CN-370000-CN230-T25CO3.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|CN230|5f4ec01f5eb38b1957861cb8292c2183
Contract number
CN230
Issued by
Florida

About this file

This is a Task Assignment Change Order Form (Change Order No. 3) issued by the Florida Department of Environmental Protection (FDEP) for Project CN230 at Myakka River State Park. The contract involves FDEP and the consultant Weiler Engineering Corporation, Inc., with FDEP Contract Manager Jeffrey Whitfield and consultant representative Jeff Weiler, PE. The project involves construction engineering and inspection (CEI) services for concession building structural repairs at the state park location.

The change order authorizes additional engineering, permitting, and construction services for discovered damaged structural, finishes, and mechanical elements. The scope includes MEP (mechanical, electrical, plumbing) inspections, 90% and final construction document preparation, permitting coordination with the State Fire Marshal, contractor submittals review, RFI responses, and multiple inspection phases throughout construction. The total change order cost is $82,695.50, comprised of $79,910.00 in fixed price costs and $2,785.50 in reimbursable costs (including a $2,000 State Fire Marshal application fee). The project timeline extends 215 business days from the original task end date of July 1, 2021, to a new end date of August 23, 2023. Services are organized into 13 subtasks (14A through 26) with individual fixed and reimbursable cost allocations, and payment will be made upon FDEP approval of deliverables for each subtask. The subconsultant ATLAS Design & Engineering Inc. provides mechanical, electrical, and plumbing engineering support with specified hourly rates ranging from $71.00 to $178.00 for unloaded labor plus applicable fringe benefits, overhead, and profit markups.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
CN-370000-CN230-T53CO1.pdf PDF
CN-370000-CN230-T57.pdf PDF
CN-370000-CN230-T59.pdf PDF
CN-370000-CN230-T60.pdf PDF
CN-370000-CN230-T64.pdf PDF
CN-370000-CN230-T66.pdf PDF
CN-370000-CN230-T7.pdf PDF
CN-370000-CN230-T70.pdf PDF
CN-370000-CN230-T72.pdf PDF
CN-370000-CN230-T75.pdf PDF
CN-370000-CN230-T8.pdf PDF
CN-370000-CN230-T80.pdf PDF
CN-370000-CN230-T82CO1.pdf PDF
CN-370000-CN230-T86.pdf PDF
CN-370000-CN230-T87.pdf PDF
CN-370000-CN230-T89.pdf PDF
CN-370000-CN230-T90.pdf PDF
CN-370000-CN230-TA30.pdf PDF
CN-370000-CN230-TA5CO1.pdf PDF
CN-370000-CN230.pdf PDF
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T21CO1.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
CN-370000-CN230-T34CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN230 TA25 CO3 61231C

Myakka River State Park Project Name:

Concession

Weiler Engineering Corporation, Inc.

Jeff Weiler (941)505-1700 weiler7@mac.com

Jeffrey Whitfield (850)245-2630 Jeffrey.Whitfield@FloridaDEP.gov Description and Justification of Change:

Additional engineering, permitting, and time for discovered damaged structural, finishes and mechanical elements. As per attached proposal dated

$ 434.70 $ 13,427.50 $ 13,862.20 $ 569.60 $ 36,529.90 $ 37,099.50

$ 2,652.91 $ 76,610.00 $ 79,262.91 $ 3,222.51 $ 113,139.90 $ 116,362.41

08/19/2020

7/1/2021

12/31/2022

8/23/2023

Diane Langston

John Goss

Jeffrey Whitfield

Jeff Weiler, PE

Bryan J. Bradner

61231C 37504000056 080039/21 675002 U3200 131500 XR $ 79,262.91

$ 79,262.91

.5/12/2022.

Repairs

Bryan Bradner Digitally signed by Bryan Bradner Date: 2022.06.07 10:17:57 -04'00'

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

May 12, 2022

Mr. John Goss Florida Department of Environmental Protection Division of Recreation and Parks Bureau of Design and Construction Assistant Project Manager Oscar Scherer State Park 1843 Tamiami Trail Osprey, FL 34229

RE: Project CN230 Task Assignment 25 – Change Order 3

Myakka River State Park Concession CEI, CO for additional scope and services

Dear Mr. Goss;

Thank you for the opportunity to provide this Change Order proposal for additional Construction Services necessary to repair the damaged structure at Myakka River State Park. It is our understanding that the Florida Department of Environmental Protection (Client) wishes to have the Weiler Engineering Corporation (WEC), the “Consultant,” expand their scope of work to include HVAC systems, mounting, and the associated structure remediation. Our services will include the following:

WEC has been asked to revise the existing permitted drawings as to adjust the scope of work per FDEP preference based on WEC’s original recommendations, as new funding has become available.

