About this file

This is a Task Assignment Notification Form and accompanying proposal from the Florida Department of Environmental Protection (FDEP) for design and permitting services related to the Stump Pass Beach State Park Repair Roads & Parking Area project. The task assignment was issued to Weiler Engineering Corporation (WEC), an engineering firm with offices in Punta Gorda and Marathon, Florida, under FDEP Contract CN230, Task Assignment Number 66. The project manager is Terry McCullum Jr. from FDEP's Bureau of Design and Construction, and the consultant representative is Robin Palmer, P.E. from Weiler Engineering Corporation.

The scope of work encompasses comprehensive design and permitting services for constructing a turnaround at the north entrance of Stump Pass Beach State Park, including survey work, environmental assessments, regulatory permitting, design development at 30%, 60%, and 100% completion stages, and construction administration services. The contract establishes a fixed price cost of $86,352.20 and cost reimbursement not to exceed $13,404.00, for a total task amount of $99,756.20. Services include survey preparation, Florida Land Use Cover and Forms Classification System mapping, listed species surveys, gopher tortoise surveys and relocation permits and services, mangrove trimming permits, and permit applications and approvals. Construction administration services include bidding assistance, pre-construction meeting attendance, submittal review, assistance during construction for three months, substantial completion inspection, and final completion certification. The project completion date is June 30, 2025, with payment to be made upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC2.pdf PDF
CN-370000-CN230-CMC4.pdf PDF
CN-370000-CN230-T10.pdf PDF
CN-370000-CN230-T18CO1.pdf PDF
CN-370000-CN230-T19.pdf PDF
CN-370000-CN230-T21CO1.pdf PDF
CN-370000-CN230-T23.pdf PDF
CN-370000-CN230-T23CO1.pdf PDF
CN-370000-CN230-T25CO2.pdf PDF
CN-370000-CN230-T26CO1.pdf PDF
CN-370000-CN230-T29.pdf PDF
CN-370000-CN230-T2CO3.pdf PDF
CN-370000-CN230-T34CO1.pdf PDF
CN-370000-CN230-T37.pdf PDF
CN-370000-CN230-T37CO1.pdf PDF
CN-370000-CN230-T42CO1.pdf PDF
CN-370000-CN230-T42CO3.pdf PDF
CN-370000-CN230-T43.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 66 FDEP 61473C

Stump Pass Beach State Park Repair Roads & Parking Area

Weiler Engineering Corporation

Robin Palmer, P.E. (941) 550-1700 rpalmer@weilerengineering.org

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Consultant to provide design, permitting, and construction administration services for the construction of a turnaround at the north entrance of Stump Pass Beach State Park, per attached proposal dated April 7, 2023.

Terry McCullum, Jr. or successor

Upon Execution $ 86,352.20 $ 13,404.00 $ 99,756.20

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.04.10 11:03:12 -04'00'

Terry McCullum, Jr. Terry McCullum, Jr.

Digitally signed by Terry McCullum, Jr.

Date: 2023.04.10 13:03:17 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.04.11 09:41:31 -04'00'

Robin Palmer, P.E. Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.04.17 09:55:26 -04'00'

Michael W. Foster Jr., P.E.

61473C 37504003099 080039/23 423001 U3200 131500 QK $ 99,756.20

$ 99,756.20

6/30/2025

Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.04.20 16:22:32 -04'00'

December 20, 2022 - Revision 4 – April 7, 2023

Mr. Terry McCullum, Jr Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399

RE: Stump Pass Road and Parking Area Repair- Contract 230, Dear Mr. McCullum, We are pleased to submit this proposal for design and permitting to make the following repairs and modifications to the above referenced facility generally including:

· Turn around at entrance o Gates to move backwards into the park o Big turn around for truck or small motorhome o Beach access at front of the park is no longer there o First ADA space is no longer there o Entrance to remain gravel. Bryon prefers paved, but likely cost prohibitive.

