: 100% plans $20235.00 $182.20
Subtask 4A Permit applications $12330.00 $1495.00
Subtask 4B Permit approvals $6310.00 $0.00
Subtask 5 Pre-Bid $3520.00 $0.00
Total Design & Permitting $171212.14 $1677.20
Subtask 6A - Pre-Construction Meeting
$2080.00 $0.00
Subtask 6B - Submittal Review $2680.00 $35.00
Subtask 6C - Regulatory Response
$1980.00 $0.00
Subtask 6D Assistance during construction
$2520.00 $0.00
Subtask 6E Inspection 1 $1007.50 $0.00
Subtask 6F Inspection 2 $1007.50 $35.00
Subtask 6G Inspection 3 $1007.50 $35.00
Subtask 6H Inspection 4 $1007.50 $35.00
Subtask 6I Inspection 5 $1007.50 $35.00
Subtask 6J Inspection 6 $1007.50 $35.00
Subtask 6K Inspection 7 $1007.50 $35.00
Subtask 6L Inspection 8 $1007.50 $35.00
Subtask 6M Substantial Completion
$1805.00 $35.00
Subtask 6N Final Completion $1380.00 $35.00
Total during Construction $20505.00 $350.00
Mr. Garland Sandel Myakka State Park Overlay Program
CN 230/TA56
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Total Fixed Price Cost: $191717.14
Total Fixed Price Cost: $2027.20
Overall Total Cost: $193744.34
Mr. Garland Sandel Myakka State Park Overlay Program
Labor Rate Category Base Hourly Rate
(Direct) Audited OH &
Benefits % Direct Cost
FCCM % Operating
Allowance FCW Billing
Rates 100.00% 166.68% 7.89% 2.70% 15.00% 292.27%
2.92
Land Surveying Division Director/Professional Surveyor & Mapper $66.12 $110.21 $5.22 $1.79 $9.92 $193.07
Senior Project Manager $57.35 $95.59 $4.52 $1.55 $8.60 $167.46
Professional Surveyor & Mapper $56.14 $93.57 $4.43 $1.52 $8.42 $163.93
Chief of Surveyors/Project Surveyor $25.60 $42.67 $2.02 $0.69 $3.84 $74.75
2-Man Field Crew $43.91 $73.19 $3.46 $1.19 $6.59 $128.22
3-Man Field Crew $60.80 $101.34 $4.80 $1.64 $9.12 $177.54
GPS Field Operator/Robotics(1 man) $25.23 $42.05 $1.99 $0.68 $3.78 $73.67
Field Technician $21.73 $36.22 $1.71 $0.59 $3.26 $63.45
All Divisions Principals/Vice Presidents $89.96 $149.95 $7.10 $2.43 $13.49 $262.68
Senior CADD/GIS Designer $35.32 $58.87 $2.79 $0.95 $5.30 $103.13
CADD DesignerII/GIS Designer $28.35 $47.25 $2.24 $0.77 $4.25 $82.78
CADD DesignerI/GIS Technician $26.56 $44.27 $2.10 $0.72 $3.98 $77.56
Project Assistant/Administrative Assistant $24.13 $40.22 $1.90 $0.65 $3.62 $70.46
Certified True & Correct
John Howard Vice President of Finance + Operations 2/8/23
Causseaux, Hewett, & Walpole, Inc.
dba CHW Civil Engineering, Planning, Permitting, Surveying and Mapping, Construction Management and Inspection
Total Multiplier 2.92
Mr. Garland Sandel Myakka State Park Overlay Program
| TA Form 61519C CN-230, TA 56.pdf |
| rev 4 021323 Proposal Myakka SP Repaving copy.pdf |