WEC will conduct a Site Visit to inspect the current conditions as to determine the extent of repairs required upon park staff removal of the outdoor ceiling finish. The drafting and engineering changes to plans will be made for building permit modifications. The Construction Document Plans sets will be significantly altered as to expand the scope for inclusion of the remainder of the building including roof‐ mounted mechanical components and the roof deck. Additionally, during construction, further inspections of the framing and truss modifications will be provided by WEC.

WEC will specify a rail‐mount system for the air conditioning and kitchen mechanical equipment, including the make‐up air unit, grease hood, refrigerator, and freezer condensing units. The Client’s Contractor (DEC) will make recommendations compatible with the selected equipment and mounting substrate. WEC shall design and specify the method of attachment of the rail system to the structure. Existing equipment to remain shall be compatible with the proposed rail attachment system, including the existing make‐up

Project CN230 Task Assignment 25 Change Order 3

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG air unit. New equipment, such as the roof‐top grease hood and the walk‐in freezer coil and condenser, shall also be rail mounted. Equipment specifications shall be provided to WEC by ATLAS Design & Engineering Inc. (“ATLAS”), the “Subconsultant,” to aid in the proper design of the attachment of the supporting rail mount to the structure. Additionally, repair drawings shall be provided by WEC to remediate leaks adjacent to the existing grease hood. Plumbing repairs are to include the downspouts, drainage diverters, gutters, and any other components necessary to facilitate a complete roof drainage system. Electrical repairs shall be detailed as they relate to the modifications which are impacted by these repairs.

WEC shall coordinate the design of the replacement condenser deck and adjacent knee wall and shall perform an inspection of the final wall and deck after construction.

The Construction Documents provided by WEC shall include air conditioner condenser deck boards, railings, damaged framing areas, and siding associated with condenser platform area. Repair and replacement drawings of the small roof area above the concession building main front door area shall also be included.

ATLAS Engineering & Design, Inc. shall be retained by WEC to provide Mechanical, Electrical, and Plumbing (MEP) engineering plan sets, consulting, and review as well as inspection, RFI, and submittal review phases.

Enclosed is a proposal summary and man‐hour documentation for these services and subtasks identified below. Please review the attached Proposal Summary and deliverables.

As always, please let me know if you need anything.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Construction Phase Services CO for Concession Building Structural Repair Myakka River State Park

Project CN230 Task Assignment 25 Change Order 3

Subtask 14: MEP Inspection for Scope Change #2

Description: Consultant shall coordinate with ATLAS Design & Engineering Inc. who will visit the site to perform up to three (3) site inspection regarding expanding the scope for additional demolition and alterations.

Deliverable: Consultant shall deliver inspection report documenting findings (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 14A

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Engineer Intern 115 1 115.00

Clerical 55 1 55.00

ATLAS Design & Engineering Inc.

Professional Engineer 150 8 1,200.00

Project Manager 150 2 300.00

Administrative 75 1 75.00

Total 1,890.00

Subtask 14B

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Engineer Intern 115 1 115.00

Clerical 55 1 55.00

ATLAS Design & Engineering Inc.

Professional Engineer 150 8 1,200.00

Project Manager 150 2 300.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Administrative 75 1 75.00

Total 1,890.00

Subtask 14C

Weiler Engineering Project Manager 145 1 145.00

Registered Engineer Intern 115 1 115.00

Clerical 55 1 55.00

ATLAS Design & Engineering Inc.

Professional Engineer 150 8 1,200.00

Project Manager 150 2 300.00

Administrative 75 1 75.00

Total 1,890.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) (3) 180 Miles x 0.445 = (3) $80.10

Reimbursable Total Cost (3) $80.10 = $240.30

Subtask 14A Subtotal: $1,970.10 Subtask 14B Subtotal: $1,970.10 Subtask 14C Subtotal: $1,970.10

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 15: Structural Inspection for Scope Change #2

Description: Consultant will visit the site to perform an additional inspection regarding expanding the scope for additional demolition and alterations.

Deliverable: Consultant shall deliver inspection report documenting findings (email only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 15

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Professional Engineer

145 2 290.00

Registered Engineer Intern 115 8 920.00

Clerical 55 1 55.00

Total 1,410.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) 118 Miles x 0.445 = $52.50

Reimbursable Total Cost $52.50

Subtask 15 Subtotal: $1,462.50

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 16: 90% MEP Plans

Description: Consultant will coordinate with subconsultant who will create MEP 90% progress documents.