§ Provide cost estimates

· Paving ADA spaces and entrances as an option

· Pricing for paving all the way up to circle o Consider storm surge with gate power

· Electric gates to automatically close

· Parking spaces are not correctly spaced (too tight) o Remove some wheel stop/re-space them. (Gravel parking)

· Mangroves present, may need to pull; turn around into parking

· Fencing (particularly on East side) needed. Aluminum fencing with foot gate/ pedestrian to allow people to walk in if no parking available.

For your review, following is a man-hour budget and associated fees.

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

NEW GATE LOCATION

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Stump Pass - Parking & Roadway Repairs/Modifications Design & Permitting

Contract Number 230, Subtask 1: Survey Description: The Weiler Engineering Corporation (Consultant) will coordinate with a Florida Registered Surveyor to prepare a special purpose survey adequate for design and permitting.

Deliverable: Consultant will provide a Signed and Sealed Special Purpose topographic a (Not a Boundary Survey) in PDF and AutoCad format via email to the District Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1 - Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 5 725

CHW 3 Man Field Crew Hr 177.54 10 1775.4

CHW Senior CAD/GIS Hr 103.13 16 1650.08

CHW Professional Surveyor & Mapper

Hr 163.93 4 655.72

Total Survey $4806.20

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 1 Survey

$4806.20

Subtask 2: Environmental

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

2.1 Florida Land Use, Cover and Forms Classification System FLUCFCS Description: Consultant will coordinate with Environmental Consultant to conduct filed work to map vegetation communities per FLUCFCS and prepare a Florida Land Use, Cover and Forms Classification System Map (FLUCFCS).

Deliverable: Consultant shall deliver FLUCFCS map in PDF format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.1 - FLUCFCS

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Passarella Senior Ecologist Hr 149.50 1 149.5

Ecologist Hr 104.65 4 418.6

Design/GIS Hr 89.70 6 538.2

Administrative Hr 71.76 1 71.76

Total $1758.06

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 2.1

FLUCFCS

$1758.06

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

2.2 Listed Species Survey

Description: Consultant will coordinate with Environmental Consultant to complete a Listed Species Survey.

Deliverable: Location of listed species on aerial & report summarizing results of survey in PDF format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.2 - Listed Species Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Passarella Senior Ecologist Hr 149.50 4 598

Passarella Ecologist Hr 104.65 8 837.2

Passarella Design/GIS Hr 89.70 6 538.2

Passarella Administrative Hr 71.76 1 71.76

Total 2625.16

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 2.2 Listed Species

$2625.16

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

2.3 Fish & Wildlife Conservation Commission (FWCC) Gopher Tortoise Survey Description: Consultant will coordinate with Environmental Consultant to complete a Gopher Tortoise survey.

Deliverable: Location of burrows on aerial in PDF format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.3 - Gopher Tortoise Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Passarella Senior Ecologist Hr 149.50 4 598

Passarella Ecologist Hr 104.65 6 627.9

Passarella Design/GIS Hr 89.70 4 358.8

Passarella Administrative Hr 71.76 1 71.76

Total 2236.46

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 2.3 Gopher Tortoise Survey

$2236.46

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

2.4 FWCC Gopher Tortoise Relocation Permit Application

Description: Consultant will coordinate with Environmental Consultant to prepare a Gopher Tortoise survey.

Deliverable: FWCC application for Gopher Tortoise relocation permit for Client’s signature in PDF format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.4 - Gopher Tortoise Relocation Permit

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 8 1160

Passarella Senior Ecologist Hr 149.50 8 1196

Passarella Ecologist Hr 104.65 16 1674.4

Passarella Design/GIS Hr 89.70 22 1973.4

Passarella Administrative Hr 71.76 2 143.52

Total 6147.32

Desc Unit Rate/Unit Number

Postage

Printing

Permit Fee

Mileage (@ $0.445 per mile)

10 Burrows 223 1 223

Reimbursable Total Cost

$223.00

Total Subtask 2.4 Gopher Tortoise Permit

$6370.32

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

2.5 Gopher Tortoise Relocation

Description: Consultant will coordinate with Environmental Consultant to conduct observations of backhoe excavation and assist with relocation efforts, deliver gopher tortoises to recipient site, if applicable, and prepare a relocation report for submittal.