Deliverable: Consultant shall deliver 90% MEP progress set for review and comment by the Department (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 16

Weiler Engineering Project Manager 145 16 2,320.00

Registered Engineer Intern

115 8 920.00

Clerical 55 4 220.00

ATLAS Design & Engineering Inc. Professional Engineer 150 30 4,500.00

Senior MEP Designer 100 160 16,000.00

Project Manager 150 15 2,250.00

Administrative 75 6 375.00

Total 26,585.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost 0

Subtask 16 Subtotal: $26,585.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 17: 90% Structural Plans

Description: Consultant will create structural 90% progress documents.

Deliverable: Consultant shall deliver 90% structural progress set for review and comment by the Department (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 17

Weiler Engineering Project Manager 145 26 3,770.00

Registered Professional Engineer

145 12 1,740.00

Registered Engineer Intern

115 130 14,950.00

Senior Engineering Designer

100 40 4,000.00

Clerical 55 2 110.00

Total 24,570.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Subtask 17 Subtotal: $24,570.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 18: Response to FDEP 90%Comments

Description: Consultant will review and reply as necessary where comments from FDEP are made regarding the 90% progress plans.

Deliverable: Consultant shall deliver a formal response letter regarding the received comments (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 18

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Engineer Intern 115 4 460.00

Clerical 55 1 55.00

Total 660.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Subtask 18 Subtotal: $660.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 19: Final Signed‐and‐Sealed Structural Plans

Description: Consultant will create final signed and sealed construction documents based upon the 90% review comments received from FDEP.

Deliverable: Consultant shall deliver final signed and sealed construction documents (digital PDF and five (5) physical copies).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 19

Weiler Engineering Project Manager 145 4 870.00

145 4 580.00

Senior Engineering Designer 100 20 2,000.00

Clerical 55 1 55.00

Total 3,505.00

Reimbursable Cost:

Postage Not anticipated

Printing 5 sets at 10 sheets for $2.80/sheet: $140.00

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost $140.00

Subtask 19 Subtotal: $3,645.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 20: Final Signed‐and‐Sealed MEP Plans

Description: Consultant will coordinate with subconsultant who will create final signed and sealed construction documents based upon the 100% review comments received from FDEP.

Deliverable: Consultant shall deliver final signed and sealed construction documents (digital PDF and five (5) physical copies).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 20

Weiler Engineering Project Manager 145 4 580.00

145 3 435.00

Clerical 55 1 55.00

ATLAS Design & Engineering, Inc.

Professional Engineer 150 8 1,200.00

Senior MEP Designer 100 20 2,000.00

Shop Drawings Review 150 20 3,000.00

Project Manager 150 4 600.00

Administrative 75 1 75.00

Total 7,945.00

Reimbursable Cost:

Postage Not anticipated

Printing 5 sets at 10 sheets for $2.80/sheet: $140.00

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost $140.00

Subtask 20 Subtotal: $8,085.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 21: Permitting

21A Description: Consultant shall assist Client to submit permit application to State Fire Marshal

21A Deliverable: Consultant shall submit an electronic application to the State Fire Marshal.

21B Description: Consultant shall coordinate with agencies and assist Client to respond to agencies for additional information.

21B Deliverable: Consultant shall respond to agency request for additional information and copy Client on all responses. Upon approval, Consultant shall provide Client with approvals and revise plans and documentation if necessary.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 21

Weiler Engineering Project Manager 145 2 290.00

145 2 290.00

Registered Engineer Intern 115 3 345.00

Total 925.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost 2,000.00 (State Fire Marshal Application Fee)

Subtask 21 Subtotal: $2,925.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 22: Contractor Submittals

Description: Consultant will assist Client in reviewing product submittals including alternates and shop drawings during construction. Where Consultant’s involvement is required for submittal reviews, a draft will be submitted to the FDEP Construction Project Consultant for review and comment.

Deliverable: Consultant will provide digital PDFs of submittals stamped as approved, approved with comment, or denied within five (5) business days of receipt from Client.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 22

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290.00

Registered Professional Engineer 145 2 290.00

Registered Engineer Intern 115 6 690.00

Senior Engineering Designer 100 4 400.00

Clerical 55 1 55.00

Total 1,725.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Subtask 22 Subtotal: $1,725.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 23: Contractor and Reviewer RFI

Description: Consultant will assist in responding to the Client’s Contractor and Plans Reviewer regarding any requests for additional information throughout the construction process. Where Consultant’s involvement is required for RFI responses, a draft will be submitted to the FDEP Construction Project Consultant for review and comment.