Deliverable: Relocation report for submittal to FWCC in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.5- Gopher Tortoise Relocation

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 8 1160

Passarella Senior Ecologist Hr 149.50 8 1196

Passarella Ecologist Hr 104.65 16 1674.4

Passarella Design/GIS Hr 89.70 2 179.4

Passarella Administrative Hr 71.76 1 71.76

Total 4281.56

Desc Unit Rate/Unit Number

Postage 0 Printing 0 Recipient site fee EA 6000 2 12000 estimate 5 Mileage (@ 0 $0.445 per mile) Reimbursable Total Cost

$12000.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Total Subtask 2.5 Gopher Tortoise Relocation

$16281.56

2.6 Mangrove Trimming Permit Application

Description: Consultant will coordinate with Environmental Consultant to prepare a mangrove trimming permit application and a mangrove trimming plan for submittal to the Florida Department of environmental protection.

Deliverable: Mangrove trimming permit application submitted to Client for signature in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.6- Mangrove Trimming Permit

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Passarella Senior Ecologist Hr 149.50 6 897

Passarella Ecologist Hr 104.65 16 1674.4

Passarella Design/GIS Hr 89.70 16 1435.2

Passarella Administrative Hr 71.76 2 143.52

Total 4730.12

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Total Subtask 2.6 Mangrove Trimming Permit Application

$4730.12

2.7 Mangrove Trimming Permit Review

Description: Consultant will coordinate with Environmental Consultant to respond to regulatory review requests and coordinate same with Client.

Deliverable: RAI responses to review agency and permit decision will be provided in PDF format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2.7 - Mangrove Trimming Permit Review

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Passarella Senior Ecologist Hr 149.50 2 299

Passarella Ecologist Hr 104.65 8 837.2

Passarella Design/GIS Hr 89.70 8 717.6

Passarella Administrative Hr 71.76 2 143.52

Total 2577.32

Postage

Printing

Overnight Travel

(if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Total Subtask 2.7 Mangrove Trimming Permit Review

$2577.32

Subtask 3: 30% documents Description: Plans completed to 30%.

Deliverable: Consultant shall deliver 30% Plans in PDF and AutoCad format via email to the District Project Manager including:

Cover Sheet Survey Existing Conditions Plans prepared to 30% with a Site Plan including new fence, revised turn around and parking and proposed stormwater management facilities.

Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:

Subtask 3 – 30% Plans

Firm Name Position Classification

Hour ly

Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 12 $1740.00

Principal in Charge 195 2 $390.00 Registered Professional Engineer

145 10 $1450.00

Registered Engineer Intern 115 16 $1840.00

Senior Engineering Designer 100 38 $3800.00

Engineering Technician 80 54 $4320.00

Clerical 55 2 $110.00

Total $13650.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Total Subtask 3 30% Plans $13650.00

Subtask 4: 60% documents Description: Plans completed to 60%.

Deliverable: Consultant shall deliver 60% Plans in PDF and AutoCad format via email to the District Project Manager including:

Cover Sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plans & Details Fence plans and details General Notes Specifications

Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:

Subtask 4 – 60% Plans

Firm Name Position Classification

Hour ly

Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 18 $2610.00

Principal in Charge 195 2 $390.00 Registered Professional Engineer

145 10 $1450.00

Registered Engineer Intern 115 15 $1725.00

Senior Engineering Designer 100 39 $3900.00

Engineering Technician 80 42 $3360.00

Clerical 55 5 $275.00

Total $13710.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Total Subtask 4 60% Plans $13710.00

Subtask 5: Permitting A – Permit Applications, Description: Consultant will submit permit applications for the County and State - Southwest Florida Water Management District and Coastal Construction Control Line (CCL) permits for site improvements as needed for construction approvals..

Deliverable: Consultant shall deliver five sets of permit applications B – Permit Approvals, Description Consultant will respond to regulatory requests for additional information through approval.

Deliverable: Consultant will provide PDF’s via email to the BDC the completed permits required for construction. The selected contractor will be responsible for the building permit if required.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 5A Permit Applications

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 6 $870.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer 100 24 $2400.00

Engineering Technician 80 33 $2640.00

Clerical 55 2 $110.00

Total $8005.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Reimbursable Cost:

Postage

Printing

County Permits Estimate $1000.00

SFWMD Exemption $100.00

Reimbursable Total Cost $1100.00

Subtask 5B Permit Approvals

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290 Registered Professional Engineer 145 1 $145.00

Registered Engineer Intern 115 2 $230.00

Senior Engineering Designer 100 2 $200.00

Engineering Technician 80 4 $320.00

Clerical 55 1 $55.00

Total $1240.00

Total for Subtask 5 Permits

$10345.00

Subtask 6: 100% documents Description: Plans completed to 100%.

Deliverable: Consultant shall deliver two set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Cover Sheet Survey

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Existing Conditions Best Management Plan Demolition Plan Site & Grading Plans & Details Fence plans and details General Notes Specifications Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:

Subtask 6 - 100 % Plans

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Principal in Charge 195 2.0 $390.00 Registered Professional Engineer 145 6 $870.00

Registered Engineer Intern 115 10 $1150.00

Senior Engineering Designer 100 26 $2600.00

Engineering Technician 80 36 $2880.00

Clerical 55 4 $220.00

Total $9270.00

Reimbursable Cost:

Postage 1 Fed-x at $35 35 Printing 20 sheets @ $2.30 per 46 sheet one set Overnight Travel Not anticipated (if applicable) Reimbursable Total $81.00 Cost

Total for Subtask 6 100% Plans

$9351.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Subtask 7: Construction Administration Subtask 7a: Bidding Assistance Description: Consultant will attend one pre-bid meeting and respond to bidders’ questions and provide clarifications during bidding.

Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 7a - Bidding assistance Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Clerical 55 1 $55.00

Total $1580.00

Reimbursable Cost:

Postage Not anticipated

Printing Not anticipated

Overnight Travel Not anticipated (if applicable) Mileage ($0.445 per Not anticipated mile)

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Reimbursable Total Cost

$0.00

Total for Subtask 7a $1580.00

Subtask 7b: Attend Pre-Construction Meeting Description: WEC staff will attend one pre-construction meeting on site, respond to questions and prepare minutes.

Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 7b - Pre-construction Mtg

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Senior Engineering Designer

100 4 $400.00

Engineering Technician 80 4 $320.00

Total $1300.00

Reimbursable Cost:

Postage Not anticipated

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

Not anticipated

Not anticipated

$0

$0.00

Total Subtask 7b $1300.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

December 20, 2022 - Rev 4 - 04/07/23 Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Subtask 7c: Review Contractor submittals

Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.

Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 7c - Submittal Review

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Registered Engineer Intern

115 8 $920.00

Senior Engineering Designer

100 2 $200.00

Engineering Technician

80 2 $160.00

Clerical 55 1 $55.00

Total $1625.00

Reimbursable Cost:

Postage Not anticipated (all deliverables in digital form only) Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile)

Not anticipated (all deliverables in digital form only) Not anticipated

Not anticipated

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Reimbursable Total Cost

$0.00

Total Subtask 7c - Submittals

$1625.00

Subtask 7d: Assistance during construction (3 Months)

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Deliverable: Correspondence with Contractor and regulatory agencies provided via

PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 7d

Firm Name Position Classification Hourly Rate

Ho urs

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 4 $400.00

Clerical 55 1 $55.00

Total $2125.00

Reimbursable Cost:

Postage Not anticipated

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Printing

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Not anticipated (all deliverables in digital form only) Not anticipated

Not anticipated

$0.00

Total Subtask 7d $2125.00

Subtask 7e: Substantial Completion Walk-Through w/Punchlist Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.