Deliverable: RFI responses will be issued by Consultant as digital PDFs within three (3) business days of receipt from Client.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 23

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290.00

Registered Professional Engineer 145 2 290.00

Registered Engineer Intern 115 6 690.00

Senior Engineering Designer 100 4 400.00

Clerical 55 1 55.00

Total 1,725.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Subtask 23 Subtotal: $1,725.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 24: Post‐Demolition MEP Inspection

Description: Consultant will coordinate with ATLAS Design & Engineering Inc. to visit the site to perform one (1) additional inspection regarding the MEP‐related elements of the scope of work.

Deliverable: Consultant shall deliver inspection report documenting findings (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 24

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Engineer Intern 115 1 115.00

Clerical 55 1 55.00

ATLAS Design & Engineering Inc.

Professional Engineer 150 8 1,200.00

Project Manager 150 2 300.00

Administrative 75 1 75.00

Total 1,890.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) 180

Reimbursable Total Cost 80.10

Subtask 24 Subtotal: $1,970.10

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 25: Framing Inspection

Description: Consultant will visit the site to perform one (1) additional inspection regarding the framing‐related elements of the scope of work.

Deliverable: Consultant shall deliver inspection report documenting findings (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 25

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Professional Engineer 145 2 290.00

Registered Engineer Intern 115 8 920.00

Clerical 55 1 55.00

Total 1,410.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) 118 Miles x 0.445 = $52.50

Reimbursable Total Cost 52.50

Subtask 25 Subtotal: $1,462.50

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Subtask 26: MEP Substantial Completion Inspection

Description: Consultant will coordinate with ATLAS Design & Engineering Inc. to visit the site to perform one (1) additional inspection regarding the MEP‐related elements of the scope of work.

Deliverable: Consultant shall deliver inspection report documenting findings (digital PDF only).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 26

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 145.00

Registered Engineer Intern 115 1 115.00

Clerical 55 1 55.00

ATLAS Design & Engineering Inc.

Professional Engineer 150 8 1,200.00

Project Manager 150 2 300.00

Administrative 75 1 75.00

Total 1,890.00

Reimbursable Cost:

Postage Not anticipated

Printing No prints/provided digitally via email

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) 180

Reimbursable Total Cost 80.10

Subtask 26 Subtotal: $1,970.10

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Project Schedule:

Activity Duration (Business Days)

Subtask 14: MEP Inspection for Scope Change #2 10

Subtask 15: Structural Inspection for Scope Change #2 10

Subtask 16: 90% MEP Plans 90

Subtask 17: 90% Structural Plans 90

90% Response Period from Client 10

Subtask 18: Response to FDEP 90% Comments 30

Subtask 19: Final Signed‐and‐Sealed Structural Plans 30

Subtask 20: Final Signed‐and‐Sealed MEP Plans 30

Subtask 21: Permitting 45

Subtask 22: Contractor Submittals 90

Subtask 23: Contractor and Reviewer RFI 90

Subtask 24: Post‐Demolition MEP Inspection 90

Subtask 25: Framing Inspection 10

Subtask 26: MEP Substantial Completion Inspection 10

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Summary of Fees:

Subtask Subtask Fixed Price

Cost

Subtask Reimbursable

Subtask 14A: MEP Inspection 1 for Scope Change #2 1,890.00 80.10 Subtask 14B: MEP Inspection 2 for Scope Change #2 1,890.00 80.10

Subtask 14C: MEP Inspection 3 for Scope Change #2 1,890.00 80.10

Subtask 15: Structural Inspection for Scope Change #2 1,410.00 52.50

Subtask 16: 90% MEP Plans 26,585.00 0.00

Subtask 17: 90% Structural Plans 24,570.00 0.00

Subtask 18: Response to FDEP 90% Comments 660.00 0.00

Subtask 19: Final Signed‐and‐Sealed Structural Plans 3,505.00 140.00

Subtask 20: Final Signed‐and‐Sealed MEP Plans 7,945.00 140.00

Subtask 21: Permitting 925.00 2,000.00

Subtask 22: Contractor Submittals 1,725.00 0.00

Subtask 23: Contractor and Reviewer RFI 1,725.00 0.00

Subtask 24: Post‐Demolition MEP Inspection 1,890.00 80.10

Subtask 25: Framing Inspection 1,410.00 52.50

Subtask 26: MEP Substantial Completion Inspection 1,890.00 80.10

Total Fixed Price Cost: $79,910.00

Total Reimbursable Cost: $2,785.50

Change Order Total Cost: $82,695.50

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE ‐ SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941‐505 ‐1700 | FAX 941‐505 ‐1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 ‐289 ‐4161 | FAX 305 ‐289 ‐416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

here.pdf
Myakka CEI TACO3 DRAFT 20220512.pdf

File details come from the government source that posted it. Updated .