Deliverable: WEC will provide comments and input on punch list within one (1) day of Substantial Completion inspection.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 7e - Substantial

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 1 $100.00

Engineering Technician 80 4 $320.00

Total $1800.00

Postage Not anticipated

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

$0.00

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

Not anticipated

Not anticipated

$0.00

$0.00

Total Subtask 7e $1800.00

Subtask 7f: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion inspection of the site with WEC representative attending the Final Completion inspection.

Deliverable: WEC will prepare final certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask7f - Final

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Prroject Manager 145 4 $580.00

Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer

100 4 $400.00

Engineering Technician 80 8 $640.00

Clerical 55 1 $55.00

Total $2885.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

$0.00

Total Subtask 7f $2885.00

Project Schedule:

Activity Duration (Calendar Days) Days from Execution

Subtask 1 Survey 60 60

Subtask 2.1 FLUCFCS 60 60

Subtask 2.2 Listed Species 60 60

Subtask 2.3 Tortoise Survey 60 60

Subtask 2.4 Tortoise Relocation Permit

90 150

Subtask 2.6 Mangrove Trimming Permit application

60 120

Subtask 2.7 Mangrove trimming review

30 150

Subtask 3: 30% plans 60 - includes 14 days for Client review

Subtask 4: 60% plans 30 - includes 14 days for Client review

Subtask 5A: Permit applications excluding 2.4 & 2.6 above

30 – includes 14 days for Client review

Subtask 5B: Permit approvals 180 – includes 14 days for Client review

Subtask 6: 100% plans 30 – includes response for additional information

Subtask 2.5 Tortoise Relocation 30 360

Subtask’s 7a - 7f 240

Summary of Fees:

Subtask Subtask Fixed

Price Cost Subtask Reimbursable

Subtask 1 Survey $4806.20 $0.00

Subtask 2.1 FLUCFCS $1758.06 $0.00

Subtask 2.2 Listed Species $2625.16 $0.00

Mr. Terry McCullum Stump Pass Parking Modifications Design & Permitting

CN 230

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 2.3 Gopher Tortoise Survey

$2236.46 $0.00

Subtask 2.4 Gopher Tortoise Relocation Permit

$6147.32 $223.00

Subtask 2.5 Gopher Tortoise Relocation

$4281.56 $12000.00

Subtask 2.6 Mangrove Permit $4730.12 $0.00

Subtask 2.7 Mangrove Permit Decision

$2577.32 0

Subtask 3: 30% plans $13650.00 0.00

Subtask 4: 60% plans $13710.00 $0.00

Subtask 5A: Permit applications excluding 2.4 & 2.6 above

$8005.00 $1100.00

Subtask 5B: Permit approvals $1240.00 $0.00

Subtask 6: 100% plans $9270.00 $81.00

Total Design & Permitting $88441.20 $75037.20 $13404.00

Subtask 7a: Assistance during bidding

$1580.00 $0.00

Subtask 7b: Attend Pre-Con Mtg $1300.00 $0.00

Subtask 7c: Review Submittals $1625.00 $0.00

Subtask 7d: Assistance during Construction - 3 Months

$2125.00 $0.00

Subtask 7e: Substantial Completion Walk-Through w/ Punchlist

$1800.00 $0.00

Subtask 7f: Final Completion w/ Certification

$2885.00 $0.00

Subtotal Construction Services $11315.00 $11315.00 $0.00

Total Fixed Price $86352.20

Total Reimbursable Cost $13404.00

Total Overall Cost $99756.20

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

File details come from the government source that posted it. Updated .